NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-21231
Frederick R. Blackwell, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Burlington Northern Inc.
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when, on April 9, 1974; Section
Foreman David Simmons was assigned to operate Jordan Spreader-Ditcher No.
SP&S X4 (System File P-P-191C/MW-84(m)-1 6/6/74).
(2) Machine Operator L. Schuh and Machine Operator Helper J. Eager
each be allowed pay at their respective straight-time rates for an equal
proportionate share of the total hours worked by Foreman Simmons in performing
the work described in (1) above.
OPINION OF BOARD: The Organization alleges that the Claimants ,'_achine
Operator Schuh and Machine Operator Helper Xoer) are
entitled to pro rata compensation for proportionate shares of work performed
in violation of Rules 5 G. and 55 N. of the Agreement, in that Section Foreman David .Simmons operat
near Klickitat, Washington, on April 9, 1974. The Carrier opposes the claim
on the ground that Foreman Simmons was assigned to operate the Jordan Spreader
because there was urgent need to use the Spreader and because the foreman was
working at the point of need. The Carrier says further that the situation
presented a temporary one-day vacancy and that the use of Foreman Simmons to
fill the vacancy was proper under Rules 19 A. and 44. The Carrier also asserts
that the Claimants should not be awarded
compensation b
ec&se they were on
duty and under pay on the claim date and in addition were not.avilable to -.
operate the Spreader since they were 34 miles away from the point where the
Spreader work was performed.
Claimant Machine Operator Schuh and Claimant Machine Operator Helper
Hager hold seniority within the Roadway Equipment Sub-Department (Rule 5 G.).
Section Foreman Simmons holds seniority in the Track Sub-Department (Rule 5
D.), and does not hold seniority in the Roadway Equipment Sub-Department. Rule
5 G. makes provision for seniority rosters in the Roadway Equipment Sub-Department for all operators
machines. The Jordan Spreader is listed in Rule 5 G. as a Group 4 Machine.
Rule 55 N. provides that a Machine Operator is an "employe qualified and assigned
to the operation of machines classified as groups 1, 2, 3, and 4 in Rule 5."
Rule 5 G. clearly and specifically refers to the Jordan Spreader as
one of the Group 4 machines within the Roadway Equipment Sub-Department and
Rule 55 N. refers to a Machine Operator as the employe who operates the
machines classified by groups in Rule 5 G. Thus, as between the Claimants who
I
i
I
i
Award Number 21.340 Page 2
Docket Number MW-21231
hold a seniority in the Roadway Equipment Sub-Department and Foreman Simmons
who does not hold seniority in such Sub-Department, Rules 5 G. and 55 N. in
the instant record establish a prima facie case that the claimants were
entitled to perform the disputed work. The Carrier's rebuttal of this prima
facie case centers on Rules 19 A. and 44. Rule 19 A. provides, inter alia,
that in filing a temporary vacancy, a "preference will be given to the senior
qualified employe who is not assigned in the rank in which the vacancy occurs
and who has on file a written request to fill such vacancy." Rule 44, the
Composite Service Rule, provides that an employe temporarily assigned to a
position paying a higher rate of pay, shall be paid the higher rate of such
position. Neither of these rules grants authority, either expressly or
impliedly, for the Carrier to remove the work in question in this dispute
from the Roadway Equipment Sub-Department for the purpose of having such work
performed by a Foreman in the Track Sub-Department who held no seniority in
the .Roadway Equipment Sub-Department. It is true that the Carrier may have
had to comply with Rule 44 in compensating Foreman Simmons for his work on
the Jordan Spreader, but mere compliance with this rule in respect to the
Foreman has no significance in determining the rights of the Claimants.
Accordingly, the claim is not negated by Rules 19 A. and 44. Further, the
claim is not negated by the Carrier°s reference to the fact that the Claimants
were working elsewhere when the need to use the spreader arose. This reference
is but a conclusionary statement, and it has no tendency to prcve that the work
involving the Spreader could not have been scheduled for performance by the
Claimants.
In view of the foregoing, and on the whole record, it is concluded
that the prima facie case in support of the claim has not been rebutted by
the Carrier and that the claim is meritorious under Rules 5 G. and 55 N. For
a consistent ruling in a similar case involving these same parties, see Award
No. 20892. With regard to compensation, numerous prior authorities have held
that an award of compensation is appropriate for lost work opportunities notwithstanding that the pa
of the violation. Award No. 19924. The claim will therefore be subtained
and each Claimant shall be compensated at his respective pro rata rate for an
equal proportionate share of the total hours worked by Foreman Simmons on
the claim date..
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved June 21, 1934;
I
Award Number 21340 Page 3
Docket Number MW-21231
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
That the. Agreement was violated in accordance with the Opinion.
A W A R D
Claim sustained as per Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST: ~ ~ ~_,r/
Executive Secretary
Dated at Chicago, Illinois, this 16th day of December 1976.