NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number SG-21260
Dana E. Eischen, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(The Washington Terminal Company
STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood of
Railroad Signalmen on The Washington Terminal Company:
On behalf of signal employees C. S. Rhodes, A. L. Watkins, M. D.
Hawley, J. A. Payne, B. J. Lucas, C. A. Dent, E. J. Lang, and E. F. Horney,
Jr,, for compensation at the punitive rate of their respective positions
for time consumed by Foley Electrical Company employees in performing work
covered by the Signalmen's Agreement on May 4, 6, 7, 9, 13, 14, 15, 16, 17
and 20, 1974, this to be divided equally between these signal employees.
ff-arrier's file: Claim
BRS-74-17
OPINION OF BOARD: This case involves alleged Scope Rule violations when
certain work in connection with the relocation and
installation of a temporary lighting system, as part of the overall
construction of the National Visitor Center (NVC) on the site of Union
Station in Washington, D. C., was performed by employes of Foley Electrical
Company rather than by Carrier's Signal employes covered by the Agreement.
The NVC was created pursuant to Act of Congress (P.L. 90-264) whereby the
Secretary of Interior contracted in March 1972 with the corporate owners
of Union Station to renovate and improve that facility for use by visitors
to the Nation's Capital. In February 1973 a general contractor, George
Hyman Construction Company, was retained to furnish all services in connection with the necessary al
letter dated March 7, 1973 Carrier advised the Organization that construction commencement wa
"The project will include renovation of the existing railroad
station into a Visitor Center complete with a motion picture
theatre. Behind the station and over the top of the existing
tracks, a parking garage will be built; behind that, roughly
parallel to "H" Street, N.W., a new passenger terminal will
be constructed. As information in connection with the project,
enclosed is a booklet entitled 'Status II - National Visitor
Center.'
The major projects are all of such magnitude that Terminal
employees could not adequately handle them. Nor do our
employees possess the required skills to undertake such a
project. Furthermore, it would not be practicable to have
the work subdivided to determine whether certain portions of
it could possibly be handled by Terminal employees.
Award Number 21409 Page 2
Docket Number SG-21260
"It is anticipated that the position of employees
represented by your organization will not be worsened
during the construction period. In this connection,
we are willing to consider retention of existing forces
during the period of construction provided your organization will agree to avoidance of contracting
in connection with this project.
While we feel that from a claim-liability standpoint that
such agreement is not mandatory under the circumstances
involved, we believe it most desirable and in the best
interest of all concerned to obtain such an agreement.
Accordingly, for the purpose of supplying additional
details and receiving questions, we invite your attendance
at a conference tentatively scheduled for 2 p.m., Monday,
march 26, 1973."
Meetings were held and on April 18, 1973 Carrier sent to the Organization
a proposed Letter Agreement reading in pertinent part as follows:
"As explained in conference, this project could not
adequately be handled by Washington Terminal employees
due to the required skills, the available force and time
allotted for completion.
It was agreed that this project, covered by Public Law
90-264 dated March 12, 1968, may be contracted out, and
during the period while contractors' forces are building
the new passenger terminal facility and for six months
after its completion, there will be no reduction in the
number of Washington
Terminal
employees represented by
your organization. During this period, vacancies occurring
because of death, retirement, resignation, etc., will be
filled promptly.
If you concur, please affix your signature in the space
provided below and return the original to Mr. Owen, Director
of Labor Relations.
Very truly yours.
C. W. SHAW, JR. s
Manager"
This proposed agreement was not executed by the Organization. Shortly
thereafter, construction of the NVC began and Foley Electrical Company
was awarded the electrical sub-contract.
Award Number 21409 Page
3
Docket Number
SG-21260
By letters dated May
23, 1974
the Organization on behalf of
named Claimants submitted claims reading in pertinent part as follows:
°l. The Washington Terminal Company contracted to
Foley Electrical Company work covered under the
Signalman's scope rule consisting of furnishing
120
volt AC energy to signal. location which will
feed track circuits in the station area.
2. The Washington Terminal Company contracted to Foley
Electrical Company work covered under the Signalman's
scope rule consisting of installing telephone lines
and pipe in the station area.
3.
The Washinton Terminal Company contracted to Foley
Electrical Company work consisting of relocating
and installing train starting light systems on
tracks in the station area ...."
It should be noted that the third claim supra listed specific claim dates
of May
4, 6, 7, 9, 13, 14, 15, 16, 17
and 20,
1974
but also stated: "This
claim is to be on a continuous basis until such violation is corrected."
The other listed claims (1 and 2) specified no claim dates at all. On
June 10,
1974
Carrier's Engineer Roadways, Signal and
Communications
denied
all three claims as follows:
"All work complained of in the above three claims is directly
connected with the National Visitor Project.
As was explained to you in conference held April
2, 1973,
and later confirmed in letter of April
18, 1973,
the
National Visitor Center Project, which is covered by the
National Visitors Center Facilities Act of
1968
(Public
Law
90-264),
shall include, but not be limited to,
demolition of umbrellas over station platforms; alterations
of existing tracks, catenary, signal, electrical, and
communication systems, and air, steam and water lines;
construction of a parking garage structure; construction
of a passenger terminal facility and all component parts
incidental thereto; and renovation of the existing station
as planned for a National Visitor Center. The entire project
is expected to be completed in approximately 2 years at a
cost of about
$21,000,000.
As was further explained, this project could not adequately
be handled by Washington Terminal, employees due to the
required skills, the available force and time allotted
for completion.
Award N=ber 21409 Page 4
Docket Number SG-21260
'"Furthermore, Claims No. 1 and No. 2 are considered vague
and indefinite in that no dates of occurrence are shown
therein.
In view of the aforementioned, the claims are hereby
denied."
Thereafter, the Organization appealed the denial to Carrier's
Manager, in a letter of June 21,
1974
reading in pertinent part as follows:
"Please consider this an appeal of Mr. M. J. Rose's,
Engineer Roadway, Signal and Comm»nication, denial
of our claim of May 23,
1974.
Please consider this a claim for the members of The
Brotherhood of Railroad Signalman because The Washington
Terminal Company violated the current Signalman's
agreement, in particular the scope rule when the Company
unilaterally assigned Signalman's work to other than
Signal Department employees. This claim to be on a
continuous basis until such violation is corrected.
The Washington Terminal Company contracted to Foley
Electrical Company work consisting of relocating and
installing train starting light systems on tracks in
the station area on the following dates.
In Mr. M. J. Rose's denial he states, 'This project could
not adequately be handled by Washington Terminal employees
due to the required skills, the available force and time
allotted for completion.'
We feel that the members of The Brotherhood of Railroad
Signalman do possess the required skills and the available
force could complete the work in the allotted time
economically.
Mr. M. J. Rose also states, 'Furthermore, Claims No. 1
and No. 2 are considered vague and indefinite in that no
dates of occurrence are shown therein.'
In our claim for the starting lights in the station area
the schedule of dates, number of employees etc. covers
claim No. 1 and No. 2 as these electricians verformed all
of the work outlined in our claims on the dates listed."
By letter dated August 26,
1974
Carrier denied the claim again as follows:
Award Number 21409 page
Docket Number SG-21260
"THE WASHINGTON =MU COMPANY
Union Station Washington, D. C. 20002
August 26,
1974
Mr. William R. Matthews . Jr.
General Chairman, Brotherhood of
`~+ ~Railroad S ignalmen
354Herbert Street
Broyhill Crest
Annandale, Virginia 22003
Re: Claim
MS-74-1
Dear Mr. Matthews:
This refers to your June 21,
1974
appeal of
subject claim filed in behalf of various Signalmen
for various dates in May
1974
for a day's pay at the
punitive rate of their respective positions for the
time consumed by the Contractors (Foley Electrical
Compaqy) performing work of relocating and installing
train starting light systems.
In our July
18, 1974
conference, the position of
the parties remained the same as reflected in the claim
and in Mr. Rose's June 10,
1974
denial. Mr. Rose's
denial, by reference, is incorporated herein and made
a part of this decision.
Your appeal is accordingly denied.
Very truly yours
C. W. SHAW, JR. /s/
Manager
cc: Mr. M. J. Rose"
Review of the record of handling reveals a number of procedural
irregularities and inadequacies by both parties. In the first place, only
one of the three original claims of May 23,
1974
(that numbered supra as
"3") properly is before our Board for review. So far as we can see by the
record, that claim was appealed to the Manager, denied by him and thereupon
submitted to our Board for adjudication. Neither of the other claims,
to wit " ....furmishing 120 volt AC energy ...." and "installing telephone
lines and pipe" were handled to impasse on the property and may not be
determined by us. Further, the one remaining claim for "relocating and
installing train starting light systems on tracks in the station area"
alleges violations on specific dates beginning may
4
and. ending Mayy 20,
1974:
and there is not a bit of evidence to support the organization's
characterization of a "continuing claim".
Award Number 21409 page
6
Docket Number
SG-21260
Turning to
the claim properly before us, we find that Carrier's
substantive position on the property consisted solely of the following:
" ....that project could not adequately be handled by Washington Terminal
employees due to the required skills, the available force and time allotted
for completion." There is no dispute, and indeed Carrier conceded on the
record, that the work in question comes under the Scope Rules of the
Signa7men's Agreement. Thus the issue before us is joined when we confine
our view, as we must, to the arguments raised on the property. Several
other more elaborate theories were raised de novo in Carrier's ex parte
submission and advanced by able advocacy in argument before our Hoard
but none of the voluminous material relative to ownership, dominion and
control may be considered by us because it was never aired on the property.
For the same reason the myriad Awards on these subjects are irrelevant
to the issue before us. Rather, the basic principles determinative of
this case are found in our early Award
5563
wherein we stated as follows:
"First, as a general rule the Carrier may not contract
out work covered by its collective bargaining agreements.
Second, work may be contracted out when special skills,
equipment or materials are required, or when the work is
unusual or novel in character or involves a considerable
undertaking. (See Awards
757, 2338, 2465, 3206, 4712,
4776, 5028, 5151
and
5304.)
Third, the work contracted out is to be considered as a
whole and may not be subdivided for the purpose of
determining whether some of it could be performed by
the employees of the Carrier. (See Awards
3206, 4776,
495+
and
5304. )
Fourth, the burden of proof is on the Carrier to show by
factual evidence that its decision to contract out work
is justified under the circumstances. (See Awards
2338,
4671
and
5304.)"
Adverting to the principles clearly enunciated in Award
5563
we
see that Carrier has the burden of proving by factual evidence justification
for contracting out the work concededly covered by the Scope Rule: to wit
"the relocating and installing train starting light systems on tracks in
the station area." Review of the record shows that Carrier has failed to
carry this evidentiary burden. Mere assertions are not "factual evidence"
and Carrier has offered nothing more than assertions that the overall
project was an unusual, novel and considerable undertaking costing several
millions of dollars. Moreover, Carrier's assertions about the magnitude
and cost of the overall project are irrelevant to the claimed violation
of the Signalmen's Scope Rule by subcontracting specifically identified
electrical work. (Emphasis added) The focus of this dispute an o
Carrier's evidentiary burden must be that electrical work and Carrier
Award Number 21409 Page 7
Docket Number SG-21260
offered not one scintilla of factual evidence on the property to justify
its decision in terms of the mitigating circumstances cited in Award 5563.
The work in question is covered by the Scope Rule, Carrier has failed to
justify the contracting out and there can be no doubt that the Agreement
thereby was violated.
We turn finally to the question of appropriate damages for the
proven violation. In processing the case on the property, the Organization
alleged a violation on each of 10 days and sought that the "Company now
be required to compensate the Signal Department Employees listed, at the
punitive rate of their respective positions for the time consumed by the
Contractors performing work covered by the Signalmen's Agreement. This
compensation to be divided equally between the listed Signal Department
Employees." The Carrier before our Board presented vigorous argument
that the employes were occupied in their regular work throughout the claim
period and, in any event, the punitive rate is not justified. As with so
much of Carrier's position in this case, however, the arguments were raised
belatedly at this appellate level but not on the property and therefore
are blocked from our view. %Nonetheless
we
rtre-guided by the basic principle
that the Organization bears the burden of making a prima facie case on
every material aspect of its claim, including the ad damauim. portion. As
we analyze this record the Organization has made no showing whatever that
damages at the punitive rate are warranted herein. Moreover, the Organization has made no evidentiar
Contractor's performing work covered by the Agreement." Because of this
evidentiary void we have no way of knowing whether each day's violation
was for a full 8-hour day or some portion thereof. Since the burden was
on the Organization to provide information on damages and it failed to do
so we shall sustain the claim only to the extent of one call for each of
the ten days i.e. two hours and forty minutes at the strai t time rate
for Maintainers prevailing at the time of the violation. Emphasis added)
This sum shall be divided equally among the eight named Claimants.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
That the Agreement was violated.
Award Number 21409 ?age
8
Docket Number SG-21260
A W A R D
Claim sustained but only to the extent indicated in the Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
dal.
Aoxgure
Executive Secretary
Dated at Chicago, Illinois, this 18th day of February 1977.