NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-21311
James C. McBrearty, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISRJTE:
(The Washington Terminal Company
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when, without an agreement in
writing between the Manager and the General Chairman as required
by paragraph (c) of the Scope rule, it contracted out the work of painting
the 'West Basement' of the depot at Washington, D. C. on March 23 and 24,
1974 (System File MW-74-2).
(2) Painters C. Ellsmore and L. H. Howard each be allowed pay at their
respective time and one-half rate for an equal proportionate share
of the total number of man-hours consumed in performing the work referred
to in part (1) hereof.
OPINION OF BOARD: The basic facts in this case are not in dispute. On
Monday, March 18, 1974, Carrier assigned Claimant C.
Ellsmore, B&B Painter, to the task of painting the walls in an area of
Carrier's Terminal between the Amtrak Commissary and the Southern Railway
Commissary. On Tuesday, March 19, 1974, Claimant Ellsmore was taken off
this assignment because of a lack of material to complete it. Subsequently,
on Saturday and Sunday, March 23 and 24, 1974, which were the assigned days
off of both claimants, outside contract painters completed the painting project which had been begun
A claim was initiated on behalf of B&B Painters Ellsmore and Howard
for payment at the time and one-half rate for an amount of time equal to the
number of man-hours consumed by the contract painters. In the handling of the
case on the property, Petitioner alleged that 24 man-hours were consumed by
the contract painters. Carrier neither affirmed nor denied this contention.
The claim is premised on the specific language of the Scope Rule which
provides in pertinent part that:
Work covered by this Agreement shall not be contracted
except by Agreement, in writing, between the Manager
and General Chairman, except in emergencies.
Award Number 21482
Docket Number
MW-21371
Page
2
There is no contention by either party that an emergency existed.
There is no contention by either party which denies that the work in question
is "covered by this Agreement." Rather, Carrier defends their denial of this
claim on the basis that they knew nothing of the employment of contract
painters inasmuch as the contract was made by Amtrak without Carrier's knowledge
or concurrence.
Based on the factual situation which exists in this particular case,
and without extending this decision to any other similar condition, it is our
conclusion that Carrier has a liability which it cannot avoid by the defenses
employed herein. However, the liability does not extend to both of the named
Claimants. As previously noted, Claimant Ellsmore was used to begin the work.
If he had not run out of material on Tuesday, March
19, 1974,
it is reasonable
to conclude that he would have completed the assignment within his normal work
week. Therefore, Claimant Ellsmore should be allowed payment of twenty-four
(24)
hours at the pro rata rate of pay. The claim on behalf of Claimant Howard
is denied.
FINDINGS: The Third Division of the Adjustment Board, upon the
whole record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes wit
the Railway Labor Act, as approved June
21, 1934;
That this Division , of the Adjustment Board has _,Jp
X,jsdiction over the dispute involved herein; and
That the Agreement was violated.
A W A R D
_7 7
P?\ 9
0 u
4
.... .
Claim sustained to the extent indicated
V
n.
ATTEST:
Executive Secretary
Dated at Chicago, Illinois, this 31st day of March 1977.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division