NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-21232
Walter C. Wallace, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Norfolk and Western Railway Company (Lake Region)
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it used a roundhouse
foreman and one other roundhouse employe to construct a small building at
Bellevue, Ohio for use as an office by the roundhouse foreman (System File
MW-BVE-74-4).
(2) B&B Foreman L. D. Wise and B&B Carpenter L. E. Weaver each
be allowed 24 hours' pay at their respective straight-time rates and 12
hours at their respective time and one-half rates because of the violation
described above.
OPINION OF BOARD: The central question of this case involves an inter
pretation of Rule 52 (b) of the applicable agreement
which provides in pertinent part:
"All work of constructing, maintaining, repairing
and dismantling buildings, lodges, turntables,
water tanks, walks, platforms, highway crossings
and other similar structures, built of brick,
stone, concrete, wood or steel, and appurtenances
thereto, shall be performed by ~ to ees of the
Bridge and Building Devartment ..."(emphasis added)
The question is in dispute presumably because the object
made does not fit precisely within the rule definition. It is undisputed that it was fabricated by M
small wind break or work booth made of wood and metal to permit a foreman
to gain protection inside the roundhouse from wind and drafts caused by
the opening of doors for the entrance and exit of locomotives. The booth
is free standing in that it is not attached to the basic roundhouse structure and, presumably, it co
It does include electrical and telephone connections however. Within the
structure there is a desk, shelf, chair and clock permitting the occupant
to utilize it as a small office. The dimensions are four feet wide by
five feet long and seven feet high. In summer time the door is detached
and it is reinstalled in winter weather.
Award Number 21592 Page 2
Docket Number W-21232
Neither the use of this booth, nor the need for it, nor
appointments inside are controlling of the question before us.
The exceptions contemplated by the rule (not quoted above) are
conceded to be inapplicable. In addition, we do not believe we may
look to past practice or custom until we are satisfies) the -plain
wording of the definition under the rule does not cover the work in
question. See Award 17569 (Robman).
It is the Carrier's contention, to the contrary, that the
petitioner must prove by a preponderance of the evidence that the
work involved must have been historically, customarily and usually
performed exclusively by he who claims it and cites awards in support thereof. We have reviewed thes
the work reserved to the craft. By its terms Rule 52 (b) contemplates
exclusivity for Bridge and Building employees and unless it can be
said the work is not within the description provided, it would appear
to be their work. See Award 18628 (Bitter). The rule description
employs general terms although a number of specific structures are
listed. Even if we assume this booth cannot be described as a
building, it can be considered covered as an "other similar structure"
and "appurtenance thereto" insofar as it was constructed as a foursided structure with roof, window
electrical and telephone connections and it cannot be claimed it is
completely "free standing". Moreover, it is built of wood or steel,
materials covered by the definition.
We believe the petitioners have met the burden of proof here.
The exchange of correspondence between the parties on the property
served to accomplish two results: (1) described the structure in
question with considerable detail (including photographs); and (2) established that the work had bee
and Building employees. We conclude the structure falls within the
broad definition of Rule 52 (b) and that work is the exclusive work of
the a an ~n3ng emp ees.-I~F-fol16wsac a case
was made. It remained for the. Carrier to develop its counter position
that the work was not the exclusive province of -this.craft. See Award
6063,- The Carrier has
not
met this burden and we must sustain Claim (1).
-- In considering Claim (2) it remains to determine the proper
measure of damages, if any, here. The exchange on the property reflects conflict as to the time invo
of claim, the organization alleged that a total of 72 hours was devoted
to this construction by two men including 24 hours on Saturdays or
Sundays. The remaining 118 hours were acco=lished on days other than
Saturdays and Sundays.
Award Number 21592 Page 3
Docket Number MW-21232
The Carrier argues the measure of damages for a violation
here is the actual loss suffered by the injured party. The Claimants
were not deprived of work during their normal work weeks and on this
basis suffered no actual loss. The Carri·_r also asserts that premium
rates rather than pro rata rates could not be applicable for time not
worked insofar as it would involve the assessment of a penalty. The
Petitioner cites awards that urge that this work was in the nature of
overtime work and as such should be considered a. continuation of the
work being performed. eeole do not reach these arguments in this case.
We are informed that the normal off days of the Claimants,
who are senior Bridge and Building employees, was on Saturday and
Sunday. There is no evidence that the Mechanical Department employees
who performed the work had similar off-days although the work scheduled
produced by the Organization indicates the rate paid on Saturdays and
Sundays is at the time and one half (premium) rate. It follows that
we cannot determine from this record that the work necessarily was
performed or would have been performed by Bridge and Building employees
on premium time at overtime rates.
For this Board to decide the question of the appropriate
remedy it must rely upon the factual showing established on the property
as to the number and quality of hours (premium or non-premium) required
to perform the work. Fere we find only allegations and assertions.
Albeit, these are repeated and even argued, they cannot be considered
evidence within the awards of this Bcard. See Award 21268 (Lieberman);
Award 20218 (Blackurell); and Award 20620 (Sickles). We cannot engage
in speculation or conjecture as a basis for a remedy. It follows that
ore must conclude, on this record, that petitioners have not met their
burden of proof to establish the basis for a money award and Claim (2)
must be denied.
_FINDINGS: The Third Division of the Adjustment Board, upon the whole
record and all the evidence finds and. holds:
That the parties waived oral hearing;
That the Carrier and The Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved June 21, 1934;
Award Number 21592 Page
Docket Number MI-PIP32
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
That the Agreement was violated.
A W A R D
As to Claim (1) sustained.
As to Claim (2) denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
_,/) By Order of Third Division
ATTEST: , f~Iy/~
Mxecutive Secretary
Dated at Chicago, Illinois, this 17th day of June 1977.