(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Southern Railway Company

STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood
of Railroad Signalmen on the Southern Railway
Company et al.:

On behalf of T. R. Riley, Signal Maintainer, Slidell, La., for sixteen (16) hours at his overtime rate as Signal Maintainer account Carrier instructing Electrician Bill White, headquarters New Orleans, La., and Don Feltman, headquarters Meridian, Miss., to load and haul signal material to Tuscaloosa, Ala., on March 11, 1975, to be used by signal employees. Signalmen used wire to repair signal circuits south of Tuscaloosa, Ala., on March 12, 1975. LCarrier's file SG-112/

OPINION OF BOARD: For the reasons set forth in our Award 21635 and with
particular reference to Third Division Awards 10613
and 12188, we deny the claim.





That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and








                            By Order of Third Division


ATTEST: 19· i

        Executive Secretary


Dated at Chicago, Illinois, this 29th day of July 1977.