NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-21411
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Louisville and Nashville Railroad Company
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood
that: ,.,
(1) The Carrier violated the Agreement when, without prior
notice to and/or discussion with General Chairman J. D. Sowders, it
contracted the work of
constructing a
building (No. 6732) at Pascagoula,
Mississippi to outside forces /System File 1-17(24)/E-201-14 E-201/.
(2) B&B Foreman L. E. Harville, Carpenters H. W. Wright,
E. Stinson, E. A. Ward, Carpenter Helpers I. W. Owen and J. W. Pruett
each be allowed pay at their respective straight time rates for 'eight
hours straight time each for April 9 through 12, April 15 through 19,.
April 22 through 26, April 29 through May 3, May 6 through 10, May 13
through 17, May 20 through 24, May 28 through 31 and June 3 through 6,
1974, and continue to be paid as long as contractor Broadmoor Corporation
of Gulfport, Mississippi is allowed to perform work on Building 6732
being contracted at Pascagoula, Mississippi.
OPINION OF BOARD: Carrier concedes it did not give the required notice
that it would sub-contract work out for the
construction of a building; therefore~there is no
question that
there
was a violation of the agreement. '
The question is what to do about the violation.
i
The Carrier argues that the sub-contracting provisions of the
agreement permit the Carrier under Section 2(e) to sub-contract out work
if there are not sufficient laid off employes to draw upon to do the work,
or if there is not enough equipment not otherwise in use to perform the
work; and that, in fact, with respect to the work in issue there were not
sufficient laid off employes to do the work.
i
Thus, the Carrier has a very strong case on the merits
supporting its decision to contract out the work on the new building.
But a National Agreement was violated. Article IV requires
the Carrier to give notice not less than 15 days before it sub-contracts
out work. Thereafter, if the Organization feels it is necessary, it can
i
~4
Award Number 21646 Page 2
ask for a meeting which shall be granted by the Carrier to discuss the
contemplated sub-contracting work. The agreement further provides that I
in the event the parties do not agree whether or not the company is
authorized to contract out the work, each party reserves the rights it
had and the Carrier can go forward with the sub-contracted work. In other
words, in the event of an impasse, the Carrier is free to proceed with
the work and the Organization is free to file a grievance.
In view of the Carrier's failure to give the required notice,
the dispute here is whether or not to grant the claim as the Organization
requests, which is for consequential damages to the extent of the
specific days missed, as identified in the claim, and for all subsequent
time missed; or whether as the cospany argues there is no basis for a
penalty or money award because there was not in fact a loss of work
opportunity for the employes involved.
The Organization relies on recent Awards 19899 (Sickles), in
which full damages were authorized, and 20020 in which damages were
paid on a half claim basis. The Organization concedes that the award
in 20020 in which half the claim was authorized to be paid did not
include any criterion as to how that judgment was reached.
The Carrier argues strongly to the contrary that in the event
there is no showing of loss of work opportunity - even though there is
showing of violation of the agreement - no damages, compensation, penalty,
etc. may be awarded.
Award 18305 (Dugan) was the first in a long line of decisions
supporting this position. Some 28 awards subsequent to the Dugan award
likewise denied damages for violation of Article IV where no pecuniary
loss was shown. These awards involve different referees and it cannot
be said they were inexperienced thereby establishing firm precedent
against damages where there is no loss of work opportunity.
The case however cannot be disposed of so matter-of-factly.
It is true that to award a penalty there must be either a
showing of damage, or it must be shown that the violation was of the
kind that was intended, and did, result in some prejudice to the
employes involved and therefore some injunctive or punitive action
should be taken to prevent the Carrier from doing the same thing in the
future with impunity.
In considering this question it is pertinent to know that
Article IV of the National Agreement of May 17, 1968 was intended to
allay the fears of the Organization about sub-contracting out work and
I
Award Number 21646 Page 3
Docket Number MW-21411
that the requirement to give notice - at least implicitly - was intended
to give the Organization an opportunity to educate the Carrier why the
intended sub-contracting work should not be assigned off the property.
Also, it can be inferred that the Organization by asking for and getting
a meeting in accordance with the notice requirements under Article IV
was educating itself to develop a grievance in the event that the
Carrier ultimately decided to go ahead with the sub-contracting out work.
For these reasons it cannot be said that the notice requirement was a
technical or meaningless requirement even in the event the Carrier - as
here - had reason to be confident that it was authorized to sub-contract.
In defense of the Carrier in this case, however, it may be said that
there does not seem to have been any intent or motive to shortchange
the Organization. Prior and subsequent to this dispute, the Carrier
did give notice about intended sub-contracting work.
The Organization is well aware of the decisions issued under
Article IV, in which compensation was denied where the employes were
employed in their regular jobs and suffered no loss of wages. This
precedent was set in Award 18305 (Dugan) where the "full employment"
concept was established in which damages were denied even upon finding .
a violation of the agreement. But the Organization states that for
over 40 years the question of damages has swung back and forth like a
pendulum in a grandfather's clock. "The pendulum is now on the side of
payment because of lost earning opportunities." Recent Award 19899
(Sickles) and early awards before the National Agreement in Article IV
give comfort to the Organization. In these cases compensation was
awarded for failure to notify or discuss in accordance with the agreement.
The Organization also relies on the decision of the Fourth Circuit Court
of Appeals in Brotherhood of RailroadYSignalmen v. Southern Railroad
Company, 330 F.2d 59, decided May 1,'1967, and the decision in Award
20020 which referred to that decision, in which the court sustained the
principle that loss of work opportunity is a compensable offense.
In Award 19899, Referee Sickles makes the point that in the
line of cases starting with Award 18305 various referees did adopt Dugan's
conclusion of denying damages if full employment was demonstrated, but
such denials were made without significant comment and, quite importantly,
no referee stated or suggested that the Board lacked authority to award
damages.
The Fourth Circuit decision supports the thought that there
is no reason for the division to continue between arbitrators on the
question whether or not damages may be awarded in the event of a
violation of Article IV. Sickles' observation makes sense that the
Board should award damages in each individual case in direct relationship
to the loss of job opportunity and tangible loss of pay, notwithstanding
a "full employment" situation.
i~
Award Number 21646 Page 4
Docket Number ITP-21411
i
The question remains, what happens to the organization's
concern about sub-contracting out work if the Carrier can effectively
disregard the Organization such as by failing to give notice it has
agreed to give under the contract?
A list of successful awards finding such violations of the
sub-contracting agreement would give amminition to the Organization
to open up the contract, in accordance with Section 6 of the Railway
,
Labor Act to require some new provisions with respect to sub-contracting
out; but this is major surgery and is not easy to do. Short of this
remedy, each case under the jurisdiction of this Board must be
considered on its merits.
On this test and in recognition of Carrier's failure to give
notice, it may be found that the Carrier did violate the Agreement but
that it did not do so with bad
intent or
motive. There is erefore no
need to impose a penalty (which could have been impose ' warranted),
particularly as the evidence is clear that the Carrier would have been .
authorized under the Agreement to sub-contract out
construction of
the
building in issue, even if it had given the required notice.
If there were actual damages in this case, the Organization
has the burden to prove them in this or other appropriate forum. It
has not proved such damages in this case.
FINDINGS: The Third Division of the A$justment Board, upon the whole
record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute
are respectively Carrier and Employes within the
meaning of
the Railway _
Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction
over the dispute involved herein; and
That the Carrier violated the Agreement.
Award Number 21646 Page 5
Docket Number MW-21411
I
i
A W A R D
Claim sustained to the extent indicated in the Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
Executive Secretary
Dated at Chicago, Illinois, this 18th day of August 1977.