NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket
Number SG-21772
James F. Scearce,
Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Southern Pacific Transportation Company
( (Pacific Lines)
STATEMENT OF CLAIM: Claims of the General Committee of the Brotherhood
of Railroad Signalmen on the Southern Pacific
Transportation Company:
Claim No. 1: Carrier's file: SIG 152-350
(a) The Southern Pacific Transportation Company (Pacific Lines)
violated
the current
Memorandum of Agreement between the Southern Pacific
Transportation Company (former Pacific Electric Railway Company) and its
employes represented by the Brotherhood of Railroad Signalmen, dated
May 6, 1970 particularly paragraphs 3 and 4.
(b) Mr. G. Bozaan be allowed five and one half hours at the
time and one half rate for January 3, 1975.
Claim No. 2· Carrier's file: SIG 152-351
(a) The Southern Pacific Transportation Company (Pacific Lines)
violated the current Memorandum of Agreement between the Southern Pacific
Transportation Company.(former Pacific Electric Railway Company) and its
employes represented by the Brotherhood of Railroad Signalmen, dated
May 6, 1970, particularly paragraphs 3 and 4.
(b) Mr. G.'Bozaan be allowed six and one half hours at the
time and one half rate for January 7, 1975.
Claim No. 3: Carrier's file: SIG 152-352
(a) The Southern Pacific Transportation Company (Pacific Lines)
violated the current Memorandum of Agreement between the Southern Pacific
Transportation Company (former Pacific Electric Railway Company) and its
employes represented by the Brotherhood of Railroad Signalmen, dated
May 6, 1970, particularly paragraphs 3 and 4.
(b) Mr. J. Olech be allowed four hours at the time and one
half rate for January 8, 1975, and also five hours at the time and one
half rate for January 14, 1975.
Award Number 21858 Page 2
Docket Number SG-21772
OPINION OF BOARD: Carrier maintains four Bonder and Welder crews,
one for each district on the former Pacific Electric
Railroad Property. On the dates of January 3, 7, 8 and 14, 1975, a
regular occupant of a Bonder and Welder crew was absent due to jury duty
and there was no one available holding seniority in the Bonder and Welder
classification to fill this temporary vacancy. Accordingly, in following
a long established practice, Carrier used a Signalman, Mr. Headers, who
was regularly assigned to Signal Gang #3 to fill these vacancies.
There is no dispute concerning Carrier's temporary assignment of Mr.
Meaders to these assignments. The dispute centers on Mr. Meadexis per
forming overtime work along with other members of the Bonder and Welder
crew which was continuous with the regularly assigned hours of the crew.
Claimants herein, members of bonder and welder gangs from adjacent
districts, contend that they should have been called to perform the
overtime work here in question.
In case after case decided by this Board, we have repeatedly
ruled that in order to establish a right to relief sought in the
statement of claim, the Petitioner must firstly cite provisions of the
a
agreement which prohibited Carrier from acting in the manner which
Petitioner challenges and secondlv, the Petitioner must show how
Carrier's action violated the cited provisions of the contract. Unless
there exists a contractual prohibition precluding Carrier from taking
the action disputed, we have no authority under the Railway Labor Act
to find for Petitioner.
In applying these principles to the facts of the instant case,
we can find no provision of the controlling agreement between the parties
which prohibited the action here in dispute. In fact, Signalman Meaders'
performance of overtime with the bonder and welder crew on the claim dates
was in accordance with provisions of the May 6, 1970 Memorandum of Agreement between the parties, wh
"If work on a particular job during regular assigned
hours extends into overtime, crew in whose District
work is being performed will remain on overtime."
Under the peculiar facts and circumstances of this case, we can see no
violation of the controlling agreement and the claim must be dismissed.
FINDINGS: The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds and holds:
That the parties waived oral hearing;
·- 7
Award Number 21858 Page 3
Docket Number SG-21772
That the Carrier and the Employes involved is this dispute
are respectively Carrier and Employes within the meaning of the Railway
Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board-has'jurisdtctioaover the dispute involved herein; and
That the claim be dismissed.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
Executive Secretary
Dated at Chicago, Illinois, this 18th day of January 1978.