(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Missouri Pacific Railroad Company

STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood
of Railroad Signalmen on the Missouri Pacific
Railroad Company:

On behalf of Signal Foreman W. H. Pankey ($1233.48 per month) and Signalman G. Brown ($5.74 per hour), members of Signal Gang #1065, St. Louis, Missouri, for 64 hours each at time and one-half their respective straight time hourly rates, account the Carrier, about the week of October 30, 1974, engaged the services of an outside contractor to dig approximately 149 holes for a signal pole line change, between North Chester, Illinois, and the south end of Reily Lake, Illinois, in violation of the Scope Rule dated September 1, 1968, included in the Scope Rule of the current Agreement dated May 1, 1964.



OPINION OF BOARD: The claim is that Carrier should not have contracted
out the relocation of some four miles of signal
lines, requiring the setting of approximately 149 poles. Some 130 new
poles were used while 19 were salvaged from their previous location.
The Carrier's decision to contract was based on engineering forecast
that the new location would require a power auger and perhaps blasting,
neither of which were within the capability of the signal gang. As it
turned out, the signal crew could probably have handled the job.







        The above is clarified by a September 1, 1968, agreement:


        "Construction and maintenance of communications pole lines, wires and appurtenances.


        "NOTE: The word 'construction' used in the foregoing

        sentence does not deprive the Carrier of the

        right to have other than Carrier forces perform

        the work required in the rehabilitation,

        upgrading and dismantling of existing communica

        tions pole lines, wires and appurtenances, nor

        does it prohibit the contracting of major new

        communication pole line construction, with the

        understanding such action will not result in

        contracting out the signal wires and power lines

        and appurtenances or the furloughing of employes

        subject to the Agreement between the parties hereto."


The issue, therefore, is whether this was construction reserved to the signalmen, or was major new work which could be contracted out. The project was required to make room for a new main track. It consisted of moving the signal lines of the tracks.

A scope agreement, not identical but similar to the above, appears in Award 16337 (Friedman) where "larger installations in connection with new work" could be contracted. We quote from that award:

        "But a fence which replaces an existing fence, and is made of new materials, although on the very site of the old one, is a new fence - even if some of the old fence posts are retained. Similarly, a house built upon the foundation of its burned-out predecessor is a new house, even if some of the plumbing is retained and its function, design and appearance are duplicated. Practically and logically, a new house has been built. At some point it may be difficult to distinguish where repair or minor modification leaves off and new construction begins, but that is no problem in dealing either with a replacement fence or house or the CTC system on this property."


This approach was approved in Award 16523 (Devine) and is equally pertinent here.

Thus, we are constrained to find that the major new work exception applies.
                    Award Number 21867 Page 3

                    Docket Number SG-21680


        FINDINGS: The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds and holds:


        That the parties waived oral hearing;


That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and

        The Agreement was not violated.


                    A W A R D


        Claim denied.


                          NATIONAL RAILROAD ADJUSTMENT BOARD

                          By Order of Third Division


        ATTEST: Executive Secretary


        Dated at Chicago, Illinois, this 31st day of January 1978.