NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number SG-21384
Nicholas H. Zumas, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Robert W. Blanchette, Richard C. Bond
( and John H. McArthur, Trustees of the
( Property of Penn Central Transportation
( Company, Debtor
STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood
of Railroad Signalmen on the Penn Central
Transportation Company (former New York Central Railroad Company-Lines
West of Buffalo):
System Docket
W-58
Southern Region - Southwest Division Case
S-5-74
Carrier violated the current Signalman's Agreement as
amended, when it required and or permitted the Fort Wayne track dep't.
gang assigned to Marion, Indiana to remove a Sperry Car rail found to
be defective in the third week of April 1 from the main track in the
3W track circuit without maintainer setting signal at stop and without
maintainer removing the bonding. Bonding was removed by track forces
in violation of Rule 1 2, 13(1) and title rule of the current agreement.
Violation occured icon Iay 02,
1974.
Carrier now be required to compensate Maintainer R. W. Hartsock
in the amount of 2.7 hours at the overtime rate for his assignment on
May 02,
1974
for denying him the opportunity to perform his regular
assignement.
OPINION OF BOARD: The Organization contends that Carrier violated the
Agreement between the parties when it used track
forces to open and enter into an in-service electrical signal circuit by
breaking signal rail bonding. It is the Organization's position that its
Scope Rule specifically covers "bonding of track for signal and inter
locking purposes", and that work on signal bond wires should only be
performed by employes classified under its agreement.
Award Number
·'18$3
Page 2
Docket Number
SG-21384
The facts and circumstances of this dispute are strikingly
similar to those in Award No.
6
of Public Law Board No.
1442,
between
these same parties. There the Board denied the claim with the
following:
"Findings: 0n some date prior to October
19, 1972,
Carrier began the project of replacing
bolted rail with continuous welded rail over a
75
mile portion of single track territory. The old
rail was removed in the following manner: maintenance of may employees removed the connecting bolts
from the rail joints, removed the spikes and plates
which held the rail to the ties, and then used a
crane to lift out the disconnected sections of rail.
Where there were rail bonds between the sections of
bolted rail, they were left in place by track
forces and were broken by the lifting action of the
crane. Prior to October
19,
Claimant, lead signal
maintainer had been following the welded rail gang
in his area and had been present when the rail was
removed and the bonds broken. It does not appear
that he performed arty function in connection with
the bond breaking other than to be present. 0n
the 19th, he was instructed not to follow the gang
but to perform other work on his section. The
claim is that when welded rail gang broke the bonds
without the presence of a. signalman, they violated
the scope rule of the Signalman's Agreement.
The Scope Rule provides for coverage of all
employees of the Signal Department engaged.in construction, installation, inspection, testing,
maintenance and repair of, among other things,
'bonding track for signal and interlocking purposes.'
The question is whether this language covers the
breaking of the bond wire in the track removal
operation under the circumstances of this case.
Various awards of the NRAB Third Division have
considered similar questions on other properties and
have reached different results depending on the
particular factual circumstances. See, e. g., Awards
8069, 20526, 20536, 20555.
Award Number
21883
Page
3
Docket Number
SG-21384
~~Under the circumstances of this case, we think
that there was no scope rule violation. The
track involved had been taken out of service and
there were no signal functions remaining in
connection with the removal and scrapping of the
bolted rail. Whatever signal adjustments had to
be made in connection with road crossing signals
affected by the breaking of the bonds had
obviously already been made by the time of the
instant claim. There is no contention that such
adjustments or any work in connection with
necessary rebonding after the welded rail was
installed, was done by other than signal employees.
It does not appear from the record that if Claimant
had been present on the dates in question, he would
have performed any function in connection with
breaking the bonds, or that the breaking of the
bonds would have been accomplished in any different
manner than it was accomplished in his absence.
Under the particular circumstances of this
case, we conclude that neither the Scope Rule nor
cited awards support the claim, and we therefore
will deny it."
On the basis of Award No.
6
of Public Law Board No.
1442,
between these parties, we shall deny the claim.
FINDINGS: The Third Division of the Adjustment Board, upon the whale
record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute
are respectively Carrier and Employes within the meaning of the Railway
Labor Act, as approved June 21,
1934;
That this Division of the Adjustment Board has jurisdiction
over the dispute involved herein; and
The Agreement was not violated.
Award Number 21883 Page 4
Docket Number SG-21384
A W A R U
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST. ~~
P,/~
Dated at Chicago, Illinois, this 31st day of January 1978.