NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number SG-21710
Irwin M. Lieberman, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Louisville and Nashville Railroad Company
STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood
of Railroad Signalmen on the Louisville and
Nashville Railroad Company:
On behalf of Signalmen C. C. Dennis and B. R. Harrison,
headquarters Signal Gang 413, Boyles Yard, Alabama, for 52 hours each
at their respective overtime rates account Mr. G. L. Tanner, SupervisorMaintenance on the Southern R
Signal Maintainer G. D. Jacobs performing work involving the wiring
and circuit changes at Boyles Yard Office Relay Room during the month
of September, 1974, in conjunction with construction projects for
`Five Mile Creek' and 'Bowl' Interlockings. (8 hours each on September
18, 19, 24, 25 and 26, and 4 hours each on September 20, 23 and 27, 1974)
/Carrier's file: G-304-12, G-304/
OPINION OF BOARD: The dispute herein involves the work of making
certain circuit changes at Carrier's Boyles Yard
Office Relay Room during September 1974. The admitted facts, which are
at the heart of the dispute, are that the Supervisor Maintenance, not
included as a covered employe in the applicable Agreement, read the
blue prints and supervised the wiring of the changes according to those
plans. Petitioner argues that this was work which should have been
performed by
a covered employe and Carrier disagrees.
An examination of the record indicates that there is no
evidence of the Supervisor going beyond the normal scope of supervisory
functions in his activities. Checking blue prints and the work for
accuracy cannot be construed to be "work" within the terms of the
Agreement. Carrier submitted evidence of supervisory employes
functioning in a similar manner traditionally and historically;
Petitioner did not submit any contrary material.
The record is devoid of evidence in support of Petitioner's
position and neither is there any apparent rule support. It must be
concluded that the Supervisor in this instance was performing a normal
Award Number 21911 Page 2
Docket Number SG-21710
supervisory function to see that the work was properly performed in
accordance with traditional practice on the property. Accordingly,
the Claim must be denied.
FINDINGS: The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute
are respectively Carrier and Employes within the meaning of the Railway
Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction
over the dispute involved herein; and
_7.
That the Agreement was not violated.
A W A R D
L~!~ 1_3
i~i1
I -~ /'Claim denied.
J
'J e
EEPR-V
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
Executive Secretary
Dated at Chicago, Illinois, this 28tb day of February
1078.