NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number SG-21958
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Toledo, Peoria & Western Railroad Company
STATEMENT OF CLAIM: "Claim of the General Committee of the Brotherhood
of Railroad Signalmen on the Toledo, Peoria &
Western Railroad Company
On behalf of Signal Maintainer Joe R. Kurtz for a call of
two hours and forty minutes at the prevailing overtime rate of pay
for each date account other than signal employes changing radios on
the BN coal train arriving and departing Bushnell, Illinois, this to
begin January 16, 1976, and to continue in accordance with Rule 701 (d)
of the current agreement until a correction is made."
OPINION OF BOARD: The Grievant requests payment for a call as a
result of the alleged action of someone other
than a signal employe changing radios on the coal train arriving
and departing Bushnell, Illinois.
The record indicates that a-unit coal train arrives at
Bushnell, Illinois, loaded with coal from amine in Montana, destined
for a power plant at Peoria, Illinois. The movement from Montana to
Bushnell is handled by the Burlington Northern. At Bushnell, the
Toledo, Peoria & Western takes over the movement to the power plant
at Peoria.
The T P & W returns the entire empty train to Bushnell and
gives the train to the B N for return to Montana.
These B N trains are equipped with B N radios installed in
the locomotive and caboose which transmit and receive only on
assigned B N radio frequencies.
When the T P & W crews board the train, they carry portable
Handie-Talkie Motorola FM Radios. One radio is carried by the
Engineer and the other is carried by the Conductor. A clip is placed
on the existing antenna and the entire set is removed when the T P & W
crew leaves the train.
Award Number
22289
Page 2
Docket Number SG-21958
There is no installation involved and no dismantling
involved in the carrying of Handie-Talkies on and off the train.
Therefore, there is no violation of the Scope Rule in this case.
FINDINGS: The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute
are respectively Carrier and Employes within the meaning of the
Railway Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction
over the dispute involved herein; and : ---__
That the Agreement was not violated. ~~>
i~
A W A R D.
Claim denied.
NATIONAL. RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
49&
61axa-0,1
Executive Secretary
Dated at Chicago, Illinois, this 31st day of January
1979.