NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number SG-22124
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Seaboard Coast Line Railroad Company
STATEMENT OF CLAIM: "Claim of the General Committee of the Brotherhood
of Railroad Signalmen on the Seaboard Coast Line
Railroad Company:
(a) Carrier violated the Agreement, as amended particularly
Rule I Scope when it required or permitted Assistant Signal Supervisor
F. M. Cutts to transport twisted pair (cable) from Rocky Mount, N.C.
to MP-145 near Lucomna N.C. on November 13, 1975 to be used for
temporary repair of Code Line. Mr. Cutts further violated the Agreement
when he made test to the Code Line at various locations between Rocky
Mount and Lucomna, N. C.
(b) Carrier should now be required to compensate Mr. C. H.
Brewer for five (5) hours and thirty (30) minutes at his time and one
half rate of pay."
jGeneral Chairman file: 68-C H Brewer-76. Carrier file:
15-1(76-4) J2/
OPINION OF BOARD: On November 13, 1975, at approximately 10 AM, it
was discovered that the Carrier's Code Line between
Rocky Mount, North Carolina, and Florence, South Carolina, was
malfunctioning. The source of the trouble was initially thought to be
at Fayetteville, North Carolina (which lies about half way between
Rocky Mount and Florence). At about noon, because checks which had
been run at Fayetteville had proved fruitless, Assistant Supervisor
Parker called Assistant Supervisor Cutts to enlist the latter's
assistance in locating the source of the trouble. Cutts went to
Rocky Mount. When he and Parker determined that the source of the
trouble was not at Rocky Mount, they called Supervisor Smith. The
latter's' determination was that the trouble stemmed from loss of tone
somewhere between Fayetteville and Rocky Mount. Cutts left Rocky Mount
with the cable mentioned in the Statement of Claim because it was
thought that the trouble might be due to the fact that a temporary
single-strand wire had been used is connection with repairs attendant
on a derailment at Lucama about two weeks earlier. A Signal Maintainer,
Award Number 22295 Page 2
Docket Number SG-22124
not Cutts, unloaded the cable at Lucama. Though the cable was subsequently installed in replacem
it was discovered that the presence of the temporary single-strand wire
at the Lucama site was not the source of the Code Line trouble.
Having found this to be so, Cutts proceeded in one direction and
instructed a Signal Maintainer to proceed in the opposite direction
for the purpose of locating the source of the trouble. Cutts used a
digital-frequency meter, neither using any other tools nor opening
the line at any point. He discovered the source of the trouble at
the Micro defect detector. The damage had been caused by lightning
during a thunder storm on the previous night. The repair work was
done by a Signal Maintainer.
In connection with both the identification and the repair
of the trouble, all six of the Signal Maintainers assigned at the
Fayetteville-Rocky Mount maintenance territory either were already at
work or were called. The claimant is a Signal Maintainer from Enfield,
which lies to the north of Rocky Mount.
The Organization is claiming a violation of the Scope Rule -relying particularly on those
"construction, installation, inspecting, testing, maintenance and
repair" and which provide that "No employe other than those classified
herein will be required or permitted to perform any of the work covered
by the scope of this agreement". The Carrier broadly denies a violation of the Scope Rule both with
and the line checking done by the Assistant Supervisor.
We are deciding the case narrowly, confining ourselves to
the particular facts and circumstances of the case and seeking to
minimize the establishment of precedent. Already in existence with
respect to the Scope Rule under the Signalmen's Agreement are a
series of Awards drawing various distinctions leading to various
results. We need to dispose of the case, but we see no need to
expand on the various criteria.
The cable-transporting element of the case is determinable
on the basis of the previously-established distinction between the
immediate and the subsequent use of materials transported by a
supervisor. Given the fact that Cutts obviously brought the cable
along because he thought it would be needed to cure the Code Line
trouble, the application of the distinction in the present case seems
artificial. But, in the given circumstances, it would also have been
Award Number 22295 Page 3
Docket Number SG-22124
the height of artificiality for him not to bring the cable along.
And to be borne in mind is that Cutts refrained from unloading the
cable. We are thus holding that the cable transporting by the
Assistant Supervisor in this instance did not violate the Agreement.
With respect to the line-checking element of the case, we
are presented with a conflict between two fundamental considerations.
On the one hand, the checking on the proper functioning of equipment
is simply an inherent part of a supervisor's role. It is thus,
indeed, that many an assignment by a supervisor to a bargaining-unit
employe is formed. And it should be obvious that the use of a digitalfrequency meter by a supervisor
properly be proscribed. On the other hand, physical diagnostic work
is plainly preserved as bargaining-unit work. Moreover, the Signalmen's
Agreement contains the unusually strong command that no non-bargainingunit person "will be ... permi
by the scope of this agreement"
The parties' respective positions echo these broad considerations. We think that we are presente
and that the case's particular circumstances should govern its outcome.
We are ruling in favor of the Carrier on the bases that there had been
difficulties in locating the source of the Code Line trouble; that
there was an urgent need to locate and overcome the trouble; and that
all the Signal Maintainers from the maintenance territory were at work.
FINDINGS: The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute
are respectively Carrier and Employes within the meaning of the Railway
Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction
over the dispute involved herein; and
That the Agreement was not violated.
Award Number
Z"95
Page 4
Docket Number SG-22124
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
4Executive Secretary
Dated at Chicago, Illinois, this
31st
day of January
1979.