NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number SG-22117
Robert A. Franden, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(The Long Island Rail Road Company
STATEMENT OF CLAIM: "Claim of the General Committee of the Brotherhood
of Railroad Signalmen on the Long Island Rail Road:
Claim SG-18-76
A. Carrier violated the current agreement when it deprived
claimants Mr. W. F. Keller IB14P11896 and Mr. C. D. Lowing IBWP10083,
Communications Technicians who occupy positions in the communications
installer gang #31, pre-determined overtime on carrier's right of way
(Montauk Branch) between Freeport, N. Y. and Babylon, N. Y. on
March 27, 28 and 29th 1976. Employees from other communications
gangs worked on the aforementioned dates, but did not work on the
project (rule 261 signal revision) prior to March 27, 28 and 29th
1976. The provisions of the pre-determined overtime rule appear
below for ready reference:
PRE-DETERMINED OVERTIME
RULE
1. When a portion of a particular gang must be worked on predetermined overtime, those with the
be given the first opportunity on the following basis:
a. That such employes are able and qualified for the
particular job.
b. That such employes are
members of
the gang working on
the project prior to the overtime date.
c. That the scheduled overtime is a continuance of the
project worked prior to the overtime date.
B. Carrier should now be required to compensate the claimants
communication technicians aforementioned sixteen hours (16) at time
and one half their regular rate, which is $8.2379 per hour. In
addition there is a weekend differential of 107 for sixteen hours (16)."
Award Number 22302 Page 2
Docket Number SG-22117
OPINION OF BOARD: This claim was filed on behalf of two communica
tions technicians who are alleged to have been
deprived of certain overtime'-work properly assigned to them under
the pre-determined overtime rule (Rule 42).
"RULE 42 -- PRE-DETERMINED OVERTIME
1. When a portion of a particular gang must be worked on
pre-determined overtime, those with greatest seniority
will be given first opportunity on the following basis:
(a) That such employes are able and qualified
for the particular job;
(b) That such employes are members of the gang
working on the project prior to the overtime
date; and
(c) That the scheduled overtime is a continuance of
the project worked prior to the overtime date."
Factual basis for the instant claim is as follows:
A new automatic signal system was being installed by the
carrier during the time in question. The communications technicians
were used to perform certain communications installation work. On
the claim dates communications maintainers were called to be available
to provide maintenance for the system should that be required.
Under Rule 42 the claimants would be entitled to the work
if (1) they were members of the gang working on the project prior to
the overtime date or (2) the work was a continuance of the project
work prior to the overtime date. Such is not the casein the
instant matter. We were persuaded that the communications technicians
had completed their installation work and that the work in question
properly fell into the category of maintenance. It is clear that
two distinct groups of employes were maintained and that the carrier
assigned the work in question to the proper group.
Award Number 22302 Page 3
Docket Number SG-22117
FINDINGS: The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute
are respectively Carrier and Employes within the meaning of the Railway
Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction
over the dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
h~ k
Dated at Chicago, Illinois, this 22nd day of February
1979.