NATIONAL RA ADJUSTMEIV°T BOARD
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Mi.ssouri Pacific Railroad Company
(Former Texas and Pacific Railway Company)
STATE2ENT OF
CLAIM: As shown in Docket No. 3G-22288 and not repeated herein.
FIATDIITGS: The Third Division of the Adjustment Board finds:
That the dispute has certified to the Third Division of the
Adjustment Board ex pane by the complainant party; and
That under date of March 2, 1979 the parties jointly addressed
a commnication to the Executive Secretary of the Third Division requesting
withdrawal of this case from further consideration by the Division, which
request is hereby granted.
A W A R D
Case dismissed.