STAT='T OF CLAIM: As shown in Docket No. SG-22576 and not repeated herein.
FINDINGS: The Third Division of the Adjustment Board finds:
That the dispute was certified to the Third Division of the
Adjustment Board ex parte by the complainant party; and
','hat under date of March 9, 1979 the complainant party addressed
a co:mainication to the Executive Secretary of the Third Division requesting
withdrrawal of this case from further consideration by the Division, which
request is hereby granted.
A H A R D
Case dismissed.
I
NATIONAL RAILROAD ADJUST'y7VT BOARD
By Order of Third Division
i
I
ATTEST: A
Executive Secretary