NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number 151-22591
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Fort Worth and Denver Railway Company
STATEMENT C&' CLAIM: "Claim of the System Committee of the Brotherhood
that:
(1) The Carrier violated the Agreement when, without an
Agreement having been reached between the Carrier and the Brotherhood as
required by Rule 4(b), it assigned the work of dismantling and
reconstruction of the main line track between Lakeside and East Third
Street at Amarillo, Texas to outside forces (System File F-17-77/MS-2).
(2) The Carrier violated the Agreement when, without an
Agreement having been reached between the Carrier and the Brotherhood
as required by Role 4(b), it assigned the work of constructing
approximately 2000 feet of track to by-pass existing main line between
Lakeside and East 3rd Street at Amarillo, Texas to outside forces
(System File F-14-77/MS-2).
(3) The foreman and members (listed below) of the Amarillo
section crew each be allowed pay at their respective straight time and
overtime rates for an equal proportionate share of the total number of
man-hours expended by outside forces in the performance of the work
referred to in Part (1) hereof.
B. B. Levitt, Foreman F. P. Simmons, Laborer
E. Navarro, Laborer f. A.
C»rningham,
Laborer
L. Thrilkill. Laborer F. & Escalante, Laborer
(4) The foreman and members (listed below) of the Amarillo
section crew each be allowed pay at their respective straight time and
overtime rates for an equal proportionate share of the total number of
man-hours expended by outside forces in the performance of the work
referred to in Part (2) hereof.
D. R. Kelly, Foreman F. P. Simmons, Laborer
E. Navarro, Laborer W. A. Cunningham. Laborer
L. Thrilkill, Laborer F. H. Escalante, Laborer
Award Number 2253$ Page 2
Docket Number MW-22591
"(5) Road Equipment Operator C. Burns be allowed pay at his
straight time and overtime rate for an equal number of man-hours as was
expended by outside equipment operators in the performance of the work
referred to in Parts (1) and (2) hereof."
OPINION OF BOARD: The State of Texas planned to change Lakeside Drive,
on the southern edge of Amarillo, from a two-lane
road into a four-lane highway. The construction work involved the
elimination of a grade crossing by building bridges and an underpass.
in order to continue service on the main line, it was necessary
that the Carrier build shooflys around part of the work during construction of the auto road and one
line shoofly crossed Lakeside Drive.
None of the State's construction work has been an issue in
this case.
In order to construct the bridges over the highway, it was
necessary to remove trackage from the Carrier's main line and an
industrial track. The employes of the Carrier removed these tracks and
replaced them after all construction work was completed.
The Carrier retained a private contractor to build shooflys
in order to continue service during the period the main lines were
inoperative at the bridge locations.
The Organization claimed that all of the work to be performed
by the Carrier on this project should be performed by employes of the
Carrier. The Carrier consented that all work to be done on the main line
would be by its employes, but that the construction work on the shooflys
would be contracted out because the shooflys and the depth planking were
not on the right-of-way.
The Carrier's track forces performed all the work necessary to
remove the tracks and restore them. They also removed the shooflys.
The Organization claimed that the Carrier violated
Rule
4
(b) of the Agreement between the parties which reads:
Award Number
22538
Page
3
Docket Number
NEW-22591
"Contracting (b): Employees included within the
scope of this agreement in the Maintenance of Way
and Structures Department perform work in connection with the construction, maintenance or repairs
of, and in connection with the dismantling of
tracks, structures or facilities located on the
right of way and used in the operation of the
Company in the performance of Common carrier
service.
"Work as described in the preceding paragraph may
not be contracted to outside parties, except by
agreement with the Brotherhood, unless special
skills not possessed by company employees,
special equipment not owned by the company, or
special material available only when applied or
installed thorough supplier, are required; or
unless work is such that the Company is not
adequately equipped to handle the work; or, time
requirements must be met which are beyond the
capabilities of company forces to meet.
"In the event the Company plans to contract out
work because of one of the criteria described
herein, it shall notify the General Chairman
of the Organization in writing as far in advance
of the date of the contracting transaction as is
practicable and in any event not less than
fifteen
(15)
days prior thereto."
The Carrier sets up the defense that notice of the proposed
project had been given to the Organization, bat no agreement was reached
by the parties. The Carrier states further that no agreement was
necessary between the Organization and the Carrier because the work was
not to be performed on the right-of-way.
The record makes clear that the construction of the shooflys
and the depth plank crossing are not on the right-of-way. Under the
circumstances, the Carrier was not required to obtain the agreement of
the Organization and the Agreement was not violated. See Awards
4783,
Award Plumber 22538 Page 4
Docket Number W-22591
10722, 19253 and others. Accordingly the Claim is denied.
FINDINGS: The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute
are respectively Carrier and Employes within the meaning of the Railway
Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction
over the dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
Executive Secretary
Dated at Chicago, Illinois, this 28th day of September 1979·