NATIONAL RAILROAD ADJUSTMENT BOARD
Award Number
22588
THIRD DIVISION Docket Number
D5d-22704
John J. Mangan, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Southern Pacific Transportation Company
( (Pacific Lines)
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood
that:
(1) The Agreement was violated when, on September
13, 14, 15,
16, 17, 23, 24, 28, 29, 30, 1976
and October 1 and
4, 1976,
track Subdepartment employes were assigned and used to perform Bridge and Building
Sub-department work at Shed 10, Mile Post
179,
east of Crystal Lake
(System File
148-414).
(2)
B&B Employes Joe Harrison, Jr., Martin L. Seadorf,
J. George Schwarts, Jerry E. Lee, J. D. Jamison, E. A George, George
Callas, Gordon Price, Roy L. Cartwright and David A. Kipp each be
allowed pay at their respective straight-tine rates for an equal
proportionate share of the total number of man hours
(840)
expended by
Track Sub-department forces in performing the subject B&B work."
OPINION OF BOARD: This case asserts that employes of the Track Sub
department were utilized to perform work normally
performed by Carrier's B&B Sub-department forces. The Organization
describes the work in dispute in their submission as occurring at Dormer
Pass, on certain snowsheds, to be comprised of the following work
elements:
"The work is dispute consisted of unloading Styrofoam
from box cars, cutting and placing second hand snow shed timbers along
the back side of the snow shed to form a retaining wall for fill,
cutting and applying styrofoam sheets to form a base to accept application of an outer shell of conc
clean-up work is connection
therewith. This
work required eight hundred
forty (840) man-hours to complete."
Carrier, on the other hand, describes what occurred as follows
(from Carrier's submission):
II
Award Number
22588
Page 2
Docket Number W-PP704
"* * * As a consequence, on the dates of claim,
namely, September 73, 14, 15, 16, 17, 23, 24, 28,
29,
30, October 1 and
4, 1976,
Carrier assigned
employes of the Track Sub-Department, consisting
of Foreman R. E. Paul and seven track laborers of
his gang, along with two qualified truck drivers,
to work along with B&B Gang No. 113 at Snowshed
No. 10. The work performed by the Track Sub-Department employes was confined to putting material on
top of the snowshed, pulling down timbers into
backwork, unloading box cars and trucking the
zonolite material to the work site, cleaning up
construction debris, including that of picking up
discarded bags that were scattered or. the hillside,
and placing them into the backwork behind the
snowshed to be used as fill material."
It is obvious from the two descriptions of :;bat transpired
that there is -a basic disagreement in facts between the parties - a
disagreement which has not been resolved during the handling of the
claim on the property and then, before this Board. However, it is
likewise obvious that Carrier did utilize B&B forces to perform work
which it felt was B&B work and supplemented this B&B force with Track
forces. The dispute seems to center on what, or to what extent, Track
forces performed work that allegedly belonged contractually to B&B
forces.
Carrier, on the property, alleged that a portion of this
claim was untimely presented. However, our review of the record fails
to disclose any improper balling of the claim by the union; to the
contrary, it was timely presented by the union in ail respects.
For the first time upon presentation of this case to the
Board, the Carrier has urged that, notwithstanding other arguments it
has raised in defense of this claim, the fact that winter would soon
unleash snowfalls on Donner Pass placed this work in an emergency
category and it could take such action with impunity under the
agreement. Secondly, it has argued damages for the first time on
appeal to 'this Board. Such positions have been given weight in mazj
of our previous decisions, and we would be in a position here to do
so were it rot for the fact that they were not discussed on the
property. Again, we must remind the parties that it is their
affirmative obligation to make such issues and arguments 'szown to each .-
other in direct discussions of the claim betuee.- them - c:? have ;yell
established this principle in light of the requirements of o,= Circular
ao.
1 and the Railway Labor Act.
Award
Number
22558 Page
3
Docket Number W-22704
Thus, our consideration of this claim is drawn upon the
arguments and evidence disclosed to each other by the parties during
the handling on the property. As-we said before herein, there is a
basic evidence question, and we are not satisfied that either party
has made a prima facie case.
Concerning the arguments, the Union has argued that its 3&B
employes had the right to perform the work in question contractually,
and has cited awards to the effect that system-wide exclusivity has no
bearing on such matters. On the ether hand, Carrier has cited a
substantial number of awards, equal or greater in number, which have
established the line of authority on this property that before a group
of employes may establish contractual right to work, it must be proven
that these employes have performed the work on a system-wide basis to
the exclusion of others. Other awards cited by Carrier stand for the
proposition that there is no reservation of work to any particular
employes of a sub-department in Carrier's Maintenance of Way absent the
same showing - to wit - system wide exclusivity.
The problem with both the arguments of Carrier and the Union
here is an evidenciary one. First, it is apparent that the track and
B&B employes supplemented each other on this work project and that each
of them performed work that was not arguably the property of the other
sub-department. It follows that tae claim: for 81:0 hours total work involved in this claim is gross
the time to examine the true evidence and facts in this case - to wit - was
there any work, or elements of work performed by the Track sub-department
which have historically and by custom been performed by the 3&3 Department
-- employes~--WF:iIe
ae
would
miich
rather rive such claims on their merits
for the future guidance of the parties, where, as here, there has rxt been
a full examination of the facts of a case by both parties on the property,
we are unable to do so - and likewise - we are unable to dismiss such claims
in their entirety. Therefore, as we have done in the past, we are remanding
this case for the parties to iron out on the property, takirg into
consideration (as only the parties are familiar with) the history,
custom and practice involved in work performed by employes of both the
Track and B&B sub-departments and admonishing the parties to examine
the work performed in the instant case in light thereof. We admonish
both parties `_o honestly review the claim in this light and determine
what amount of this claim should be sustained and make a settlement
on such a basis.
FINDINGS* The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds and holds:
Award Number 22588 Page
Docket Number W-22704
That the parties waited oral hearing;
That the Carrier and the Employes involved in this dispute
are respectively Carrier and Employes within the meaning of the Railway
Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction
over the dispute involved herein; and
That the claim is remanded to the Parties.
' A W A R D
Clain remanded to the Parties as provided in the Opinion
of the Board.
NATIONAL RAILROAD ADJUSTENT BOARD
By Order of Third Division
AMEEST:
Executive Secresary.
Dated at Chicago, Illinois, this 30th day of October 1979.
s_ .