NATIONAL RAILROAD ADJUSTrAENr BOARD
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:(
(Missouri Pacific Railroad Company
STATEr'TNT OF CLAIM* As shown in the respective dockets and not repeated herein.
FINDINGS: The Third Division of the Adjustment Board finds:
That the disputes were certified to the Third Division of the
Adjustment Board ex parte by the complainant party; and
That under date of October 26, 1979 the parties jointly addressed
a communication to the Executive Secretary of the Third Division requesting
withdrawal of these cases from further consideration by the Division, which
request is hereby grarted.
A W A R D
Cases dismissed.
NATIONAL RAILROAD ADJUST M-4T BOARD
By Order of Third Division
ATTEST:
Pz" 4'%y-'
Dated at Chicago, Illinois this 9th day of November 1979.