NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-22560
James F. Scearce, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(The Baltimore and Ohio Railroad Company
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood
that:
(1) The Agreement was violated when Trackman George Holder
was used to operate a Class 'A' machine on February 3, 7 and 11, 1977
instead of using Claimant Roger E. Himes who holds seniority as a
machine operator and who was available to perform such service
(System File BALT-W-207/2-MG-1836).
(2) As a consequence of the aforesaid violation, Claimant
Himes shall
be allowed the difference between a Class 'A' Operator's
rate and the trackman's rate for twenty-four (24) hours plus three (3)
hours at the Class 'A' Machine Operator's time and one-half rate for
a total of $50.73."
OPINION OF BOARD: The dispute in this case centers upon the
Carrier's decision to place a trackman in the
position of a "work equipment operator" on certain dates in February,
1977, such action being grieved by the Claimant herein who was more
senior and held seniority as an equipment operator. There is no
question that both men were apparently qualified to operate the
equipment.
Per the Carrier, its decision to place the less senior
employe on the equipment - a Tie Shear - was because (1) such equipment
would not operate in extreme cold, (2) at that time of the year -
February - it could only be determined on short notice if the weather
would permit use of the Tie Shear, (3) such conditions meet the
"unforeseen nature" contemplated under Rule 53 (d-1), and (4) under
such circumstances, the Carrier is entitled to use a qualified
operator who is "immediately available" - also as set out in Rule 53
(d-1). The Organization contends that the Claimant was available
and within a favorable distance to the work.
Award Number 22680 Page 2
Docket Number MW-22560
Rule 53 (d-1) states that:
"Where vacancies of an unforeseen nature occur in
positions of Work Equipment operator and where there
is no Work Equipment Operator immediately available
to cover such vacancies, the senior employee who
can operate the machine may be assigned to cover
such vacancy for a period of two (2) days or less.
It is understood that such employee will be allowed
pay at the applicable Work Equipment Operator's rate
while filling such position."
The record of handling on the property indicates that the
Claimant was working as a trackman some 30 miles distant from where
the machine was to be used, while the trackman used on the machine
was working at the site where the Tie Shear was to be used.
Arguably, had the decision been made to operate the equipment prior
to start-up of the crews on the dates in question, then the Claimant
should have been called. The record does not specify when the
decision was made, although the Carrier asserts such work was done
during the shifts involved. We find nothing in the record that
offers support to the Organization's claim; conversely, the actions
of the Carrier would appear to be in concert with the provisions of
Rile 53 (d-1).
FILINGS: The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute
are respectively Carrier and Employes within the meaning of the
Railway Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction
over the dispute involved herein; and
That the Agreement was not violated.
Award Number 22680 Page 3
Docket Number MW-22560
A W A R D
Claim is denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST://V . /Q..~
Executive Secretary
Dated at Chicago, Illinois, this 14th day of December 1979.