NATIONAL RAILROAD ADJUSTMENT BOMB)
THIRD DIVISION Docket Number CL-22717
Martin F. Scheinman, Referee
(Brotherhood of Railway, Airline and
( Steamship Clerks, Freight Handlers,
( Express and Station Employes
PARTIES TO DISPUTE;
(Southern Pacific Transportation Company
( (Pacific Lines)
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood
(GL-8647) that:
(a) The Southern Pacific Transportation Company violated
the Clerks Agreement on March 25 and 26, 1975, at Roseville, California,
when it called Mr. Steve Morris to fill Position No. 42, Train Clerk,
and subsequently refused to properly compensate Clerk Morris under
the rules of the Agreement; and,
(b) The Southern Pacific Transportation Company shall now
be required to allow Mr. Steve Morris eight (8) hours additional
compensation at the overtime rate oz Position No. 42, Train Clerk,
for March 25 and eight (8) hours additional compensation at the
straight time Guaranteed Extra Board rate for March 26, 1975.
In addition, Claimant is to be allowed interest at the rate of two
percent (2I) per month, compounded monthly, commencing March 26, 1975,
and continuing until the basic claim has been fully adjudicated.
OPINION OF BOARD: Claimant, Steve Morris, was regularly assigned
to the Guaranteed Extra Board at Roseville,
California, working various positions and hours as required by the
Agreement. Claimant worked Position No. 40, Train Clcrk, hours
7:00 A. M. to 3:00 P. M., on Tuesday, March 25, 1975. He was then
released back to the Guaranteed Extra Board.
On Wednesday, March 26, 1975, a vacancy existed on Position
No. 8, Train Clerk, hours 12:00 midnight to 8:00 A. M. Carrier assigned
Clerk R L. Ratzlaff to fill Position No. 8. Ratslaff was removed
at 12:00 midnight on March 26, 1975, from Position No. 42, Train Clerk,
hours 11:00 P. M. to 7-.00 A. M. Ratzlaff's assignment to Position No. 8
created a vacancy in Position No. 42. Claimant was instructed to
report to fill this vacancy at midnight on March 26, 1975. He worked
Award Number 22757 Page 2
Docket Number CL-22717
Position No. 42 from 12;00 midnight to 7:00 A. M. and was allowed
seven hours at the straight time rate of Position No. 42, plus one
hour paid for, but not worked, at the same rate from 7;00 A.M. to
8;00 A. M. for a total of eight hours.
The Organization claims that Carrier violated the Agreement
between the parties by failing to properly compensate Claimant for
March 25 and 26, 1975. It contends that Claimant was entitled to
work Position 42 as it was scheduled, 11;00 P. M. - 7;00 A.M.
The Organization argues that had this been the case, Claimant would
have received 8 hours at the overtime rate since this would have
been Morris'- second start on March 25, 1975. The Organization
maintains that Carrier's sole purpose in changing the starting time
was to avoid paying overtime as is required by the Agreement. It
asks that Morris be allowed eight (8) hours additional compensation
at the overtime rate of Position No. 42, Train Clerk, for March 25,
1975, and eight (8) hours additional compensation at the straight
time Guaranteed Extra Board rate for March 26, 1975. This Board
is also asked to award interest to Claimant.
Carrier, on the other hand, insists that it has not
violated the Agreement. Carrier argues that Claimant's starting
time was 12;00 midnight. Therefore, it contends that Claimant did
not work two assignments on March 25, 1975. Carrier also argues
that the starting time for Position No. 42 was not changed. The
incumbent, Ratzlaff, worked the first hour and then Claimant worked
the remainder of the shift. Carrier claims that while Claimant's
starting time was 12:00 midnight, the position's was 11;00 P. M. as
bulletined. Finally, Carrier maintains that a letter of understanding,
dated October 29, 1959, permitted what occurred here - using an
available extra employe to provide relief for the remainder of a
shift, and paying the employe eight hours at the applicable rate.
Claimant was assigned to Position No. 42. It had a fixed
regular starting time of 11;00 P.M. Pursuant to Rule 16, a
"regular starting time shall not be changed without at least five (5)
working days' written advance notice to employes affected." Carrier
did not provide the required notice of its intent to change the
starting time. Yet, Carrier did alter the starting of Position No. 42
on March 25-26, 1975 far Claimant. By having Clerk Ratzlaff cover the
position for one hour and only then allowing Claimant to work, the
effect upon Claimant was to change the starting time of Position No. 42.
Award Number 22757 Page 3
Docket Number CL-22717
This is unacceptable. .Claimant had a demand right under Rule 16 to
report to work at 11:00 P. M. That is, he was entitled to fill
Position
No.
42 as it was bulletined - including the fixed starting
time.
Carrier also attempted to base its action in dividing
Position
No.
42 on a letter of understanding, dated October 29, 1959.
This contention must be rejected. The circumstances in this case
are not those which that letter of understanding attempts to address.
It is inapplicable to facts presented here.
The final question is that of the appropriate compensation.
Under Rule 20(a), Claimant should have been paid time and one half
for all work he performed between 3:00 P.M. on March 25, 1975 and
7:00 A.M. on March 26, 1975. We will sustain the claim to that
extent. In all other aspects, the claim is denied.
FINDINGS: The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute
are respectively Carrier and Employes within the meaning of the
Railway Labor Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction
over the dispute involved herein; and
That the Agreement was violated.
A W A R D
Claim sustained to the extent and in the manner set forth
in Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
f~ '~
ATTEST::r'~%.~C.
Executive Secretary
Dated at Chicago, Illinois, this 29th day of February 1980.