NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number SG-228:1
George E. Larney, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Southern Railway Company
STATEMENT OF CLAIM: "Claim of the General Committee of the Brotherhood of
Railroad Signalmen on the Southern Railway Company et al:
On behalf of R. L. Jackson, assigned to a temporary signalman job
headquarters Sheffield, Alabama, on Bulletin S-97, dated September 19, 1977,
for eight (8) additional hours at the time and one-half rate for each day
he is held off his bulletined assignment and required to work the second
shift Signal Maintainer position at Sheffield Retarder Yard."
LGeneral Chairman file: SR-7. Carrier file: SG-292/
OPINION OF BOARD: On September 5, 1977, Carrier issued Bulletin No. S-96
in which among the several assignments announced and
positions advertised for bid, the Carrier simultaneously appointed Mr. J. W.
Raper, a first trick Signalman headquartered at Sheffield, Alabama to the
temporary vacancy of Signal Maintainer at Town Creek, Alabama, and posted
for bid Raper's position at Sheffield on a temporary vacancy basis. On
September 19, 1977, Carrier issued Bulletin S-97 announcing among other
items the appointment of the Claimant, Mr. R. L. Jackson, then a second
shift Signal Maintainer at the Sheffield Retarder Yard to the temporary
Signalman's position vacated by Raper. In this same Bulletin, Carrier put
up for bid the Claimant's second shift position. Claimant was advised at
first that unless otherwise instructed, he would report to his new first
shift Signalman's position on September 26, 1977, but as the bidding period
established by Bulletin S-97 was not due to expire until September 29, 1977,
the Claimant was subsequently instructed to remain on the Sheffield Yard
Maintainer's position until this latter date. Inasmuch as no signal employe
bid for Claimant's vacated position under Bulletin S-97, the Carrier sought
to get the Assistant Maintainer at Sheffield to work the Maintainer's
position, but he refused on the basis he was medically incapable of performing
the work. According to the Carrier, because no other qualified employes
were available to fill this vacancy, it held the Claimant in the second shift
Maintainer's position in order to protect the requirements of the service
and at the same time it blanked the first shift Signalman's position at
Sheffield.
Award. NLmber 22845 Page 2
Docket Number SG-22851
By Bulletin S-106, dated January 23, 1978, the Signal
Maintainer's
position
at Town Creek, assumed by Raper
on a
temporary basis was bulletined
as a permanent position. In turn, the temporary Signalman's position at
Sheffield was also bulletined as permanent. In Bulletin S-107 dated
February 6, 1978, the Claimant was appointed to the permanent Signalman's
position and in turn the Claimant's permanent second shift Maintainer's
position was advertised for bids. On February 21, 1978, Carrier announced
in Bulletin S-108 the appointment of Mr. J. R. Scott to Claimant's former
second shift Maintainer position at Sheffield and as a result Claimant was
allowed to report to the first shift Signalman's position at Sheffield on
February 27, 1978.
The Organization alleges that Rules'4, 34, but primarily 20 (c) of
the Controlling Agreement bearing effective date of February 16, 1948, was
violated when Carrier failed to allow Claimant to assume the first shift
Signalman's position at Sheffield on or before October 16, 1977. Rule 20(c)
reads as follows;
ASSIGNMENTS - RULE 20
(Revised - effective April 1, 1942)
(c) Transfer of successful applicants to new assignments
will be arranged for, unless prevented by special circumstances, within twenty (20) days after close
Employees failing to go to new positions within this period,
unless prevented by illness, shall take leave of absence,
and failing so to do may thereafter place himself only by
bidding on other vacancies.
The Organization alleges that Carrier's inability to fill the
Claimant's second shift Maintainer position is not, as the Carrier has
maintained, a "special circumstance" as contemplated under Rule 20(c), but
rather a very coon circumstance. The Organization argues that Carrier's
failure to fill the second shift Maintainer's position is directly
attributable to the Carrier's unwillingness to consummate an agreement with
the Organization concerning the establishment of an apprentice training
program for signal employes that would provide a source of qualified signal
forces sufficient to meet Carrier's needs. But notwithstandirig this fact,
the Organization asserts, Carrier could have moved to fill Claimant's
second shift Maintainer position by posting the position on every subsequent
Bulletin following Bulletin S-97, or by hiring additional persons for its
Signal Department and/or by working the existing signal force overtime,
none of which the Carrier elected to do. It is the Organization's position
Award Number 22845 Page 3
Docket Number SG-22851
that Carrier is obligated to have a sufficient number of available signalmen
on its roster to meet its needs which in the instant case, the Carrier did
not have. Therefore, the Organization reasons, the Carrier also violated
Agreement Rule 34 when in keeping Claimant off his bulletined assignment
(first shift Signalman's position at Sheffield, rest days Saturday and Sunday),
Claimant, was in effect, required to suspend work on said bulletined assignment in order to avoid ov
the Organization cites Third Division Award No. 7346 which reads in relevant
part as follows;
"By almost a solid line of authority the Board is
committed to the doctrine that an employe may not be
used outside his regular assignment to protect another
position for the purpose of avoiding payment of
punitive rates, because, to do so, weakens the job
protection and security to be found in seniority, and,
equally important, the bulletining of positions as to
hours of work and job duties would have little meaning."
It is this line of argument, the Organization asserts, that well supports its
demand in the case at bar, for eight (8) hours at the time and one-half (1~)
rate for each day Claimant was held off his bulletined assignment.
Finally, it is the contention of the Organization that the "special
circumstances" argument invoked by Carrier here constitutes an affirmative
defense which the Carrier has the burden of proving. Instead of proving the
existence of "special circumstances", the Organization alleges Carrier
merely relied
on
argument that constitutes nothing except excuses for failing
to have an adequate force of trained signal employes.
The Carrier notes its Sheffield facility, a computer controlled
hump classification yard containing 45 miles of track, was designed and
constructed to classify up to 1800 cars each day, but presently classifies
between 2100 and 2300 cars per day. Because of this
high volume
of traffic
it is imperative, the Carrier argues, that the second shift Maintainer's job
be filled in order to meet the requirements of service. The Carrier asserts
that "special circumstances" as that contemplated by Rule 20Jc) arose and
became operative when no other signal employe bid on the Ciaimant's second
shift Maintainer position. It is the Carrier's position that while the term
"special circumstances" is not defined, reason and logic dictate that
operational requirements would be the primary criterion to determine whether
"special circumstances" exist. Furthermore, the Carrier argues, even if .
Rule 20 (c) did not provide for delays due to "special circumstances", in
its place a test of reasonableness would have to be applied. Such a test of
reasonableness, the Carrier notes, has been applied by this Board in other
cases. --
Award Number 22845 Page 4
Docket Number SG-22851
Insofar as the first shift Signalman's position which was bid
successfully by the Claimant is concerned, the Carrier stated that the
position was one (1) of three (3) headquartered at Sheffield. Because of
the nature of the Signalman's duties at Sheffield and the fact that there
were some eleven (11) other signal maintainers stationed between
Chattanooga and Memphis, it was not of pressing need, the Carrier maintains,
to fill the Signalman's ,job especially since it had other forces to
perform the required work.
Carrier further argues that based on pertinent language in the
following three (3) Third Division Awards, the Claimant was never "assigned"
to the first shift Signalman's position until date of February 27, 1978,
and therefore was not entitled to either the assigned hours or the rest
days of that position until he actually commenced working the position.
In Award 12315, Carrier cites the following language; " _ the words
'having a regular assignment' means more than bidding in a position and
having been assigned; there must be 'actual acceptance by physically
taking over the duties..."' And in Award 2389, Carrier cites the following;
"positions are not to be construed as assigned until such time as work is
actually begun thereon," and finally in Award 19671; "an employee, in order
to acquire the rights of an occupant of a position, must commence work on
such position." Thus, the Carrier concludes, because Claimant was not
"assigned" to the first shift Signalman's position until February 27, 1978,
he could not possibly have been required to suspend work on that position
to absorb overtime or for any other reason.
Upon an exhaustive review of the record before us, this Board has
given considerable thought to the central question posed here and that is,
what meaning did the parties intend to impart to the term "special circumstances" within the context
of probative evidence in the record to use as a beacon in assisting us to
divine what is and what is not a "special circumstance". Neither party has
offered any bargaining history to elucidate what the parties intended by
the language in question and neither party has presented specific instances
or examples of what has qualified in the past as "special circumstances".
Even the Carrier admits there is an absence of a definitional standard with
regard to the term "special circumstances" as used in Rule 29.(c). That
being the case, it is our determination that this claim must be dismissed
on the basis that both parties have failed to meet their burden of proof.
Award Number 22845 Page 5
Docket Number SG-22851
FINDINGS: The Third Division of the Adjustment Board, after giving the
parties to this dispute due notice of hearing thereon, and upon
the whole record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
That the Claim be dismissed-
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:/~ /~.
Executive Secretary
Dated at Chicago, Illinois, this 16th day of May 1980.