NATIONAL RAILROAD ADTUSMM BOARD
RIIRD DIVISION Docket Number
MW-23078
Rodney
.EJ.
Dennis, Ref°_ree
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPWE:
(Consolidated Rail Corporation (formerly The New York,
( New Haven & Hartford Railroad Company)
STATEMENT CF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when outside forces were used
to cut brush and install track ties on the West Hanover Secondary Track
between North Abington and West Hanover, Massachusetts (System Docket
NH-7
Northeastern Region - New England Division).
(2) As a consequence of the aforesaid violation, Trachea
T. Pawlak, C. Medeiros, M. M. Medeiros, Jr., A. Almeida E. Tamara..
J. Almeida and G. Farrell each be allowed sixty-six
(661
hours of pay
at their respective straight-time rate and twenty-two and one-quarter
(22D
hours of pay at their respective time and one-half rates."
OPINION OF BOARD: Between October
31, 197'(
and November
7, 1977,
an
outside contractor performed Maintenance of Way work
on the West Hanover Secondary track running between North Abington and
West Hanover, Massachusetts. This short piece of track
(3.6
miles) was
not part of the Conrail System, but was still under the control of the
trustee of the Penn Central. The State of Massachusetts desired that
train service be continued on this line and it obtained control of the
right of way from the Penn Central trustee. The state thereupon entered
into an agreement with Conrail to operate trains over the road and to
perform certain maintenance work for which Conrail would be compensated
by the Commonwealth of Massachusetts as the subsidizer.
(ksrrier also entered in to an agreement with the Commonwealth to
obtain by subcontract certain accelerated maintenance of the
3.6
miles of
track in question. Carrier notified the Organization that it intended
to obtain a subcontractor to do the accelerated maintenance work. It
then obtained a subcontractor and the work was completed. The Organization filed a grievance allegin
employes should have been used to do the work.. not an outside subcontractor.
The Organization relied on Rule
53,
classification, to buttress its claim.
Award &anber 23034 page 2
Docket Humiber MW-23078
Carrier denied the claim,'arguing that:
(1) it did not own or control the track in question,
(2) the work performed was not instigated by it,
was not done for its benefit, and was not paid for
by wrier, and
(3)
the agreement between Conrail and the Commonwealth of Massachusetts specifically states that
accelerated. maintenance will be done by subcontract.
Carrier was not in control of the situation when
this agreement was made and was directed by the
Commonwealth to subcontract the work.
It is clear from the record that claimants were furloughed
employes who normally would have performed maintenance work on the section
of track involved. It is also clear that the work done by the contractor
was work belonging to Maintenance of Way employes.
This Board has carefully, reviewed the record of this case and
can find no basis on which to justify Carrier's position. We have care-
fully studied the Third Division awards cited by Carrier in its submission, ~-
Awards 20639 and 20644, and we do not find them on point. This Bawd,
however, has been guided by a recent award involving Carrier and the Org
anization and an identical issue, though on another part of the railroad
(Public Law Board No. 2203, Award 21, Harold M. Weston, Chairman).
The facts of Award 21 closely parallel those in the instant case
and this Board agrees fully with that awards
(1) Claimants cited are proper claimants.
(2) The action was consistent with the terms of
the agreement between carrier and the Commonwealth
of Massachusetts.
(3)
The action, however, violated Rule
53
of the
agreement.
(4) This Board is not
in
accord with
carrier's
view
that it bears no responsibility in this matter.
'-
. Award Number 23034 page
3
l Docket Nwnber
D4W-23073
We believe that Carrier knew that it had commitments under
collective bargaining agreements when it entered into operating contracts
with the Commonwealth. These collective bargaining commitments were not
eliminated by these operating agreements.
Based on the record of the case and the rationale expressed
in Award No.
21
(with which we fully agree), this Board must issue a
sustaining award. As to the damages to be paid to claimants, after
considerable discussion we have concluded that a total of
$8.25
hours
at the pro rata rate shall be divided equally among the named claimants.
In arriving at this award, this Board is confined to the
undisputed facts of this record. We may not, no matter how reasonable
it may appear to be, speculate on the existence of facts not cited in
the record. The only fact agreed upon or cited in this record concerning the subcontract was the num
(88.25).
No mention was made of the total labor cost, number of men working, hourly
rates paid, etc.
This Board, therefore, has been confined to basing this award
on the total hours cited in the record.
FINDINGS: The Third Division of the Adjustment Board, upon the whole
record and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute
are respectively Carrier and Employes within the meaning of the Railway
Labor Act, as approved June
21, 1934;
That this Division of the Adjustment Board has jurisdiction
over the dispute involved herein; and
That the Agreement was violated.
AWARD
Claim sustained in accordance with Opinion.
NATIONAL RAILROAD AATLU"V.MT BOARD
By Order of Third Division
ATTEST:
Executive Secretary
Dated at Chicago, Illinois, this 28th day of October 1980.