(Brotherhood of Maintenance of Way Employee PARTIES TO DISPUTE:


STATEMENT OF CIAIM;r "Claim of the System Committee of the Brotherhood that:


to Project Manager R. J. Brueske shall be allowed as presented because said
claim was not disallowed by Project Manager R. J. Bxueske in accordance with
Rule 47(a) System File C#133/D-225J .



OPINION OF BOARD: Claimant D. M. Gunther is a roadway equipment operator who
worked during June, July, and August 1978, in a capacity in
which he was authorized, by agreement, to receive certain travel expenses.
According to the record, claimant was paid for travel time and a meal and lodg
ing allowance in accordance with Rule 26 of the agreement. It also appears
from the record that claimant submitted a normal expense account and apparently
included certain items that Project Manager R. J. Brueske thought were not
reimbursable. Claimant and Brueske had a telephone discussion about the expense
account items prior to September 13, 1978.

On September 13, 1978, Project Manager Brueske, by letter, informed claimant that he was returning his expense accounts for July and August and that he had already been paid expenses in accordance with Rule 26. If he would resubmit the August expens
On September 18, 1978, claimant responded to the Brueske letter. In his response, he commented that since he and Bn:eske had talked on the phone about his expenses, Brueske could have checked a few things out before he returned the accounts to c
Claimant then went on to outline his job situation and discuss the machines he operated between June 5 and September 18. Claimant ended the letter by stating that he intended to submit expenses for June when he got them figured out and that he hoped that the letter straightened things out and that there would be no more delay in his expense payment.

                        Docket Number MW-23180 Page 2


Nothing further transpired between the parties in this case until December 12, 1978, when General Chairman R. W. Mobry wrote V. W. Merritt, Carrier's Assistant Vice President for Labor Relations, indicating that Mr. Brueske had not responded within 60 days to claimant's September 18, 1978 claim. Merritt responded by letter on January 23 to Mobry, stating that Carrier considered claimant's original submission of his expense account as the initiation date of a claim under rule 47(a) of the agreement. It also considered the Brueske letter of September 13, 1978, to be Carrier's rejection of that claim. Carrier argued in the Merritt letter that the Organization failed, in its appeal to Carrier's highest official, to cite what, if any, schedule rile was violated.

This case is before this Board solely on a time limit question under Rule 47(a) of the controlling agreement. Rule 47(a) states that all claims or grievances must be presented within 60 days of the date of the occurrence on which the claim or grievance is based. It also states that if a claim or grievance is to be disallowed, Carrier must do so within 60 days from the date that claim is filed. The issue in this case is when did claimant file his claim as contemplated under Rule 47 and when did Carrier respond?

After a thorough review of the record and of the previous awards cited by each side in support of its position, it is the opinion of this Board the claim must.be sustained. This Board does not consider claimant's submission of his expense account as the filing of a claim, but as an action that regularly takes place in the normal course of business when an employe has reimbursement for travel.expenses due him. Whether claimant made a mistake in his initial submission is immaterial. What is material, however, is that after Carrier returned claimant's expense account on September 13, 1978, indicating that he would not receive the amount requested, he wrote a letter explaining why he thought that he should be paid his expenses as submitted. It is the opinion of the Board that at this point a claim was filed.

Carrier had an obligation under Rule 47(a) to respond to claimant's September 18, 1978, letter and indicate why his claim was rejected. Carrier's letter of September 13, 1978, cannot be considered as having met this requirement, since the origina under the agreement. Carrier failed to respond to claimant's September 18, 1978, letter within the required 60 days. Article 47(a) states that in such a situation, the claim mist be
        FINDINGS: The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds and holds:


        That the parties waived oral hearing;

                        Award Number 23205

                        Docket Number NW-23180 Page 3


That the Carrier and the Employes involved in this dispute are respectively Barrier and Employee within the meaning of the Railway Labor Act, se approved June 21, 1934;

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and

        That the Agremnt VsS violated. _ . .


                        A W A R D


        Claim sustained.


                              NATIONAL RAILROAD ADJUSTMENT BOARD

                              By Order of Third Division


ATTEST; (~' e
Tcu iveta~

Dated at Chicago, Illinois, this 16th day of March 1981.