0 D







(Brotherhood of Railway., Airline and Steamship Clerks, . ~ Freight Handlers, Express and Station Employes PARTIES TO DfSP(1BE.




Carrier violated the Agreement at Atlanta, Georgia, when it suspended Mr. J. S. Baker, Clerk at Inman Yard, from the service of the Carrier begins October 27, 1976, through November 25, 1976.

Carrier shall be required to compensate Mr. J. S. Baker at his regular rate of pay for all time lost during the period October 27 through November 25, 1976.

OPINION OF BOARD: Claimant, J. 3. Baker, after investigation, was
suspended thirty (30) days for tardiness. The incident which led to this dispute ocasred on October 24, 1976. Claimant arrived to work 44 minutes past his scheduled 7:00 A.M. reporting time.

The Organization acknowledges that Claimant was late that day. Eowever, it believes that Carrier violated Rule C-1(c) of the Agreement by considering tardiness more than 30 days previous to October 24, 1976, is determining the penalty to be imposed. It asserts that consideration i of past offenses amounts to arbitrary, capricious and unreasonable action.





There can be no doubt that Claimant is guilty of tardiness. He admits as much. His explanation that he overslept is no mitigation is any sense of the word, An employs must insure that he reports to work at his scheduled reporting time. When Claimant failed to do so, he subjected himself to appropriate discipl



i The seriousness of the proven offense is a consideration because regard-




















That thin Division of the Adjustment Board has jurisdiction over the dispute involved herein; and

        That the Agreement vas not violated.


                  A W A R D


        Claim denied.


                          RATIONAL RAILROAD AnTtJSTIaNT BOARD

                          By Order of Third Division


ATTEST:
      Executive Secretary


Dated at Chicago.. nlinois, this 19th day of June 1981.