NATIONAL RarLRawn ADJUS7KE2iT BOARD
THIRD DIVISION Docket Number SG-23077
John J. Mikrnt, Jr... Referee
(Brotherhood of Railroad Signalmea
PARTIES TD DISP=:
(Southern Railway Company
STAM(EN'P OF CLAgt: "Claim of the General Committee of the Brotherhood of
Railroad Signalmen on the Southern Railway Oompany et al:
Claim on behalf of J. H. Fox., Signal Foreman, suspended from service
for thirty (30) days, due to an investigation held is Gainesville,, Georgia on
May 9j, 1978s with a request that claimant be paid for the thirty (30) days he
vas suspended and his record cleared." (Carrier file: SG-326)
OPINION CF HOARD: On March 14, 1978, Claimant was assigned as the Signal
Foreman of a five (5) member Signal Gang which vas engaged
in replacing a crossing signal relay case at the at-grade crossing of State
Highway 21 sad the Southern Main Line which is located near Pineville,, North
Carolina*
However,
because the new signal case could mat be placed into
service at that time ("polder linen hadn't been raised"), the Project Engineer.
C. L. Davis, who vas present at the fob site, directed Claimant to make a temporary hook-up by canni
door of the new signal. case and then tie it into the circuit with temporary
wire. When this particular activity vas completed, the now circuits were
tested and the crossing signal worked ("the crossing bells rang, and the
crossing signal flashed."). Thereupon, the Project Engineer left the fob
site, but before doing so, he directed Claimant to supervise the remaining
final steps of the assignment. Said assignment vas completed at approximately
2:30 PM at which time Claimant and his work crew departed for another assignment is Drexel, North (h
The first train to came through the nearly repaired crossing vas
Train No. 73 which did so at approximately 3:45 PM. According to the Train's
Engineer., the crossing vas made without incident ("the crossing signals flashed
and the bell rang"). At approximately 4:20 PM, a second train. Train No. 185·
Second, also came through the eroasiag, but this time the crossing signal did
not function properly ("the belle rang but the lights did not flash") and, as
a result, the Train struck a tractor trailer which had failed to atop at the
crossing. The tractor trailer is turn struck a second vehicle causing an ia,jury to one of the vehic
Award Number 23344 Page 2
Docket Number SG-23077
An investigation of the accident was conducted by Carrier representatives who arrived at the sce
and it was discovered that same of the wires which had dust been installed
that afternoon by the Signal Crew "...had been crimped by the door (of the
relay case), thereby exposing the wire which overheated and caused the relay
contacts to barn out." In light of this discovery, the investigators
"...concluded that the burned out relay contacts and the signal failure
were directly attributable to the crimped wiring."
Pursuant to the a8brestatad investigation, Claimant, who was
the employs in charge of the Signal Gang, was charged with "failure to
properly perform his duties" and a hearing as the matter was conducted on
may 9a 1978. As
8
result of said hearing, Claimant was found guilty as
charged and was assessed a thirty (30) day suspension fns failure "...to
properly perform his duties as the employs in charge when he permitted the
temporary signal airing to be installed in an unsafe manner which resulted
is the signal system malfunction and thus the serious accident."
Organization's position in this dispute is two-fold: (1) that
Carrier prejudged Claimant's guilt prior to the conducting of the iavestigatory hearing; and (2) tha
herein.
Regarding the first of these two contentions, Organization maintains that the specific contents
Notice ("...you are charged with failure to properly perform your duties as
Signal Foreman on March 14, 1978 when you permitted the temporary signal
control wires to be installed is an unsafe manner which resulted in a
serious accident"), "...shoxs conclusively that (terrier decided before the
iavesti
lion
that Claimant was guilty as charged" (Emphasis added by
Organization . Organization alleges that because of this pre3udgement
"...it was impossible for Claimant to receive a fair and impartial investigation" affil that "This r
sustaining award."
Turning to the second of its contentions, organization asserts that
"...Carrier did not and could not support the instant charge with probative
evidence" sad that
Carrier,
therefore, has failed to sustain its requisite
burden of proof in this dispute (First Division Award No. 20834; Third
Division Awards No. 9216, 1120, 18885 and 19515). In support af this position, Organization maintain
the effectiveness of the blocking procedure which was utilized by the Signal
knowledge incorrect"; the relay properly blocked/protected
direct ledge of pxotected
by the Signal Gang, whereas Organization's witnesses did have such knowledge
and so testified at the investigation herring.
Award Number 233+ Page 3
Docket Number SG-23077
As its final area of argumentation is this regard, Organization
contends that insofar as the crooning signal flashers were walking properly
when Train No. 73 Passed over the crossing approximately one hour and fifteen
minutes after the Signal Grey had left the scene, this fact alone is proof
that, the relay case was properly protected at the time of the Gang's departure. Given this particul
that whatever might have canned the crossing signal to malfunction between
the passing of Train No. 73 and Train No. 185-Second was not caused by any
fault or negligence on the part of the Signal Gang and Claimant's suspension, therefore., was improp
Carrier's position in the dispute is equally as clear and direct
as that which has been proffered by Organization. Simply stated, Carrier
maintains that: (1) evidence adduced in the investigation proves (claimant's)
guilt of failing to properly perform his duties on March 14, 1978; sad (2)
the discipline which was imposed was fair and reasonable, and should not be
disturbed.
In support of its contention that Claimant failed to properly perforce
his duties, Carrier maintains that, over cad above its conclusive shoving
that the damaged wires is the relay case were the direct cause of the accident, which occurred on Ma
establish that: (1) the crossing signal worked properly before Claimant
directed the dosing of the relay case doors; (2) Carrier investigators
found no evidence that Claimant and/or Signal Gang blocked the relay doors
is accordance with normal procedures; and (3) Carrier's investigation of the
scene immediately after the accident revealed that the manner in which
Claimant alleges that "he blocked the dear would still have resulted in
the wires being crimped."
Regarding its second contention, (drier maintains that its actions
is this matter have neither bean arbitrary nor
capricious,
and the Board
therefore, must not disturb the discipline which has been imposed. (First
Division Award go. 130061 Thud Division Awards No. 15828 and 20194).
Moreover, Carrier also contends that, given the notions nature of Claimant's
infraction, Carrier's imposition of severe discipline upon Claimant was
justified; sad "...in light of the nature of the proven offense and its possible catastrophic conseq
The Board has carefully rued and studied the complete record is
this dispute and is unable to find evidence, either in fact or is substance,
which would justify the recision of the penalty which has been imposed upon
Claimant by Carrier.
Award Number 233 Page 4
Docket Number SG-23077
From the outset, Organization's contention regarding Carrier's
alleged prejudgment of Claimant's guilt is reverted as being without foundation. The totallity of Or
phraseology utilized by Carrier is its March 21, 1978 Investigation Notice
which, according to Organization, "...shows conclusively that Carrier decided
before the investigation that Claimant was guilty as charged."
While it is indeed true that prejudgment of an accused prior to the
conducting of a fair sad impartial hearing, if graven, can be sufficient
grounds for the setting aside of disciplinary action, it is equally true that
the charge of "prejudgment" cannot merely be asserted,, but must be supported
by same degree of substantive and creditable evidence. In the instant cssep
no such evidence has been proffered, and that which has been alluded to
by Organization is nothing more than a specific and precise statement which
apprised Claimant of the matter which was to be inquired into at the investigation "...and was state
of the offense and enable him to prepare his defense." Additionally, the
specific words which Organization cites as the basis of its argument in this
regard have been completely taken out of context by Organization and these
words, by themselves, tend to obscure the true meaning sad intent of the
Investigation Notice from which they were extrapolated. In such instances,
rather they relying upon bits sad pieces of evidence and/or testimony, the
actual conduct of the hearing itself is viewed as being a more appropriate
index of the fairness and impartiality of the investigation, and, is this
regard, the transcript of said hearing clearly indicates to this Board that
the proper standards of conduct were followed and were met by Carrier as
required under Rule 23 of the parties' Agreement. The basis for this particular rationale was articu
Englestein in Third Division Award No. 13727 when he concluded:
"In respect to the contention that the notice of
investigation did not set forth the 'known circumstances'
as required by Rule 21, we find that Carrier's letter of
September
19, 1963,
included such significant information
as the date and place of the occurrence, the rules violated, and reference to Claimant's conduct
necessitated his removal from service at Forgo.
Claimant was, therefore, adequately apprised of the
nature of the charges so that he could prepare his
defense. Moreover, the hearing indicates that he
was not taken b surprise when the char s were
presented. Emphasis added by Hoard.
Award lYumber
23344
Page
5
Docket Humber
SG-2307r
As to organization's second. major contention "...that (terrier
has failed to meet its burden of proof and therefore forfeits its right
to discipline.." the Hoard 18 as equally unpersuaded by this particular
line of argumentation as was the case in the foregoing consideration.
Suffice it to say that though the total blame for the Signal Gang's
be
attributed any one member of said crew (supervisory or otherwise)..
and though it is impossible to determine with affil degree of absolute
certainty the enact manner is which Claimant functioned in the per
formance of said assignment, there is sufficient evidence available
within the record to conclude that: (1) the accident of March
14, 1978
occurred as a result of the crossing signal's failure to operate properly;
(2)
said failure, most likely, was caused by the improper/inadequate
blocking procedure which was utilized by the Signal Gang in temporarily
restoring the crossing signal relay case to service'; and
(3)
Claimant. -
in the final analysis, was the employs who was accorded ultimate authority
and responsibility for the proper performance of said assignment. Thus the
Board concludes that under such
circumstances,
(terrier's imposition of dis-
cipline herein was neither unreasonable, arbitrary nor capricious; Was a
proper exercise of Carrier's managerial authority; and said determination,
therefore, shall remain undisturbed. (Third Division Awards No.
9326s
11775
and
21047)·
"The fact that the crossing signal worked properly when Train
No, 73
came through the crossing does not indicate that the signal was
properly protected at the time of the Signal Gang's departure since the
record adequately demonstrates that the newly repaired circuit was
adequate to "energize" the flashers for the first train's passing, bat
"as the train continued to pass over the circuit, the current fluxing
through the crimped wires created heat, end the heat cont4med to increase until it reached the level
to burn oat (Carrier's Submission, p.
6;
also see Hearing Transcript, pp.
21,
25
and
29·
Award
Number
233 Page
6
Docket Number SG-230T(
FnWnVG3: The Third Division of the Adjustment Bird, after giving the
parties to this dispute due notice of hearing thereon, ate.
upon the whole recd and all the evidence, finds and holds:
That the Carrier and the Employee involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved Juan 21, 1934;
That this Division of the Adjustment Board has jurisdiction
over the dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
Executive Secretary
Dated at Chicago, Illinois, this 30th day of July 1981.
,:
I ,
_.