NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number
MW-23038
Martin F. Scheinman, Referee
Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Missouri Pacific Railroad Company
( (Former Chicago and Eastern Illinois Railroad Co.)
STATEMENT OF CIAIM:
"Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when the members of surfacing Gang
5748
were compensated at their respective straight-time rates instead of at
their respective time and one-half rates for the service each performed on
certain dates during the period January
3, 1978
through February
12, 1978
(System File S
214-94).
(2)
The Agreement was further violated when the members of Surfacing
Gang
5748
were not permitted to work their scheduled assigned hours on certain
dates during the above-mentioned claim period.
(3)
Each member of Surfacing Gang
5748
now be allowed the difference
between what they should have been paid at their respective time and one-half
rates and what they were paid at their respective straight-time rates because
of the violation referred to in Part (1) hereof.
(4)
Because of the violation referred to in Part (2) hereof, each
member of Surfacing Gang
5748
be allowed eight
(8)
hours of pay for each day
they were not permitted to work their scheduled assigned hours during the abovementioned claim period."
OPINION OF BOARD:
The Organization claims that Carrier violated the Agreement
when it compensated the members of Surfacing Gang
5748
at
their straight-time rates rather than at the time and one-half rate for work
performed on certain dates during the period January
3, 1978
through February
12,
1978.
During this period, Carrier divided the Surfacing Gang into two
segments, one worked Monday through Thursday, ten hours each day, and the other
worked Thursday through Sunday, ten hours each day. Carrier compensated each
employe at the straight time rate for all hours in excess of eight hours each
day, and at the straight time rate for any work performed on Saturday or
Sunday.
The Organization asserts that Carrier's actions violated the Agreement
which provides that, subject to limited exceptions, employes will work a five
day work week, Monday through Friday, eight hours each day.
Carrier, on the other hand, claims it did not violate the Agreement
since each employe voluntarily signed an agreement to work four ten hour days
straight time as a means of meeting a "legitimate operational need" of the
Carrier, and to prevent the layoff of several employes. It also insists that
the "double shifting" ended on February
8, 1978.
Award Number
23461
Page
2
Docket Number
W-23038
POSITION OF EMPLOYES:
Rule 9 of the Agreement provides, in relevant part:
"Rule 9--The 44-Hour Week
Establishment of Shorter Work Week
NOTE: The expressions 'positions' and 'work' used in
this Agreement refer to service, duties, or operations
necessary to be performed the specified number of days per
week, and not to the work week of individual employes.
(a) General--
Subject to the exceptions contained in this Agreement,
a work week of
40
hours, consisting of five days of eight
hours each, with two consecutive days off in each seven, is
hereby established. The work week may be staggered in
accordance with the Carrier's operational requirements; so far
as practicable the days off shall be Saturday and Sunday. The
foregoing work week rule is subject to the provisions of this
Agreement which follows:
(b) Five-Day Positions--
On positions the duties of which can reasonably be met
in five days, the days off will be Saturday and Sunday.
(f) Deviation from Monday-Friday Week--
If in positions or work extending over a period of five
days per week, an operational problem arises which the carrier
contends cannot be met under the provisions of paragraph (b)
of this rule, and requires that some of such employes work
Tuesday to Saturday instead of Monday to Friday, and the
employes contend 'the contrary, and if the parties fail to
agree thereon, then if the Carrier nevertheless puts such
assignments into effect, the dispute may be processed as a
grievance or claim under this agreement.
It is further agreed that the following statement of
principles shall be used as a guide in the future application
of this rule:
1. There is no absolute right to make work assignments
from Tuesday to Saturday on any positions the duties of which
can reasonably be met in five days as specified in paragraph
(b) of this rule. Paragraph (b) governs such assignments.
2. Paragraph (f), however, permits exceptions to paragraph
(b) under certain conditions.
Award Number
23461
Page
3
Docket Number
MW-23038
3.
The first condition is that there must be an
operational problem which cannot be met under the
provisions of paragraph (b).
4.
The second condition is that the operational problem
'requires that some of such employes work Tuesday to Saturday
instead of Monday to Friday.'
5.
Another condition is that the operational problem
and the necessary number of Tuesday to Saturday assignments
to meet it must be explained to the duly accredited representative of the employes and an effort made to reach agreement.
6.
If the parties fail to agree. the management may
then put into affect the assignment it deems necessary to meet
the operational problem, but it does so at its risk, because
paragraph (f) gives the employes the right to process as a
grievance or claim their contention that the assignment itself
is improper."
The Agreement is clear that a Monday through Friday, eight hour per
day work week is the contractually preferred schedule. Deviation from the
Monday through Friday work week is permitted, pursuant to Rule
9
(f) and
9 (3),
if an operational problem arises which cannot be handled on a Monday
through Friday schedule.and if the operational requirement necessitates a Tuesday
through Saturday schedule Rule
9 (4)).
In either case, a five day work week
is clearly contemplated by the Agreement.
Carrier has failed to demonstrate that an operational problem existed
which could not be accommodated in the Monday through Friday work week.
Carrier's assertion that the work was seven day per week work is not sufficient
in light of the fact that the work was previously performed on & Monday through
Friday basis.
Rule
9 (5)
of the Agreement requires Carrier to explain the operational
problem to the Organization in an effort to reach agreement and prevent the
implementation of a Tuesday through Saturday work week. This the Carrier did
not do.
While the Carrier may have been responding to the employes' desires
to avoid the layoff of their fellow workers, it is nevertheless absolutely clear
and well established in prior Board decisions that an employer cannot enter into
individual agreements with employes which modifies a collective bargaining agreement. (See Awards
21048, 4461.)
Even if the four day work week were desire- .: all employes, it is
fundamental that they cannot individually agree with Carrier to amend the Agreement.
On this there can be no dispute.
There is nothing in the Agreement to authorize a four day, ten hours per
day, work week. To the contrary, the Agreement contemplates a five day, eight hours
per day, work week.
Award Number
23461
Page
4
Docket Number MEd-2"038
Accordingly, the claimants listed shall be paid at the straight time
rate for all days on which they would have been scheduled to work but did not
work. All claims for overtime are denied.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21,
1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was violated.
A W A R D
Claim sustained in accordance with the Opinion.
NATIONAL RAILROAD ADJUSTMNT BOARD
By Order of Third Division
Attest:
Executive Secretary
Dated at Chicago, Illinois, this 8th day of December 1981.