NATIONAL RAILROAD AwuSTen BOARD
THIRD DIVISION
Rodney E. Dennis, Referee
PARTIES TO DISPUTE:
STATEMENT OF CLAIM:
Award Number
23478
Docket Number
TD-22936
(American Train Dispatchers Association
(
Consolidated Rail Corporation
(Former Penn Central Transportation Company)
'System Docket No. CR-7 Central Reaioa -
Allegheny Div. Case
5-1
"Claim of American Train Dispatchers Association that Claimant
D. J. Harpster, Train Dispatcher Altoona Movement Office, Altoona, Pa.,
is entitled to eight
(8)
hours pay either pro r:ta or punitive rate
Train Dispatcher for the following dates when agreement was violated.
Regulations 4-B-1,
4-C-1, 4-D-1
and
7-B-1
of present agreement with
American Train Dispatchers Association governing.
1/26/75 -
1/28/75 -
2/ 2/75 -
2/ 9/75 -
2/16/75 -
1/24/75
1/25/75 -
!'3)./75 -
2/
7/7; -
2;1w; f5 -
2/21/7> -
1/21;75 -
1/22/75 -
1/23/75 -
1/29/''5 -
1/30/i7 -
2/ 4/75 -
2/ 5/75 -
2/ 6/75 -
2/11/75 -
2/12/75 -
2/13/75 -
2/18/75 -
2/19/75 -
2/20/75 -
Pro rata rate - aeaigne<
_ _
Punitive rate - assigned
No IN
_ _
_ _
It to
_, n
Punitive rate -performed
n _ _
n _
_ _ _
_ _ _
_ _ _
_ _ _
_ _ _
" _ n
_ _ _
n n n
_ _ _
_ _ _
_ _
work day - not permitted to work
_ _ _
n _
n n
of
it
n n
relief day - performed service
_ a
_ _ n
No 11
n n
service
off
assigned hours
_ _ _
n
,
n
n
n
n
n
n
,
_
to
Award Number 2347$ Page 2
Docket Number TD-22936
OPINION OF HOARD: Claimant was regularly assigned as a relief
train dispatcher on the Section "A" desk in
carrier's Altoona, Pa., office. His regular work schedule was the
Sunday and Monday day shift, 7:00 a.m. to 3:00 p.m; Tuesday and
Wednesday shift, 3:00 P.m. to 11:00 p.m.; and Thursday, the 11:00 p.m.
to 7:00 a.m. shift. Friday and Saturday were rest days.
Claimant was assigned by carriei on Janvary20, 1975, to
work with a member of the M & W department on the preparation of a
gross ton mileage report. This report is used for the M & W department. The project was complete
claimant returned to.his relief dispatcher assignment on the following Sunday.
During the time claimant was assigned to the gross ton
mileage report, he worked from 73:00 a.m. to 5:OO.p.m., with Saturday
and Sunday as rest days. This work schedule coincided with the schedule
worked by R. E. Chambers of the M & W department, who was working with
claimant on the project. On march 4, 1975, claimant alleged that carrier
had violated his rights under the contract because of the work schedule it
gave him during his special assignment from January 20, 1975, to February 20,
1975. Because of this violation, he claimed:
(1) pro rata pay for the days he was normally scheduled to work but did not
(alleged violation of Regulation 4-B-1);
(2) the punitive rate for rest days he was required to work during the
special assignment (alleged violation of Regulation 4-C-1); and
(3) the punitive rate for all services performed on the special project
during hours not regularly assigned (alleged violation of Regulation
4-D-1).
Claimant itemized his claim by days and alleged violations. A
total of twenty-five (25) days are included in the claim in one of the three
categories of violations mentioned. The claim was denied at every level.
After considerable delay, due to extensions requested by both sides, it
has been submitted to this board for resolution.
The Organization makes two basic arguments that require consideration:
(1) Claimant was required to accept the special assignment. Consequently,
it is clear on its face that he worked a schedule considerably different
from his regular assignment. Carrier is required to pay the appropriate .
penalties, as enumerated in regulations 4-B-1, 4-C-1, and 4-D-1.
Award Number 2347$ Page 3
Docket Number TD-22936
(2) Whether he was assigned the project or he agreed to do it makes no
difference. The contract is clear and unambiguous on all points
contested. Carrier cannot make a private deal with an employe to
transcend the requirements of the agreement. The Organization.is
the bargaining agent and has the right to require compliance with
the contract at anyy time.
The organization presented awards in support of its position.
Carrier argues that since the special assignment at issue here
is not covered under the agreement, any alleged violation of the agreement is inappropriate and has
It further argues that claimant has performed this same
assignment for the last eight or ten years, with no complaint from
him or the Organization. It finally argues that if claimant would
have voiced an objection when he was asked to work on the gross ton
mileage report, he would not have been required to do the job. Claimant
performed the work every year for the past eight or ten years with no
complaint. He set his own work schedule and his own rest days during
the period he was assigned to the project. Claimant should not now be
heard to say that a contract violation exists. Carrier should not pay
s penalty for an assignment that claimant volunteered to accept.
The record of this case reveals that claimant accepted the
assignmeqt,and,that he requested that his rest days be changed to coincide with the rest days of his
The recordAis barren of any probative evidence that claimant or the
Organization lodged a complaint about claimant's assignment to the
. project before-or during the one month he performed his duties. This
'-;-failure to complain can only be construed by carrier and this Boaxd
to mean that the parties involved did not consider the arrangement
between carrier and claimant in any way objectionable.
This Board is mindful of the line of cases that state that
individuals cannot make a private deal with a carrier that is violative
of the collective bargaining agreement. This Board subscribes to that
basic concept as essential to the stability of union-management relations.
It has so stated in many decisions in every Division.
Our decision in the instant case does not ^ontradict that
principal. Carrier and claimant have engaged in the same arrangement
for a period of eight to ten years. (The record is not precise on this
point, but it is agreed that the arrangement has existed for a long period
of time.) The Organization cannot now come forward and complain about such an
Award Number
23478
Page
4
Docket Number
TD-22936
arrangement by pressing a claim for penalty pay. The Organization,
by its acquiescence to the arrangement over such a long period of time,
has signaled the carrier that the arrangement in this particular case
would not be queried. To now file a claim to tell Carrier that the
arrangement that has existed for the last eight or ten years is no
longer acceptable is inappropriate and not acceptable procedure in
good faith labor relations.
If the Organization and/or the Claimant wanted to set
carrier straight on this issue, they should have, at the outset of
the assignment, made their objections known. Given the long period
of time during which the arrangement was accepted by the union, its
failure to file a complaint bars them from lodging an objection now.
FINDINGS: The Third Division of the Adjustment Hoard, upon the whole
record and all the evidence, finds and holds:
That the parties waived oral hearinEr,
That the Carrier and the Employes involved is this dispute
are respectively Carrier and Employes within the meaning of the Railway
Labor Act, as approved June 21,
1934;
That this Division of the Adjustment Hoard has jurisdiction
over the dispute involved herein; and
That the Agreement was not violated.
RE C E
vin <~''.
A W A R D
A
~~
2,
J ~9R~
Claim denied.
°9o Office . 6
NATIONAL RAILROAD ADiUSTMENT HOARD
By Order of Third Division
ATTEST:
i a.~.·~-·~
Executive Secretary
Dated at Chicago, Illinois, this 8th day of January
1982.
l