NATIONAL RAILROAD ADJUSTMENT BOARD

THIRD DIVISION


Herbert L. Marx, Jr., Referee

PARTIES TO DISPUTE:

Award Number 23678
Docket Number CL-23584

(Brotherhood of Railway, Airline and Steamship Clerks,
( Freight Handlers, Express and Station Employes
(
(Chesapeake and Ohio Railway Company



(a) The Carrier violated the Clerical Agreement when they did not apply the provisions of the General Agreement and Memorandum Agreement dated September 1, 1949 and arrange to allow E. I. Sheppe 2 days in excess of 251 Annual Work Days in 1976.

(b) The Carrier should now recompute E. I. Sheppe's pay for the year 1976 and allow him $137.66 for 2 days pay due to working 2 days in excess of the 251 Annual Work Days in 1976.

OPINION OF BOARD: The issue in this claim is identical to that considered
in Award 23589. The claim will be sustained on the
basis of that Award.



That the parties waived oral hearing;

That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and

That the Agreement was violated.

A W A R D

Claim sustained.

Attest: Acting Executive Secretary
National Railroad Adjustment Board

BY

o emarie Brasch - Administrative Assistant

NATIONAL RAILROAD ADJUSTMENT BOARD

By Order of Third Division


Dated ai; Chicago, Illinois, this 26th day of ?larch, 1932.
,' i

(/ :-~,




U y-_ v
i~


~~'~ u.i ~~ U

\,1.


~~ ~ J ~, r,