NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number
SG-24055
Martin F. Scheinman, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Consolidated Rail Corporation
STATEMENT OF CLAIM: "Claim of the General Committee of the Brotherhood of
Railroad Signalmen on the Consolidated Rail Corporation
(former Lehigh Valley Railroad) involving the question:
That Signal Maintainer John Eorio be paid for all benefits and
time lost due to his suspension from service for a period of sixty three
days commencing May
9, 198O.~
OP33ION OF BOARD: The Claimant, Signal Maintainer John Eoirio, after in-
vestigation,, was suspended for a period of
63
days commencing on May
9, 1980·
The Organization claims that Carrier failed to
establish that Claimant was guilty of any offense.
At the time of this discipline, Claimant was assigned as a Signal
Maintainer at South Plainfield Garage, South Plainfield,, New Jersey. His
regular tour of duty was from 7:00 A.M. to
3:30
P.M.
The incident which led to Claimant's discipline occurred on
may
8, 1980.
During that day Claimant performed signal revision work at
Krimko Switch., which was within his assigned territory. Carrier asserts
that Claimant performed this walk improperly. Specifically., it argued that
Claimant removed the signal circuits from the circuit controller without
proper paint protection. In addition, according to Carrier, Claimant failed
to perform the required testing of the signals system which, as a consequence
of the signal revision, showed a false proceed signal at Signal 191.
After discovery of the problem on Signal
191
on May
9, 1980,
Claimant was removed from service. As a result of this incident, Claimant was
notified to attend an investigation on May
16, 1980
is connection with the
following charges:
"Alleged violation - General Instructions C&S
23 #"(
Alterations or additions must not be made to any individual components or systems . iaral
_~-__~- _ _.
atus or circuits unless properly authorized.
"Alleged violation - General Instructions MS
23, X25 -
When any changes are made, sufficient tests shall be
performed promptly to assure signal system is functioning as intended. All such modifications shall
ms 4
by the responsible man making the
changes.
Award Number 24072 Page
2
Docket Number
SG-24055
...
"Alleged-violation - Changes and Tests Incident thereto
C&S
23 #25q
- Before final cutover, all circuits changed
must be thoroughly tested as far as possible, and final
arrangement must be tested in entirety by a supervisory
employee other than the man in charge.
"Insofar as you removed the signal circuits fray the
circuit controller at Krimko Switch, on may
8, 198o
leaving the snitch without point protection and not
properly tasting tie Signal System when work was completed. Resulting in a false pn'ooeed signal at
191
Signal location track +l, which was discovered by
Assistant Supervisor F. Wilxwaki on May
9, 1980."
On June
4, 198o,
her informed Claimant that he had bees found
guilty of the charges brought against him. He vas informed that he vas dismissed from Carrier's cerv
At a later date July 11,
1980,
Carrier informed the General Chairman
that the discipline imposed was to be changed to a suspension consisting of
all the time held out of service. As a result, Claimant returned to service
on July 15,
1980·
After reviewing the evidence on the record, we must conclude that
Carrier shouldered its burden of establishing that Claimant is guilty of
violating the rules quoted in the charge. Stated simply, we are persuaded
that Claimant failed to provide sufficient point protection an the Krimko
Snitch on May
8, 1980.
His actions resulted in a false proceed signal at
191
Signal which could have resulted in a serious accident. Nothing in the
record convinces us that Claimant's action vas appropriate.
The final question that remains is whether the imposed penalty is
appropriate. This Board has reputedly determined that it x111 not overturn
penalty assessed unless that penalty is arbitrary, capricious or excessive*
Given the seriousness of a proven offense, we are convinced that the penalty
here is not arbitrary, capricious or excessive. Thus, we will deaf te
claim in its entirety.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence., finds and holds:
That the parties waived oral hearing,
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the manning of the Railway labor
Act, as approved June 21,
1934;
Axard Number 24012
Docket Number SG-24055
Pace 3
That this Division of the Adjustment Board has jurisdiction
over the dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
ATTEST: Acting Executive Secretary
NATIONAL RAILROAD ADJOSTMENT BOARD
By Order of Third Division
National Railroad Adjustment Board
BY
o ~e~rie Breach - Administrative Assistant
Dated at Chicago,, Illinois this 20th day of October 1982.