(Brotherhood of Maintenance of Way Employee PARTIES TO DISPUTE:
                (Norfolk and Portsmouth Belt Railroad Company


STATEMENT OF CLAIM: As shows in Docket hb1-24804 and not repeated herein.

FaPDI1PGS: The Third Division of the Adjustment Hoard finds:

That the dispute was certified to the Third Division of the Adjustment Hoard ex pane by the complainant party; and

Under date of January 11, 1983 the complainant party addressed a formal communication to the Executive Secretary of the Third Division requesting withdrawal of thi which request is hereby granted.

                        A W A R D


          Case dismissed.


                            NATIONAL RAILROAD ADJIT3RMENT HOARD

                            By Order of Third division


ATTEST: Acting Executive Secretary
National Railroad Adjustment Hoard

      i Rosemarie Breach - Administrative Assistant


Dated at Chicago, nllnois, this 14th day of January 1983.