NATIONAL RAILROAD ADJUSTrFrrr BOARD
THIRD DIVISION Docket Number
Mb1-23749
Joseph A. Sickles. Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
Southern Pacific Transportation Company
(Pacific Lines)
STAT34ENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned the work of
constructing inspection pits at E1 Paso, Texas to outside forces be;gi
^n
January 2,
1979
(System File MofW
152-859).
(2)
The Carrier also violated Article IV of the May
17s 1968
National Agreement when it did not give the General Chairman advance written
notice of its intention to contract said work.
(3)
As a consequence of the aforesaid violation, the claimants*
each be allowed pay at their respective rates for an equal proportionate share
of the total number of man-hours
(2455
straight time hours and
2938
overtime
hours) expended liy outside farces.
*The claimants are:
WESTERN SENIORIT7C DISTRICT, H&8 GANG NO. 15
R. E. Daughtry Foreman
G. S. Romero Assistant Foreman
G. S. Branteliea Carpenter
E. 0. Durate Carpenter
M. A. Eldridge Truck Driver
R. M. Martinez Welder
EASTERN SENIORITY DISTRICT, B&B Gangs
No.
17
and 3
r
H&8 No.
17
Charles F. Miller Foreman
G. H. Gonzales Welder
R. C. Bogart Carpenter
E. I. Snelling Carpenter
Mike Harvey Carpenter
B&B No. 3
Robin Mills Foreman
Berkie Duncan Helper
Manny Parra Carpenter
Andy Rolnick Helper
Doug Sauer Tractor Operator"
Award Number
24136
Page
2
Docket Number
MYI-23749
OPINION OF BOARD: The Carrier submitted to the General Chairman (in
October of
1978)
a letter expressing as intention to
contract out the excavation of three
(3)
inspection pits and allegedly it
was stated that the remainder of the work would be performed by Carrier
forces.
Agreement was reached concerning the use of outside forces
however in the following January it is asserted that employer of the outside contractor were assigne
farms for concrete, welding, concrete works clean-up works etc.
In addition to its assertion that the Carrier violated the basic
Agreement when it contracted out the work in question the Employes insist
that the action of the Carrier far exceeded the stated intention concerning
excavation of three
(3)
pits and consequently Article 1V of the May 17.9
1968
Agreement was violated.
There is no question under this record that the Carrier gave
notice under Article IV but the dispute centers around the extent of the
work performed. Unquestionably if a Carrier gives s limited notification of
intention to sub-contract and the General Chairman agrees to certain walk
being performed in accordance with that notification there is nonethless a
violation if the Carrier extends the work far beyond the work originally
contemplated because in essence the Carrier deprives the Employes of the
right to present their views concerning the potential contracting out.
However here the Carrier insists that the original notification was augmented through various discus
contract out work significantly beyond the scope of the work discussed with
the Organization's representatives.
Essentially then the dispute presents a fact question for resolution
rather than a question of the permissible extent of work under Article IV of
the May
lTs 1968
Agreement. In the view of this Board the organization has
failed to establish by a substantive preponderance of the evidence that the
Carrier exceeded the stated extent of the work in question and as a matter of
proofs we will dismiss the claim.
FILINGS: The Third Division of the Adjustment Board.. upon the whole record
and all the evidence.. finds and holds:
That the parties waived oral hearing;
That the Carrier sad the Employes involved in this dispute are
respectively Carrier and Hnpl.oyes within the meaning of the Railway Labor
Act as approved June
21.. 1934;
Award Number
24136
Docket Number
MW-23749
Page 3
That this Division of the Adjustment Board has
over the dispute involved herein; and
jurisdiction
That the Agreement was not violated.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUS2aNT BOARD
By Order of Third Division
ATTEST: Assistant Executive Secretary
National Railroad Adjustment Board
By
o emerie Bras -Administrative Assistant
Dated at Chicago, Illinois this
27th
day of January 1983.