NATIONAL. RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-24259
George S. Roukis, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
Terminal Railroad Association of St. Louis
STATEMENT OF CLAIM: "Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it failed and refused
to allow Machine Operators B. Ellis and 0. Rodriquez pay at the Bridge and
Building Mechanic's rate for the work they performed on the 'Merchants Bridge'
beginning June 16, 1980 (System File TRRA 1980-16).
(2) Machinie Operators B. Ellis and 0. Rodriquez each be allowed the
difference between what
they should
have received at the Bridge and Building
Mechanic's rate and what they were paid at the machine operator's rate beginning
June
16,
1980 and continuing until the project is completed."
OPINION OF BOARD: The basic issue before this Board is the appropriate
application of the Controlling Agreement's Classification
Rule (Rule 2), particularly that portion delineated under the designation,
General Notes, Paragraph (b), which reads as follows:
"When machines manned by bulletined machine operators are used
in the Bridge and Building Department, the operators will
receive ironworkers (B&B Mechanics) rate of pay for the actual
time worked."
Claimants argue that they were assigned with their respective machines
to assist B&B forces in the replacement of bridge ties on Carrier's Merchants
Bridge and performed maintenance of bridge work, which entitled them to be paid
the ironworkers rate, in accordance with Paragraph (b) (Supra). In addition,
they contend that Rule 39, the Composite Service Rule, requires that employes
working in higher positions will be paid the higher rate for the actual time
worked.
Carrier asserts that Claimants were performing their assigned tasks
when operating the tie handler machines in effecting tie replacements, which
was work routinely performed by track machine operators within the Track SubDepartment. It argues th
rather than at ground level, is not B&B Ironworkers work in connection with the
construction, erection, maintenance and dismantling of bridges, buildings,
miscellaneous structures and appurtenances, but track maintenance work which is
their assigned duty.
In considering this case, the Board finds it difficult to determine
precisely whether the ties were inserted on a gavel deck approach or the open
Award Number 24264
Docket Number MW-21+259
Page 2
steel bridge. The claim as filed indicates that the tie replacement occurred
on both ends of the Merchants Bridge and as such, it could well be that the ties
were inserted in the subgrade vis the approach to the bridge. We recognize the
separation of work between the respective sub departments as set forth by Paragraph
(b) Supra, but we are not certain as to the exact location where the ties were
replaced. Without this evidence, we are unable to determine whether the aforesaid paragraph was viol
FINDINGS: The Third Division of the Adjustment Board, upon the whole record and
all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the
meaning of
the Railway labor Act,
as approved June 21,
1931+;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
Attest: Acting Executive Secretary
National Railroad Adjustment Board
NATIGNAL RAIIROAD ADJUSTMENT BOARD
By Order of Third Division
y
; Rosemarie Brasch - Administrative Assistant
Dated at Chicago, Illinois, this 23rd day of March
1983.
t~.l v a <b
~G
fit , .
Chica 9o