NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-24217
Martin F. Scheinman, Referee
Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Seaboard Coast Line Railroad Company
STATEMENT OF CLAIM: "Claim of the System Co~ittee of the Brotherhood that:
(1) The Agreement was violated when Welder Helper L. F. Griffis, Jr.
was compensated at his straight-time rate instead of at his time and
one-half
rate for the service he performed on certain dates during the period Au ust 1,
1979
through September 14,
1979
(System File C-4(36)-LFG/l2-35(80-14) H~.
(2) The Agreement was further violated when Welder Helper L. F.
Griffis, Jr. was not permitted to work his scheduled assigned hours on certain
dates during the above-mentioned claim period.
(3)
Welder Helper L. F. Griffis, Jr. now be allowed the difference
between what he should have been paid at his time and one-half rate and what he
was paid at his straight-time rate because of the violation referred to in
Part (1) hereof.
(4) Because of the.violation referred to in Part (2) hereof, Welder
Helper L.*F. Griffis, Jr. be allowed eight
(8)
hours of pay for each day he was
not permitted to work his scheduled assigned hours during the aforementioned
claim period."
OPINION OF BOARD: The essential facts of this case are not in dispute. At
the time this claim arose, Claimant, L. F. Griffis, Jr., was
regularly assigned as a Welder Helper to Welding Force
9079
with headquarters at
Jacksonville, Florida. His normal work week consisted of eight hours, Monday
through Friday, with Saturday and Sunday designated as rest days.
From the period August 1,
1979
through September 14,
1979,
Carrier
required Claimant to work with the Rail Gang at Tallahassee, Florida to temporarily
assist welders regularly assigned to that gang. During that six week period,
Claimant did not work his regular days and hours. Instead, along with the rest
of the Rail Gang at Tallahassee, Claimant's work week consisted of ten hour work
days, with some exceptions, and additional days off to compensate for those longer
work days.
As a result of the change in Claimant's work schedule, the Organization
filed this claim. In it, the
Organization alleged
that Carrier violated the
Agreement, particularly Rule 20(f), when it altered Claimant's work week. That
rule provides in relevant part:
Award Number
24265
Page 2
Docket Number MW-24217
"(f) DEVIATION FROM MONDAY - FRIDAY WEEK
If in positions or work extending over a period of
five days per week, an operational problem arises which
the Carrier contends cannot be met under the provisions of
Section (b), and requires that some of such employees work
Tuesday to Saturday instead of Monday to Friday, and the
employees contend the contrary, and if the parties fail to
agree thereon, then if the Carrier nevertheless puts such
assignments into effect, the dispute may be processed as a
grievance or claim under the current Agreement."
According to the Organization, the language of Rule 20(f) is clear and unambiguous.
It provides that only an "operational problem" can permit Carrier to alter
Claimant's regular Monday to Friday work week. Here, Carrier never contended,
that an operational problem did exist. Furthermore, the Organization maintains
that even if Carrier asserted that there was an "operational problem", it could
change Claimant's work days only if he or the Organization agreed to do so.
Clearly, no such agreement ever was secured or even attempted by Carrier.
In addition, the Organization argues that the Rules relied upon by
Carrier in support of its position clearly do not apply to Claimant. Those Rules -
Rule
38
and the April
31, 1971
Memorandum of Agreement - apply only to "make up
time" for employes stationed in a camp car. Rather, he is a welder helper with
stationary headquarters at Jacksonville, Florida. Thus, according to the
Organization, the April
1971
Memorandum does not apply to Claimant.
For these reasons, the Organization asks that the claim be sustained.
It seeks appropriate compensation for Claimant for hours and dates he was
required to work beyond his normal eight hour, Monday to Friday work week.
Carrier, on the other hand, insists that it acted in conformity with
the Memorandum of Agreement dated April
13, 1971
in this instance. The Memorandum
reads:
"IT IS AGREED:
That in the application of Rule
38,
Section I, System
Forces, in making up time for the purpose of accumulating
rest time for longer consecutive rest periods, may elect,
under the provisions of Section, to work up to ten (10) hours
on any calendar days to the extent that the total hours
worked in each half month, at no additional expense to the
Company, are the equivalent of the straight-time work hours
therein."
According to Carrier, the Memorandum specifically allows the Rail Gang to act as
it did in this dispute. That is, its hours may be increased from eight to ten
per day, with additional days off, at no expense to Carrier.
In addition, Carrier argues that there has been a consistent practice
on the property of assigning welders and welder helpers to assist rail gangs. In
many, if not all of these instances, the welders and welder helpers were assigned
Award Number
24265
Page
3
Docket Number NN-24217
to work ten hour days and four day weeks. This was done without protest from
the Organization. Thus, Carrier argues that the practice clearly supports its
position. It asks that the claim be denied.
It is true as the Organization maintained, that past practice, even if
proven, can not supersede clear contractual language. Thus, if only Rule 20 were
at issue here, we might well find for the Organization, even
though the
practice
is to the contrary.
However, here the April
13,
1971 Memorandum of Agreement is also at
issue. The Organization argued that it applied only to system forces housed
in camp cars. Carrier contended that welders assigned to assist rail gangs
were also covered by its provisions. Either view is tenable under the language
of the Memorandum since welders working with Rail Gangs are, arguably, part of System
Forces within the meaning of the Memorandum. Where such ambiguity exists, the
past practice on the property is instructive.
Here, the record evidence reveals that numerous welders and welder
helpers have had their work weeks altered in virtually the same manner as
Claimant. Furthermore, these changes were made without protest by the Organization
until after this claim was filed. Accordingly, we conclude that the language of
the Memorandum
supports Carriers position. Thus, under the facts of this case,
Rule 20 is in apparent conflict with the normal work week and exceptions thereto.
The Memorandum, however, allows for specific exception to the normal work week
where system forces are "making up" times. Such are the facts of this case.
Accordingly, the specific language of the 1971 Memorandum must prevail over the
general language of Rule 20, to the extent they are in conflict.
Awards cited by the Organization in support of its position are not
directly on point to the facts of this case. They deal only with the conflict
between clear Agreement language and contrary past practice. We agree with the
Organization that under those circumstances, clear language must prevail. Here,
however, the past practice of Carrier is instructive in interpreting the vague
language of the 1971 Memorandum. Furthermore, since that Memorandum specifically
covers the facts of this claim, it must prevail over the general language of Rule
20. Accordingly, the claim must be denied.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record and
all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispaite involved herein; and
That the Agreement was not violated.
Award Number 24265 Page 4
Docket Number rE·1-24217
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest: Acting Executive Secretary
National Railroad Adjustment Board
By
Rose
marie Brasc - Administrative Assistant
Dated at Chicago, Illinois, this 23rd day of March
1983.
ce~d~o
E' ~ ~P~ 2`1903 ~~c.. ,
e
e'
~~Chfco 9 o O(fc