NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number SG-24227
Ida Klaus, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Southern Railway Company
STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood of Railroad
Signalmen on the Southern Railway Company et a1.:
(a) Carrier violated the Signalmen's Agreement, particularly scope
Rule 1 among others, when C&S Supervisor
H. H.
Stanley and two employees of
Harmon Electronics, who are not covered by the Signalmen's Agreement and have
no contractual right to perform signal work, were permitted to megger cable
and test presence detectors in Sheffield Retarder Yard on May 20 and 21, 1980.
(b) Carrier should now be required to compensate Claimants Kimbrough,
Hamilton, Butler and Scott for a total of forty-eight (48) man hours to be
divided equally among each Claimant, in addition to any other pay they have
received, at their overtime rate of pay because of this loss of work opportunity
and because the Agreement was violated.
OPINION OF BOARD: The claim asserts that work performed by two outside employes
and a C&S Supervisor on switch-retarding devices violated
Scope Rule 1 of the Signalmen's Agreement. It alleges that the work should
properly have been performed by the Claimants.
The Carrier contends that the work of the two outsiders was not
covered by the Scope Rule, and that the Supervisor performed no signal work at
a11. It explains that a field test was conducted under a no-cost warranty by
employes of the outside supplier of the devices to resolve a malfunctioning
problem experienced with them. The C&S Supervisor, the Carrier says, was
assigned to provide a "liaison" function with the supplier.
The Organization argues that the work performed and the equipment
used were essentially within the duties of the Signalman craft.
On the entire record before us, we conclude that the Organization
has failed to produce adequate factual evidence to support its claim, or to
rebut the Carrier's apparently credible and material assertions as to the
warranty work and the nature of the C&S Supervisor's role.
Award Number 24613 Page 2
Locket Number SG-24227
It is the clear precedent of this Board that work performed under
warranty does not violate a scope rule (Award No. 23890). Moreover, we cannot
find on this record that the presence of the Supervisor as an administrative
contact for management was subject to the restrictions of the Scope Rule. The
claim must be denied.
FINDINGS: The Third Division of the Adjustment Board, after giving the parties
to this dispute due notice of hearing thereon, and upon the whole
record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J. Le v xecutive Secretary
Dated at Chicago, Illinois this 13th day of January 1984;