NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-24739
Robert Silagi, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(The Kansas City Southern Railway Company
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned or otherwise
permitted outside forces to construct a crossover switch at Beaumont, Texas
(Carrier's File 013.31-247).
(2) The Carrier also violated Article IV of the May 17, 1968 National
Agreement when it did not give the General Chairman advance written notice of its
intention to contract said work.
(3) Messrs. F. J. Caillier, A. Como, W. Hargrove and L. Leger each be
allowed pay at their respective rates for an equal proportionate share of the
total number of man-hours expended by outside forces in performing the work
described in Part (1) hereof.
OPINION OF
BOARD: During the latter part of 1978 Southern Pacific proposed
to the Carrier that the latter grant the former the right to
operate on Carrier's Yard main through wall Street to enable straight way
movements of Southern Pacific trains between the east and north. Such a proposal
involved track changes. An agreement was reached in November 1979 permitting
Southern Pacific to operate through the Wall Street Yard on Track No. 5. To
accomplish the connection at College Street, the existing crossover between
Carrier and Missouri Pacific main lines had to be relocated. Carrier's portion
of the existing crossover between Carrier and Missouri Pacific was removed by
Carrier's forces during the week of December 17, 1979. On January 7, 7980,
Missouri Pacific requested that the new crossover be returned to its original
location or that a new crossover be constructed farther west of its present location.
A week later Carrier informed Missouri Pacific that it would review the request
and advise Missouri Pacific of its decision. Missouri Pacific reinstalled the
crossover connection allegedly on January 29 and 30, 1980.
The organization contends that the installation of switches is work
encompassed within the Scope Rule in that it customarily and traditionally
13
performance of Maintenance of Way employes. Carrier does not challenge Claimants'
contractual right to do the work.
Award Number 24621 Page 2
Docket Number MW-24739
The organization further contends that Carrier violated Article IV of
the May 17, 1968 National Agreement which reads in
pertinent part:
"In the event a carrier plans to contract out work within
the scope of the applicable schedule
agreement, the
carrier
shall notify the General Chairman of the Organization involved
in writing as far in advance of the date of the contracting
transaction as is practicable and in any
event not
less
than 15 days prior thereto."
Carrier concedes that the work was done by outside forces, however, it
insists that such work was performed without advance notice to itself, without
its consent or knowledge and that it did not plan or contract with Missouri Pacific
to do the work. Moreover, Carrier asserts that the dates on which the work was
actually performed are not the dates for which the organization makes its claim.
Finally, Carrier argues that even if it violated the
Agreement the
Claimants are
not entitled to compensation because they were fully employed on and paid for the
claim dates.
An undated letter signed by all Claimants addressed to the General
Chairman of the Organization states that the work on the cross-over switch took
place on 3 days at the end of January 1981 and on 3 days in mid-February. Since
that letter was never made available to the Carrier while the claim was progressed
an the property, it will not be considered now (Award 14244). The claim dates
advanced by the Organization were February 10, 11 and 12, 1981. Carrier asserts
that the actual dates of work were January 29 and 30, 1981, according to records
of Missouri Pacific. Carrier did not produce said records. Its failure to
introduce such vital evidence into the proceedings when it either had the records
in its possession or could easily have obtained them invites the conclusion that
the evidence was unfavorable. (Award 14244) We are therefore left with conflicting
claim dates. Assuming, arguendo, that the work was indeed performed on two days
late in January 1981, we now examine the Organization's comment regarding said
work. According to the Organization the installation of a switch mandates that
the track be taken out of service for a considerable number of hours. It therefore
argues that Track No. 5 could not have been removed from service for such a
period of time without Carrier's knowledge and consent. Track No. 5, whether it
was a main line as contended by the Organization, or a non-main line as contended
by Carrier, ran through the Wall Street Yard. As such it was highly visible. It
is improbable that anyone could have taken the track out of service and installed
switch without Carrier's knowledge and consent. There is no evidence in the
record that Carrier attempted to stop Missouri Pacific once it learned of the
latter 's activities. Had an effort been made to halt the outside forces from
installing the switch, Carrier's argument about its lack of knowledge, consent
rind plans to contract out work would carry greater weight. Given all the
circumstances of the preliminary negotiations between Carrier and Missouri Pacific,
the timing of those negotiations end the dates on which the work was performed,
we conclude that Carrier's conduct in tolerating the work without objection,
manifested implied consent and knowledge of an act which infringed upon Claimants'
rights.
Award Number 24621 Page 3
Locket Number MW-24739
Carrier argues that the failure to specify the precise dates on which
the work was performed is fatal to the claim. The record does not show that
Carrier had any difficulty in identifying the incident which precipitated the
claim. Nor did Carrier allege surprise or inability to prepare a proper defense
because of the alleged errors in claim dates. This Board has often held that a
charge against an employe in a disciplinary case is adequate if it reasonably
apprises the employe of the set of facts or circumstances under inquiry to
provide an opportunity to prepare a defense and prevent surprises. (Award 12255
- Seff) Elementary fairness indicates that a similar rule may be invoked against
the Carrier, especially in this case where neither party produced irrefutable
evidence as to the actual claim dates.
We turn now to Carrier's argument about compensation. Carrier argues
that Claimants may not receive compensation because they were fully employed
during the claim period. The organization argues that the assignment of this
work to outside forces resulted in loss of work opportunity and related monetary
benefits to Claimants. We agree. See Awards 12785, 15689, 15888 and others.
"This Board is not precluded from granting compensation for the loss of opportunities
of earnings resulting from the contracting out of work
...°
(Award 16009).
The claim is sustained and compensation shall be paid to Claimants as
requested in Claim (3).
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employe within the meaning of the Railway Labor Act, as
approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was violated.
A W A R D
Claim sustained.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
~~ · "
Nancy ver - Executive Secretary
Dated at Chicago, Illinois this 13th day of January 1984.