NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Locket Number SG-25018
Marty E. Zusman, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Southern Railway Company
STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood of Railroad
Signalmen on the Southern Railway Company et al.:
(a) Carrier violated the Signalmen's Agreement, particularly Rule 37
and Rule 4 among others, when Signal Maintainers E. L. Tucker, D. A. Riley and
G. C. Morris cleared signal trouble on the assigned territory of Signal Maintainer
Davis when he was available from 2 PM to 6:30 PM on November 22, 1981 and was
being held for call under the provisions of Rule 37. The signal trouble was
near MP S-166.2 on Signal Maintainer Davis, assigned territory.
(b) Carrier now be required to compensate Signal Maintainer T. C.
Davis for four and one-half (4 1/2) hours at his overtime rate of pay that he
was denied on November 22, 1981, from 2 PM to 6:30 PM because the agreement was
violated and because Signal Maintainer Davis was available and was held for
call under Rule 37 but was not called.
(General Chairman file: SR-277. Carrier file: SG-5371
OPINION OF BOARD: Claimant T. C. Davis, a Signal Maintainer, was held on
call on November 21, 1981 and November 22, 1981. This fact
is not disputed. Claimant was paid his pro rata for each day worked and was
paid overtime and had used up his allowable hours of work under the Hours of
Service law. The instant dispute arose when on November 22, 1981 at 8:00 a. m.
and at 8:30 a.m. three signalmen were called up for service when trouble occurred
on the Claimant's assigned territory. The specific dispute is derived from the
fact that Claimant Davis was again available for service at 2:00 p.m. when the
restriction imposed by the Hours of Service law was no longer in effect. Since
the work begun on his territory was not completed until around 6:30 p.m., the
claim is for four and one-half hours (4 1/2) at overtime pay in which the
Claimant was not called while work was being performed on his territory.
It is the determination of this Board after a complete review of Rule
37, Rule 4 and a thorough consideration of the facts that the Carrier violated
no rules. The work was begun on Claimant's assigned territory when the Claimant
was restricted from service. This Board has previously held that a vacancy is
treated as a single entity and therefore considered for its entire duration
(Third Division Awards 11497, 15593). The Carrier had the right to expect
those employes it had properly called to perform the work, to complete the
work. There is nothing in the Agreement between the parties which requires or
allows the Carrier to replace an employe who has begun work or add an employe
after the work has begun, who is not needed, merely because somewhere in the
course of the work the Claimant has become available. After full consideration
of the facts before the Board in the case at bar, this claim is found to be
without merit and denied.
Award Number 24966 Page 2
Docket Number SG-25018
FINDINGS: The Third Division of the Adjustment Board, after giving the parties
to this dispute due notice of hearing thereon, and upon the whole
record and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J. ~ - Executive Secretary
Dated at Chicago, Illinois, this 14th day of August 1984.