NATIONAL RAILROAD ADJUSTMENT BOARD
Award Number 24985
Docket Number MW-25076
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Seaboard Coast Line Railroad Company
STATEMENT OF CLAIM: As shown in Docket No. MW-25076 and not repeated herein.
FINDINGS: The Third Division of the Adjustment Board finds:
That the dispute was certified to the Third Division of the Adjustment
Board ex parte by the complainant party; and
Under date of August 29, 1984, the parties addressed a formal communication
to the Executive Secretary of the Third Division requesting withdrawal of this
case from further consideration by the Division, which request is hereby granted.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST: z
Nancy J er - Executive Secretary
Dated at Chicago, Illinois, this 12th day of September 1984.