· - . ·',~'\s NATIONAL RAILROAD ADJUSTMENT BOARD
Award Number 25059
E
\` THIRD DIVISION Docket Number SG-24629
· i
0
Ida Klaus, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Southern Pacific Transportation Company (Western Lines)
STATEMENT OF CLAIM: "Claim of the General Committee of the Brotherhood of
Railroad Signalmen on the Southern Pacific Transportation
Company:
On behalf of Signal Foreman A. A. Perry, Leading Signalman J. C.
Holmes, and Signalmen H. D. Williams and R. E. Wierema, for 24 hours' pro rata
pay each account Carrier using a contractor (Stienly Electric Inc.) to install
signal PVC conduit at Mile Post 37.1 for the widening of Highway 237, Mt. View,
California." (Carrier file: SIG 152-428)
OPINION OF BOARD: This claim concerns signal cable work contracted out by the
Carrier in connection with the relocation of an underground
circuit along a Carrier right of way. The claim alleges that the use of outside
employes to perform the work violated the Scope Rule of the Signalmen's Agreement.
The disputed work was performed by the outside employes on February
10, 11 and 12, 1981. The claim was initiated by letter dated May 3, 1981, and
received two days later.
As its preliminary response, the Carrier alleges that the claim is
time barred under the 60-day limitation prescribed by the Agreement. Citing
Rule 60(a) of the Agreement and Section 3, First (i) of the Railway Labor Act,
as amended, the Carrier holds the claim to have been improperly initiated and
thus beyond the jurisdiction of this Board to entertain it.
Rule 60(a) specifies that claims must be presented "within 60 days
from the date of the occurrence on which the claim is based".
The Carrier considers the applicable date of occurrence to be the
three days of February 10-12, 1981, when the work under challenge was performed.
Thus it counts 82 days as the time elapsed between those dates and the receipt
of the claim.
In the petitioner's view the operative date marking the start of the
60-day period is the day on which the signal force first became aware of the
disputed work, which was March 27, 1981, the day the signal gang installed the
completed cables on the Carrier's right of way. By that reckoning, the claim
was initiated well within the prescribed period.
The Board must reject the petitioner's reasoning. The act complained
about is the improper performance of work. That act is the contractual violation
on which the claim is based. The date on which the act took place marks the
beginning of the 60-day limitation period for initiating the claim. The date
~a c s v~
Award Number 25059 Page 2
Docket Number SG-24629
NO Y $ 1984
i
of the discovery of the violation is not the critical contract 4"t~l~/
which to measure the start of the 60-day period. Indeed, we note
was, in fact, ample time from the alleged date of discovery to initiate a
proper claim, but the petitioner did not move to do so until the prescribed
time had elapsed.
Accordingly, we must hold that the claim was untimely presented and
that it is improperly before this Board. We are without authority to consider
it.
The claim must be dismissed for lack of jurisdiction.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record and
all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the claim is barred.
A W A R D
Claim dismissed.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
Nancy J ;'lower - Executive Secretary
Dated at Chicago, Illinois, this 4th day of October 1984.