NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-24995
Edward L. Suntrup, Referee
(Brotherhood of Maintenance of Way
PARTIES TO DISPUTE:
(Southern Pacific Transportation Company (Western Lines)
STATEMENT OF CLAIM: ·CZaim of the System Committee of the Brotherhood that:
(1) The Carrier violated the
Agreement when
it assigned Mechanical
Department forces instead of Bridge and Building Department forces to construct
a wash rack at Roseville, California June 24, 1981 through September 30, 1981
(Carrier's Files MofW 152-930, 932, 927).
(2) As a consequence of the aforesaid violation, B&B Welders T. A.
Freeman and J. Pascuzzi shall each be allowed six hundred fifty-three and onethird (653-1/3) hours of pay at their respective straight-time rates and B&B
Welder M. Petty shall be allowed fifty-three and one-third (53-1/2) hours of
pay at his straight-time rate."
OPINION OF BOARD: On August 10, 1981, September 8, 1981 and November 6, 1981
the Organization filed pay claims which cumulatively ran
from June 24, 1981 through September 30, 1981 for Claimants J. Pascuzzi and T.
A. Freeman. The claim dated November 6, 1981 also sought relief for Claimant
M. Petty. The claims, which were disallowed by the Carrier on the first instance,
and on appeal, alleged violation of the provisions of the current Agreement
when the Carrier assigned Mechanical Department employes to perform work
'...
of the nature which is customarily, historically and traditionally performed by
Bridge and Building Sub-Department employees on a system-wide basis". The work
in question consisted in the design, cutting and assembling of a wash rack for
servicing and cleaning locomotive diesel units at the east end of the Carrier's
Diesel Shops at Roseville, California.
It is an established precedent that the burden of proving a claim
according to the standards of substantial evidence acceptable to the National
Railroad Adjustment Board lies with the moving party. A review of the record
shows that the pertinent Rules of the Agreement between the Organization which
is party to this claim and the Carrier provide possible jurisdiction over the
work in question. But the record also shows that Rule 62 of the Agreement
between the Carrier and the Boilermakers appears to reasonably provide
jurisdiction to those employes over the work at bar. The Board can find,
therefore, no support in the record on the basis of contract to permit a
conclusion with respect to the Claimants' exclusive right over the work.
In terms of past practice it does appear to be true, from the record,
that the building of wash racks at the Carrier's Roseville, California facility
had been the exclusive purview of the B&B forces in the past and that this was
the first time that the Mechanical Forces at that point in the system had built
such a structure. This is attested to by documents signed by employes working
under both Agreements and this is not denied by the Carrier. The intent of the
claim goes to the issue of system-wide application of the B & B Agreement. The
record, however, shows that the Carrier had similar 'wash racks and/or scaffolds
Award Number 25077 Page 2
Docket Number MW-24995
...
built by
...
Mechanical Department employees ... at both Eugene, Oregon and
Ogden, Utah
...-
Verification of this is contained in the record under the
signature of the Plant Manager at Eugene Oregon. In the case of the Eugene,
Oregon structure, which was built approximately a year before the claims
relative to the instant case were filed, the B & B forces assisted by mounting
the structure to an existing
cement walkway
floor, but the Mechanical
Department employes built the structure. The Board cannot, therefore, find
sufficient evidence of probative value in the record to warrant conclusion that
the work in question is reserved, in terms of system-wide exclusivity, to the
craft herein claiming such. And such evidence is required in cases of this
type (Third Division, 21854; Public Law Board No. 3348; Award No. 1).
Any new information or arguments found in either Submission to this
Board which had not been exchanged by the parties during the handling of this
case on property is inadmissable (Third Division, 21463, 21841).
FINDINGS: The Third Division of the Adjustment Board, upon the whole record and
all the evidence, finds and holds:
That the parties wavied oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the
Agreement was
not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST:
Nancy J. er - Executive Secretary
Dated at Chicago, Illinois, this 4th day of October 1984.