PARTIES TO DISPUTE:


STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:

(1) The Carrier violated the Agreement when it laid off Messrs. J. Vermulen, J. Walling, J. Helgren, M. Wilcoxen, J. Foucault and J. Benson on December 9, 1980 without benefit of five (5) days' advance notice (System File ELS-1678).

(2) President John Larkin failed to disallow the claim (appealed to him under date of May 2, 1981) as contractually stipulated within Rule 52(a).

(3) As a consequence of either or both (1) and/or (2) above, the claimants shall



OPINION OF BOARD: The relevant facts of this claim are not in dispute. In
December 1980, Claimants were employes of Carrier holding seniority in their respective classes within the Track Sub-Department. They were regularly assigned to a rail gang working in the Upper Peninsula of Michigan. On December 9, 1980, Carrier notified Claimants that they were laid off at the end of their regular work period on that date.

The Organization contends that Carrier should have given Claimants five (5) working days' advance notice of force reduction in accordance with Rule 9(b) of the Agreement. That rule reads:



The Organization maintains that Claimants were regularly assigned employes. They are not casual employes; nor were they substituting for regularly assigned employes. Thus, the organization reasons that Claimants were entitled to five days' advance notice when they were laid off in December 1980. Accordingly, it asks that the claim be sustained.

Carrier, on the other hand, denies that it violated the Agreement. First, Carrier points out that the Organization did not file an appeal to this Board until some two years after the Organization appealed Carrier's original denial of the instant claim. In Carrier's view, this delay constitutes laches. Thus, Carrier reasons that the claim should be dismissed on this ground alone.

                    Locket Number MW-25091


Second, Carrier asserts that the claim was not filed until March 8, 1981, more than sixty days after the date of the alleged violation, December 9, 1980. Therefore, Carrier concludes that the claim should be rejected because it was not filed in a timely manner.

As to the merits, Carrier maintains that Claimants were verbally notified that their jobs would be abolished with the first snowfall. Accordingly, Carrier suggests that it complied with Rule 9(f) in that Claimants had advance notice that they would be laid off. Accordingly, Carrier contends that the claim should be denied on its merits as well as on procedural grounds.

A review of the record evidence convinces us that the claim must be sustained. This is so for a number of reasons.

First, we note that Carrier did not respond to the Organization's appeal of Carrier's denial of the claim in May 1981. Under.these circumstances, the Organization cannot be found guilty of laches. The delay in the Organization's appeal to this Board was caused in part, by Carrier's failure to respond to the organization's prior appeal. Thus, we reject Carrier's contention that the claim should be rejected on the basis of laches.

As to Carrier's other arguments, we note that the record evidence reveals that Carrier failed to raise these issues on the property. That failure bars this Board from considering these arguments. Had they been raised on the property, they might have constituted valid defenses against the Organization's claim. However, they cannot be considered here. Thus, we are compelled to sustain the Organization's claim.

        FINDINGS: The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds and holds:


        That the parties waived oral hearing;


That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1939;

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and

        That the Agreement was violated.

                Award Number 25121 Page 3

                Locket Number MW-25091

                A W A R D


        Claim sustained.


                            NATIONAL RAILROAD ADJUSTMENT BOARD

                            By Order of Third Division


Attest,
        Nancy ,7.,j5ever - Executive Secretary


Dated at Chicago, Illinois this 9th day of November 1984.