NATIONAL RAILROAD ADJUSTMENT BOARD
Award Number 25146
' THIRD DIVISION Docket Number MW-24009
Wesley A. Wildman, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(The Denver and Rio Grande Western Railroad Company
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The discipline (sixty demerits) imposed upon B&B Painter D. L.
Pisarczyk for alleged "use of improper tool· on December 18, 1979 was arbitrary,
unwarranted, without just and sufficient cause and on the basis of unproven
charges (System File D-4-80/MW-19-80).
(2) The claimant's record shall be cleared of the charge leveled
against him.
OPINION OF BOARD: Claimant in this case is a B and B Painter with sixty demerits
assessed against his record by carrier for alleged use of
improper tool on the job.
On the day of the charged transgression, a group of four employes,'
two from the B and B crew (including Claimant) and two from a Section crew,
were engaged in pulling lag screws and rolling planks to clear a crossing in
Pueblo, Colorado. Claimant alleges that while attempting on this day to remove
a lag screw with a claw bar, a sudden slip of the end of the bar out from under
the head of the screw resulted in a fall which caused an injury to Claimant's
back.
The tools available to, and primarily employed by, this group for
pulling the lag screws on the shift in question consisted of claw bars and
track wrenches. These tools had been brought to the job site and provided by
the Section crew members, rather than by the B and B crew team who were part of
the work group. The record discloses that somewhat more sophisticated (and,
under certain circumstances, safer) equipment exists for the pulling of lag
screws, namely, ratchet wrenches and drift jacks used in
conjunction with
claw
bars.
The record makes it clear that ratchet wrenches and drift jacks are
in the possession of, and normally available only to, B and B crews. When
Section crews pull lag screws, they typically employ only the equipment which
was being used on the day in question, i.e., claw bars and track wrenches.
There is conflicting testimony on the record as to whether the two B
and B men (including Claimant) were instructed by supervision to take their own
(optimum) B and B equipment for pulling lag screws, or whether they were told
that adequate equipment would be available on the job site. Also, the record
1 is unclear concerning the availability of properly operating lag screw pulling
equipment at the B and B garage at the time the B and B team left for the crossing
site.
Award Number 25146 Page 2
Docket Number MW-24009
In any event, whether the B and B team could have or should have
taken their own equipment for pulling lag screws to the job site is not, in the
opinion of this Board, a critical issue in this case. It seems unarguable to
us from the record that the utilization of the Section crew's equipment by this
entire work group on this shift clearly constituted at least minimally normal
and acceptable (although not necessarily best) practice and procedure in terms
of both safety and efficiency for the pulling of lag screws. Perhaps when B
and B crews do lag screw pulling with their own more sophisticated equipment
they do it more efficiently and safely. However, apparently Section crews
routinely do lag screw pulling in a manner we must infer is acceptable to the
Carrier, utilizing precisely the same equipment which was available and employed
on the shift in question. Certainly, that threshold with respect to safety at
which a refusal by Claimant to perform would have been legitimate or countenanced
by Carrier was not reached.
Carrier has made much of the fact (and justifiably so) that Claimant
made a de facto admission against interest with regard to the safety issue when
he was quick to state on his accident report that the cause of his alleged
injury was an improper tool. Moreover, Carrier points out, wholly aside from
what was evidently the initial and larger concern as to whether the appropriate
type of equipment had been employed by Claimant, Claimant asserted at the
hearing on the property that excessive wear on the claw bar had caused the
slip, implying that his accident report reference to "improper tool' was meant
to designate the defective (worn) claw bar he was using on the shift in question.
Carrier asserts that, in that event, Claimant had an obligation, per applicable
safety rules, to inspect his claw bar before use and not to proceed if he found.
it worn to the point where it might present a safety hazard.
Given the entire record in this case one might speculate, somewhat
uncharitably, that Claimant's easy assertions of improper tool" as a cause of
injury were meant to assure that his back condition would be accepted without
question as having been the result of the alleged accident and thus job related.
Be that as it may, however, we have just found that with regard to type of
equipment employed on the day in question, in fact no obvious or palpable
safety hazard existed which should have cautioned an employe against proceeding,
despite any inferences one might try to draw from Claimant's mildly
self-incriminating
statements on his accident report. Similarly, despite Claimant's testimony
regarding ·wear' on the claw bar discovered after the fact of the slip, there
is no substantial evidence on this record of any defect in the claw bar obvious
to warn the average employe against its use.
Much evidence on the record as to when it first became apparent that
Claimant was injured, or whether Claimant officially notified Carrier of his
injury in timely fashion, indicates that Carrier was obviously dubious (possibly
with good reason) as to whether any mishap with the claw bar actually occurred
which could have been the cause of Claimant's subsequent back condition. However,
the question of job relatedness of Claimant's back condition (i.e., whether any
accident actually occurred as alleged), whether Claimant timely and properly
reported the alleged accident, etc., are issues clearly not before the Board in
this case. The only question we have is, has Carrier established that Claimant,
whether as a result of mis- or mat-feasance (carelessness or willful, conscious
error), departed from at least minimally acceptable safe practices with regard
to the use of tools on the day in question. The answer of the Board is no.
Accordingly the claim must be sustained.
Award Number 25146 Page 3
Docket Number MW-24009
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor Act,
as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was violated.
A W A R D
Claim sustained.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
G
Attest:
Nancy J.: Dever - Executive Secretary
Dated at Chicago, Illinois this 9th day of November 1984.