NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Locket Number MS-25386
James Robert Cox, Referee
(F. S. Trevizo
PARTIES TO DISPUTE:
(Union Pacific Railroad Company
STATEMENT OF CLAIM:
1. Whether I was dismissed from the service of the Union Pacific
Railroad Company in violation of Rule 48 of the BMWE .gchedule Agreement and assessed
a 90-day suspension as the result of alleged insubordination for failing to operate
speed swing crane PSS-83, when ordered to do so by supervisor J. W. KELLY,
when I had already been given general instructions by general foreman G. Moreau, to
operate the DTL-78 machine, and whether I am entitled to pay for all the time lost
while serving the 90-day suspension.
2. Whether Union Pacific violated Rules 1, 15, 15(d), 20, and 20(e) of
the BMWE Schedule Agreement, when on January 7, 1982, when junior employee B.
Westley was awarded the REO-ATC CLlll operator's position, instead of me, when I
have a seniority of July 17, 1967 and am qualified to operate the machine while
Westley only has a seniorty date of March 4, 1981, and whether I am entitled to
be compensated for the difference between the ATC-3 CL k1 position of pay and
my DTL-78 rate of pay.
OPINION OF BOARD: June 17, 1982, Claimant Trevizo was working on Extra Gang 5982
as a Roadway Equipment Operator at Yermo, California.
Claimant argues that he was improperly removed from service under
Rule 48 of the BMWE Schedule Agreement before a Hearing was held since he had
not refused to work but continued to operate the DTL-78 Machine he had been
previously instructed to run by General Foreman Moreau instead of following the
direction of Foreman Kelly to operate the PSS-83 Machine.
When Claimant initially came to work that morning, he had informed
Foreman Kelly that he was not going to run two machines anymore. He asserted
that he was to be assigned to one machine and that was the machine he was going
to operate. The Foreman testified Trevizo told him that he had been assigned
by General Foreman Moreau to smooth the roadway, taking panels out between
tracks 6 and 8.
Foreman Kelly stated that Holman first asked Trevizo to operate the
Speed Swing about 9:15 A. M., his response was that he was grading the roadway
and was not going to operate the Speed Swing.
Staff Engineer Holman, who replaced vacationing General Foreman Moreau
that day, said that when he asked Trevizo if he would run the Speed Swing PSS83, Trevizo refused, co
Swing. There is no claim that Claimant was unqualified to run the Crane. A
short time thereafter, Holman returned again, repeated the order and Trevizo
again refused. The Carrier needed the Speed Swing Crane to facilitate the
replacement of two rails.- No other qualified Operator was available.
Having a qualified Operator operate more than one machine during a
work day was not unusual and in fact had been frequently done, according to the
evidence.
Award Number 25197 Page 2
Locket Number MS-25386
Trevizo admitted that he refused to run the Crane "because I had a
lot of work to do" and acknowledged that he understood that Holman, as a
Supervisor, had given him an order and that he had a responsibility to operate
any machine a Supervisor asked him to operate so long as he was qualified.
Claimant also conceded that he was working under the direction of
Kelly and that, when Kelly told him to run the Speed Crane, he told him he was
not going to run it because he had work to do on his machine and was tired of
running both machines for a long time -- "that I wasn't very secure running
both machines at the same time; that I thought it was unsafe for me to be
running both machines at the same time... for months I have been running both
machines
...."
He contends he told Holman something different -- that he could
not run the Crane because that machine was not his responsibility and he had
work to dq with his Front-end Loader.
The evidence indicates that Claimant refused three separate requests
to operate the Crane. He refused to perform the work as assigned giving different
reasons for such refusal as the disciplinary process continued. Claimant's
refusal to follow a work assignment was clearly a refusal to work within the
meaning of Rule 48. There is insufficient evidence that running two machines,
a task Claimant had been performing by his own admission for about four months,
was an unsafe practice. Trevizo had an obligation to perform the work assigned
and then grieve. Under these circumstances we find that the Carrier had just
cause for the suspension.
Trevizo's second claim involves his application for the position of
Operator of a Hydraulic Rough Terrain Truck Crane, ATC-3CLk1, a job awarded to
a less senior employe -- Mr. Westley -- January 7, 1982.
Claimant argues that even if he were not qualified, since he was the
most senior applicant, he should have been temporarily assigned to the position
for thirty days under Rule 20(e). Moreover, he asserts that he was "better
qualified" than Westley since he, not the junior man, had qualified to run
machines similar to the ATC-3CL##1.
Under Rule 10(b) employes applying for the position of Operator within
the Roadway Equipment Sub-Department will not be assigned until "considered
qualified by the Supervisor of Work Equipment". The evidence did not establish
any basis for a determination that Claimant was qualified for the position he
sought. Only where there is a reasonable expectation of qualification should
an applicant be temporarily assigned under 20(e).
FINDINGS: The Third Division of the Adjustment Board, after giving the parties
to this dispute due notice of hearing thereon, and upon the whole record
and all the evidence, finds and holds:
That the Carrier and the Employes involved in this dispute are respectively
Carrier and Employes within the meaning of the Railway Labor Act, as approved
June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
Award Number 25197 Page 3
Docket Number MS-25386
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
,
0010
Attest:
4angr
Nancy er - Executive Secretary
Dated at Chicago, Illinois this 11th day of January 1985.