PARTIES TO DISPUTE:



STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:

(1l The Carrier violated the Agreement when it assigned hauling, grading, cutting and burning work in connection with the 'Allentown Yard Project" to outside forces (System Locket LV-138).

(2) The claim as presented by District Chairman R. M. Koval on March 5, 1979 to Division Engineer R. C. Archihofsky shall be allowed as presented because said claim was not disallowed by Division Engineer R. C. Archihofsky. in accordance with Rule 5-c as amended.

(3) As a consequence of either or both (1) and/or (2) above the furloughed claimants shall each be allowed



OPINION OF BOARD: By specific letter of Agreement between the Organization
and Carrier over the contracting of work to be done at the
Allen town Yard in Allentown, Pennsylvania, it was agreed on September 8, 1978
in part that 'no Track Department employees in the Seniority District will be
furloughed" while contractor's forces were still working the Allentown Yard.
On March 7, 1979 the Carrier received by certified mail a claim on behalf of
wall people, furloughed on February 23, 1979 and all furloughed people on the
February 28, 1979 job abolishment. On March 12, 1979 the District Chairman
sent a second letter to the same Division Engineer with whom the claim had been
initiated. That letter referenced forty-two (42) furloughed Track Department
employes for whom the claim of eight (8) hours per day at their appropriate
rates of pay should be paid. After receiving no response the District Chairman
sent a letter of May 18, 1979 requesting Carrier payment due to the merits of
the claim and also "due to the violation of time limits involved". These time
limits state that claims must be filed by the Organization *within 60 days from
the date of the occurrence· of the claim, be responded to by the Carrier if
declined 'within 60 days from the date same is filed ·, or 'the claim or grievance
shall be allowed as presented. The Organization maintained Carrier violation
of the time-limit provisions of Rule 5-C as amended in the controlling Agreement
and therefore argued the claim should be allowed.

                    Locket Number MW-25254


On June 19, 1979, Carrier's Manager of Labor Relations, responded to the organization's request for payment. In that response, he indicated that the claim had been denied in a letter of April 5, 1979 by the Division Engineer and therefore there was no violation of the Time Limit on Claims. The facts of the claim were disputed and appealed by the Organization up to and including the highest Carrier Officer designated to hear such appeals. Not being resolved this claim is now properly before the Third Division of the National Railroad Adjustment Board.

The central issue in the case at bar, lies not in the merits of the case, but in the procedural issue of the alleged time limit violation and the conflicting evidence in the record as handled on property. The Organization claims that it never received the letter of April 5, 1979 to disallow the claim. The Carrier claims that the letter was sent by the U. S. postal service and it produced a copy of the letter from its files, unsigned by the Division Engineer, which responds to the undated letter of March 5, 1979 and denies the claims.

In ruling on this procedural issue, this Board must consider both precedent and substantial evidence of record. There is considerable past precedent that it is the responsibility of Carrier to unequivocally assure that letters of declination are properly delivered to the appropriate organization official within the stated time limits (Third Division Awards 10173; 11505; 14354; 16163; 25100). With respect to substantial evidence, this Board has long held that assertions alone that letters have been mailed wi1.I not suffice. Specific to the case at bar where such problems have already occurred, it is even more incumbent that attention be paid to the issue of meeting the evidence test that such letters were sent as argued. Carrier assertions alone that letters were mailed, even when copies of such letters are produced, do not provide the necessary evidence required in cases of dispute which come before this Board (see Third Division Awards 17291, 10173, 10742).

Therefore, the claim must be sustained on procedural grounds. Carrier objections to the claim as 'vague and indefinite' or failing to indicate "how claimants were effected' have been carefully reviewed and are dismissed as this claim is in the mind of this Board, lacking any procedural deficiency. In addition it should be noted that discrepancies found in the record between the materials presented on property and those presented to the Board by either party in their Submissions have been dealt with by treating the latter as inadmissible.

As such, considering the record as developed on property, this Board firmly holds that from February 23, 1979 through and to include, February 28, 1979, each of the forty-two (42) Claimants listed by letters of March 12, 1979 and July 18, 1979, shall be allowed payment as requested in part (3) of the Claim.

        FINDINGS: The Third Division of the Adjustment Board, upon the whole record and all the evidence, finds and holds:


        That the parties waived oral hearing;

                    Award Number 25309 Page 3

                    Locket Number MW-25254


That the Carrier and the Employes involved in this dispute are respectively Carrier and Employes within the meaning of the Railway Labor Act, as approved June 21, 1934;

That this Division of the Adjustment Board has jurisdiction over the dispute involved herein; and

        That the Agreement was violated.


                        A W A R D


        Claim sustained.


                          NATIONAL RAILROAD ADJUSTMENT BOARD

                          By Order of Third Division


Attest:
        Nancy J r - Executive Secretary


Dated at Chicago; Illinois, this 28th day of February 1985.