NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Locket Number MW-25222
Edward L. Suntrup, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Southern Pacific Transportation Company (Western Lines)
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it used other than carpenters
to perform carpenter's work at Eugene, Oregon October 6 through October 9, 1981
(Carrier's File MofW 152-936).
(2) Because of the aforesaid violation, furloughed Carpenters R. J.
Judd and W. L. Cutshell shall each be allowed ten (10) hours of pay at the
carpenter's straight time rate.
OPINION OF BOARD: By letter dated November 1, 1982, a claim was filed on behalf
of two senior Class A Carpenters on furlough status for ten
hours straight time rate each. The claim alleges that other than Class A Carpenters
were assigned to the building and erecting of a wood and metal roof over an existing
concrete slab adjacent to the Carrier ·s B&B shop and office building at Eugene
Yards, Eugene, Oregon. The work allegedly took place between October 6, 1981,
'and October 9, 1981.
The Carrier does not deny that the work in question was performed on
the dates in question, or that it was not performed with the assistance of the
B&B Foreman and Assistant Foreman. It is the position of the Carrier that the
latter are not prohibited from doing such work by the Agreement. It is the
further contention of the Carrier that past practice on this property is such
that "Foremen and Assistant Foremen have always assisted in the performance of
B&B cork, the same as Track Foremen and Water Service Foremen throughout the
Western Lines on the Southen Pacific Transportation Company" (Letter of January
14, 1983). The Carrier is also in disagreement with the Organization on exactly
how long it took to do the work in question.
A review of the record shows that while the claim references a number
of different Rules of the current Agreement which the Carrier allegedly violated
because of the work performed between October 6-9, 1981, the claim appears to
lean heavily on Rule 1 which is the Scope Rule. An examination of that Rule
shows, however, that it is a general classification Rule and as such cannot
provide support for a claim such as the instant one. This Board has ruled numerous
times in the past that such a Rule does not provide exclusive grants of work to
each classification listed under the Rule (Third Division Awards 12501, 12668, 12949).
Award Number 25350 Page 2
Docket Number MW-25222
The Organization also argues on the basis of current Agreement Rules 3, 5 and
26(f) which address the issues of classes, seniority and wage schedule. After
studying these Rules the Board is unpersuaded that they form the basis, in
combination, for sustaining the instant claim. The Organization as moving party
must also bear the burden of proof with respect to substantial evidence showing
when it is a question of any past practice violation. A search of the record
fails to produce such proof. There is insufficient evidence of probative value
in the record to warrant conclusion that the Carrier was in
contravention of
either Agreement Rules or past practice when it assigned the personnel it did to
build the structure in question on October 6-9, 1981. The claim cannot, therefore,
be sustained.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are respectively
Carrier and Employes within the meaning of the Railway Labor Act, as approved
June 21, 1934;
. That this Division of the Adjustment Board has jurisdiction over the -
dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
4ZO=X
Nancy J. -Executive Secretary
Dated at Chicago, Illinois, this 15th day of March 1985.