NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Locket Number CL-24496
W. S. Coleman, Referee
(Brotherhood of Railway, Airline and Steamship Clerks,
( Freight Handlers, Express and Station Employes
PARTIES TO DISPUTE:
(The Chesapeake and Ohio Railway Company
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood (OL-9555) that:
(a) Carrier violated Article 5 of the National Vacation Agreement
when they arbitrarily advanced the scheduled starting date of Clerk Henry Ramsey's
vacation from May 23, 1978 to May 20, 1978, and
(b) That Carrier shall now be required to allow Claimant eight (8)
hours pay at the punitive rate of $58.92 per day for the dates of May 27, 28,
and 29, 1978 in addition to other pay allowed for these dates as a result of
this violation.
OPINION OF BOARD: Claimant H. L. Ramsey held a regularly assigned position
of Crew Dispatcher on the 8:00 A.M. to 4:00 P. M. shift,
Saturday through Wednesday, with Thursdays and Fridays off. Claimant was
scheduled for one week's vacation beginning Tuesday, May 23, 1978, and concluding
on May 29, 1978. At the time this schedule was requested and approved, Claimant
was working a Tuesday through Saturday week, with Sunday and Monday off. Prior
to his vacation date, however, he was awarded the Crew Dispatcher job and his
days off changed to Thursday and Friday. This change in assignment and schedule
caused Claimant to request a change in his assigned vacation.
He requested that his vacation be deferred so that it would start on
May 17, 1978. Carrier reviewed his request and the vacation schedule of other
Crew Dispatchers and rescheduled Claimant's vacation to begin on May 20, rather
than on may 27, as he had requested, or May 23, as was previously approved.
Organization contends that Carrier was arbitrary in its assignment of
May 20 as Claimant's start date for vacation. It argues that if Carrier could
not honor Claimant's request for a change to May 17, it should have left his
vacation as it was scheduled (with the start date of May 23rd). It had no
right to unilaterally reschedule Claimant to start his vacation on May 20.
Carrier contends that due to the requirements of service, it had the right to
reschedule Claimant's vacation.
This Board has reviewed the record presented on this case and must
conclude the Carrier did not act in an arbitrary manner when it rescheduled
Claimant's vacation to meet the needs of the service in the Crew Dispatcher
Office. Article 5 gives Carrier certain latitude in assigning vacations, just
as it grants employes certain rights in regard to vacations. The rights
granted to Carrier, however, are that it can consider the needs of the service
when scheduling vacations. It must have proper coverage on critical jobs. The
record of this case does not contain any evidence to support Organization's
allegation that Carrier, by its actions, acted in an arbitrary fashion or
purposely set out to expand its authority under the Vacation Agreement through
this case.
Award Number 25374 Page 2
Docket Number CL-24496
c.i
FINDINGS: The Third Division of the Adjustment Board, upon the whole record and
all the evidence, finds and holds: . ;,
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are respectively
Carrier and Employes within the meaning of the Railway Labor Act, as approved June
21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT
BOARD
By
Order of Third
Division
Attest:
Nancy J. r - Executive Secretary