NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Docket Number MW-24648
W. S. Coleman, Referee
(Brotherhood of Maintenance of way artployes
PARTIES TO DISPUTE:
(Burlington Northern Railroad Company
( (former St. Louis-San Francisco Railway Company)
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Agreement was violated when, on September 2 and 24, 1980, five
(5) Track Department employes were used to perform Bridge and Building Department
cork on Bridges C589-4 and C590-8) (System File F-118401HWC 81-4-1B).
(2) The Agreement was also violated when, on January 5, 1981, Track
Department employes (Gang 304) were used to perform Bridge and Building Department
work on Bridge 52.5 (System File B-9221MWC 81-6-2).
(3) Because of the violation referred to in Part (1) hereof, furloughed
Bridge and Building Department employes R. C. Gann, D. R. Carter and C. J. Blake
each be allowed an equal proportionate share of the thirty-five (35) man-hours
expended by Track Department employes in performing the work referred to in Part
(1) hereof.
(4) Because of the violation referred to in Part (2) hereof, Track
Foreman M. 0. Naumann shall be allowed the difference between what he was paid at
the Track Forman's rate and what he should have been paid at the B&B Foreman's
rate and Trackmen C. B. Eaton, G. F. Bahr, G. E. Leutzinger, M. Xozma, T. R.
Fallert and L. J. Wi11et shall each be allowed the difference between what they
were paid at the trackman's rate and what they should have been paid at the B&B
Helper's rate for five (5) hours for January 5, 1981.
OPINION OF BOARD: On September 2 and 24, 1980, Carrier used a Foreman and four
Laborers (members of Track Gang 201) to spike-line rail on
Bridges C589-4 and C590-8. Each member worked a total of seven hours on both
bridges. The organization maintains that such work is reserved to Bridge and
Building Sub-department employes under Rule 29 of Article 3 and that furloughed
Bridge and Building Department employes Garin, Carter, and Blake should be allowed
an equal proportionate share of the thirty-five (35) man-hours expended.
Rule 29 reads as follows:
'Work on bridges, or that portion of bridges, which have wooden
substructures below the caps is work which belongs to the B&B Subdepartment. Steel bridge crane
bridge piling of any type.·
Award Number 25386 Page 2
locket Number MW-24648
On January 15, 1981, seven members of Track Gang 304 were used by Carrier
to spike-line rail on Bridge 52.5. They worked a total of five hours on the
project. The Organization contends that the Foreman (Naumann) and the trackmen
assigned to the gang (Claimants Eaton, Bahr, Leutzinger, Kozama, Fallert, and
Wi11et) performed duties of a B&B foreman and B&B helpers and should therefore be
compensated at the appropriate rates required by Rule 70 (a):
"(a) An employe corking on more than one class of work, on any day, will
be allowed the rate applicable to the character of work preponderating
for the day, except that when temporarily assigned by the proper officer
to lower rated positions, when such assignment is not brought about by a
reduction of force or request or fault of such employe, the rate of pay
will not be reduced.'
The Board has carefully reviewed the record of this case and must
conclude that both parts of the claim should be denied. Organization has failed to
demonstrate that, by tradition or by contract, the disputed work is work belonging
to bridgemen. At the same time, it does not refute, by citation or example,
Carrier's contention that spiking and lining rail on a bridge is work that has been
performed by both trackmen and bridgemen, as the need arose. Since Organization
has failed to carry its required burden in this
instance, we
shall deny the claim.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record and
all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are respectively
Carrier and Employes within the meaning of the Railway Labor Act, as approved June
21, 1934;
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the Agreement was not violated.
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
ATTEST
Nancy J. r - Executive Secretary
Dated at Chicago, Illinois, this 15th day of April 1985.