NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Locket Number MW-25124
Martin F. Scheinman, Referee
(Brotherhood of Maintenance of Way EYnployes
PARTIES TO DISPUTE:
(Escanaba and Lake Superior Railroad Company
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the agreement when it failed and refused to
properly compensate the employes assigned to the Section Gang headquartered at
Channing, Michigan for work performed in going to and from their work location
and assembly point prior to and continuous with their regular assigned work
period on November 2, 3, 4, 5, 6, 9, 10, 12 and 13, 1981 (System File ELST2808).
(2) The claim as presented by Assistant General Chairman F. M. Larson
on December 21, 1981 to Director Field Operations W. F. Drusch shall be allowed
as presented because said claim was not disallowed by Mr. W. F. Drusch in accordance
with Rule 52(al.
(3) As a consequence of either or both (1) and/or (2) above
"Mr. Jeff Vermulen, Social Security No. 388-52-0206, Mr.
James Helgren, Social Security No. 397-74-1308, Mr. Art
Burby, Social Security No. Unknown and Mr. Dennis Pepin,
Social Security No. Unknown, asking that each be compensated
at his respective overtime rate of pay for a total of
eleven (11) hours."
OPINION OF BOARD: The relevant facts of this claim are not in dispute. On
the dates of November 2, 3, 4, 5, 6, 9, 10, 12 and 13, 1981,
Carrier assigned Claimants to peform Section Gang work at Sidnau, Michigan.
Claimants had been regularly headquartered at Channing, Michigan.
By letter dated December 21, 1981, the Organization filed this claim.
In it the Organization contended that Carrier impermissibly changed Claimants'
regular designated assembly point. On February 19, 1982, the Organization
wrote another letter to Carrier, insisting that Carrier had failed to timely
respond to the initial claim, in violation of Rule 52(a) of the Agreement.
Carrier denied the Organization's claim by letter dated February 21,
1982. Thereafter, on April 25, 1982, the Organization appealed Carrier's denial.
On June 15, 1982, Carrier's highest designated officer rejected the Organization's
appeal. On March 14, 1983, the Organization appealed the claim to this Board
for adjudication.
The Organization contends that Carrier failed to timely respond to
its initial submission, in violation of Rule 52(a). It filed the original
claim on December 19, 1981. Carrier denied it on February 21, 1982, more than
sixty days thereafter. Rule 52(a) requires that claims be denied within sixty
days or they will be 'allowed as presented'. Thus, the Organization concludes
that the claim should be sustained on procedural grounds alone.
Award Number 25475 Page 2
Locket Number MW-25124
As to the merits, the organization asserts that Claimants were required
to assemble at Channing, Michigan one hour prior to their regular starting time
and one hour after their regular quitting time. As such, the Organization
contends, claimants were clearly entitled to eighteen hours' overtime in accordance
with Rules 27 and 33.
Carrier, on the other hand, asserts that it received the claim on
December 24, 1981. It denied the claim on February 21, 1982, fifty-nine days
later. Thus, Carrier argues that it complied with Rule 52(a).
On the merits, Carrier maintains that it has often verbally notified
employes of changes in their regular designated assembly point. Carrier insists
that it did so in this case. Accordingly, Carrier urges that it complied with
Rules 27 and 33 here. Therefore, it asks that the claim be rejected.
After carefully reviewing the record evidence, we are convinced that
the claim must be sustained on procedural grounds. The claim was initiated via
letter dated December 21, 1981. Carrier's defense that it was not received
until December 24, 1981 was never raised on the property. President J. Larkin
rejected the Organization's appeal via letter dated June 15, 1982. That letter
makes no reference to the Organization's contention that Carrier had defaulted
on the claim. Instead, it simply reiterates Carrier's position that it complied
with Rules 27 and 33.
It is axiomatic in railroad labor relations that arguments not raised
on the property cannot be considered by this Hoard. As was noted in Award No.
8484:
"...it is apparent that the Hoard has diligently protected
the parties ...in limiting the defenses imposed so that
there can be no enlargement - or in lay language, no
second look after the case is concluded on the property."
Here, by its letters of February 19, 1982, and April 25, 1982, the Organization
specifically argued that Carrier had defaulted on the claim, in violation of
Rule 52(a). Carrier never responded to this argument on the property. Thus,
it is barred from raising it for the first time before this Hoard. Accordingly,
and for the foregoing reasons, the claim must, in the language of Rule 52(a),
be allowed as presented.
FINDINGS: The Third Division of the Adjustment Hoard, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are respectively
Carrier and Employes within the meaning of the Railway Labor Act, as approved
June 21, 1934;
Award Number 25475 Page 3
Locket Number MW-25124
That this Division of the Adjustment Hoard has jurisdiction
over the dispute involved herein; and
That the Agreement was violated.
A
W
A R D
Claim sustained.
NATIONAL RAILROAD ADJUSTMENT HOARD
;Z0,
By Order of Third Division
Attest:
Nancy J er - Executive Secretary
I
Dated at Chicago, Illinois, this 23rd day of May 1985.