NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Locket Number MW-25273
Martin F. Scheinman, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(Consolidated Rail Corporation
(former Lehigh Valley Railroad Company)
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The disciplinary demotion of Foreman A. R. Holmes for alleged
falsification of 'monthly switch inspection report submitted September 24, 1980'
and alleged ·failure to properly perform assigned duties as foreman in 'that you
failed to make proper inspection of A&I switch in Ithaca Yard' was without just
and sufficient cause and on the basis of unproven charges (System Locket 668).
(2) Mr. A. R. Holmes, seniority as foreman be restored and unimpaired
and he shall be compensated for all wage loss suffered beginning November 7, 1980
until he is returned to work as a foreman with seniority as such unimpaired.
OPINION OF BOARD: At the time this dispute arose, Claimant A. R. Holmes, was
employed as an Area Foreman, assigned to carrier's Ithaca Yard
in Ithaca, New York.
On
September 24, 1980, Claimant made his regular monthly
inspection of the A & I Switch at the North End of Ithaca Yard. He recorded the
condition of the switch to 'good' on his inspection report.
On
October 21, 1980, three cars in a train derailed at the South end of
the switch, allegedly due to wide gauge account of timber condition in that area.
As a result of this incident, Claimant was ordered to appear for a
hearing in
connection with
the following charge:
·Falsifying monthly switch inspection report submitted
September 24, 1980 which indicated A & I switch was in
good working condition. Also failure to properly perform assigned duties as foreman in that you fail
make proper inspection of A & I switch in Ithaca Yard
which resulted in derailment of three cars of WSIT-1
on October 21, 1980 due to wide gauge account of timber
condition.
The hearing was held on November 3, 1980. Subsequently, Carrier notified
Claimant that he had been disqualified in all capacities as Foreman.
The Organization timely protested Claimant's disqualification. Thereafter,
the claim was handled in the usual manner on the property. It is now before this
Board for adjudication.
Award Number 25480 Page 2
Locket Number MW-25273
The Organization contends that the timber condition on September 24,
1980, did not warrant special citation or attention. It points out that Track
Supervisor R. L. Rudloff did not note any evidence of new movement in the area in
question from September 24, 1980, to October 21, 1980. Thus, the Organization
reasons that both Claimant and Supervisor Rudloff believed the area to be in
acceptable condition.
In the Organization's view, the A & I switch condition worsened by the
large amount of tonnage traveling over it daily. Therefore, the Organization
contends, the condition of the A & I switch deteriorated after September 24,
1980, so as to cause the derailment of October 21, 1980.
Under these circumstances, the Organization concludes that the Claimant
filed a fair and accurate report. Accordingly, it asks that the claim be
sustained.
Carrier, on the other hand, asserts that Claimant was properly found
guilty of filing a defective switch report. It points out that Supervisor of
Track S. C. May testified that the poor track condition must have existed for
quite some time prior to September 24·. In Carrier's view, -Assistant Supervisor
Rudloff corroborated this testimony. Thus, Carrier argues that the inspection
T
report of September 24, 1980, was false in that it reported the condition of the
A & 1 Switch as "good'. Under these circumstances, Carrier concludes, disqualificatic
is a penalty. Thus, Carrier asks that the claim be rejected.
A review of the record evidence convinces us that the claim must be
sustained in part. Claimant is charged with ·falsifying· his switch report of
September 24, 1980. However, nothing in the record suggests that Claimant
deliberately entered a false statement as to the condition of the A & I switch.
At most, Claimant may have failed to accurately perceive the deteriorated
condition of the area in question.
Under these circumstances, Claimant's report of September 24, 1980, was
negligently made. However, it was not falsified.
In our view, Claimant should be restored to his position as an Area
Foreman and his restoration should become effective with the date of this Award.
FINDINGS: The Third Division of the Adjustment Hoard, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are respectively
Carrier and Employes within the meaning of the Railway Labor Act, as approved
June 21, 1934;
Award Number 25480 Page 3
Locket Number MW-25273
That this Division of the Adjustment Board has jurisdiction over the
dispute involved herein; and
That the discipline was excessive.
A W A R D
Claim sustained in accordance with the Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attest:
Nancy J pier - Bxecutive Secretary
Dated at Chicago, IlFlinois, this 23rd day of may 1985.