NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Dbcket Number SG-25813
James Robert Cox, Referee
(Brotherhood of Railroad Signalmen
PARTIES TO DISPUTE:
(Missouri Pacific Railroad Company
STATEMENT OF CLAIM: Claim of the General Committee of the Brotherhood of
Railroad Signalmen on the Missouri Pacific Railroad
Company on behalf of acting Signal Pbreman R. D. Gatewood, Signalmen H. R.
Thatcher and L. L. Barnes that:
(al Carrier violated the May 1, 1964 Signalmen's Agreement, as
amended, particularly the discipline Rule 700, when on August 16, 1983, 12:01
a. m. , claimants were suspended from the service of the Missouri Pacific
Railroad Company for thirty (30) days without just and sufficient cause and
on the basis of unproven charges either before or during an investigation
held August 11, 1983, at Fbrt Worth, Texas, resulting in claimants receiving
discipline notices number 1 7-4-40 (A), (B) and (C) advising them that their
records, as of August 15, 1983, had been assessed with thirty (30) days
Actual Suspension for their alleged failure to properly perform their duties,
resulting in damage to Bridge 1592 by fire, July 27, 1983, and their alleged
violation of Rules and Regulations of the M of W and Structures, General
Rules A, C, N (2).
(b) Carrier should now be required to make claimants whole for all
lost wages and benefits beginning August 16, 1983 and continue through
September 14, 1983, including overtime worked by other members of Signal Gang
1373 during that period, as consequence of the violation. (Carrier file: K
22-5-9661
OPINION OF BC14RD: The Organization contends that Claimants were improperly
suspended for 30 days without just cause for alleged
failure to properly perform their duties July 27, 1983. On that date they
had been working on rails which cross a wooden bridge, installing cadwld
bonds during the afternoon, leaving this assignment at 4:00 p. m. The last
train over the bridge had passed at approximately 11:30 a.m.
A fire was reported on the bridge at 6:00 p. m. and subsequent
investigation established two hot spots adjacent to areas where Claimants had
been welding. There was slag from welding the bonds on top of the tie plates
in areas where the bond wires had been installed.
The bond wires applied to the rail joints are thermal welded and
applied by grinding the face of the rail, then using a bonding mold to weld
the bonds to the rail. A powder is poured into a mold and ignited with a
striker to produce sufficient heat, welding the bond wire to the rail. The
flare-up of the bonding equipment produces considerable sparks as well as
slag. The sparks and hot slag constitute a fire hazard on the wood bridge.
Award Number 25599 Page 2
locket Number SG-25813
One hundred fifty bridge ties burned and approximately nine rail
links had to be replaced. The evidence showed that the fire had originated
from the hot slag that had fallen m to the ties. Discipline was imposed for
failure of Claimants to take all necessary safety precautions to prevent a
fire. The bridge was open deck pile truss timber with some concrete in the
center portion.
Claimants testified that, when they finished work at 4:00 p.m.,
they walked the bridge to inspect it in order to be sure that fire was not
present, looking all around the bridge without finding any evidence of fire.
One Claimant testified that he, in the course of his bonding work, used water
on areas where they had seen smoke. The Carrier states that "if Claimants
had properly followed Company rules, all sparks would have been extinguished
and the slag metal cooled."
The record reflects that Claimants checked the bridge before
leaving their jobs July 27th. The Board also recognizes that employes are
not insurers and cannot properly be subject to discipline unless their
conduct results in culpable job performance. However, welding on a wooden
bridge calls for a high degree of care and attention to fire prevention. The
evidence established that not ony did the fire originate in the area where
Claimants had been working with the welding materials, but that there was no
supervening cause which would relieve them from their responsibility to see
that the debris on the rails left from their welding work was in a noncombustible state. Since a fir
area, it dermnstrates that they were negligent in failing to properly
extinguish material that had become combustible as the result of their work.
The nexus between their failure to use proper care in the performance of
their work and the resulting fire has been established.
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
That the Agreement was not violated.
Award Number 25599 Page 3
Docket Number SG-25813
A W A R D
Claim denied.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order o f Third Division
Attest:
Nanc4;iicxe~ 30 y J - Executive Secretary
Dated at Chicago, Illinois, this 22nd day of August 1985.