NATIONAL RAILROAD ADJUSTMENT BOARD
THIRD DIVISION Locket Number MW-25679
George S. Roukis, Referee
(Brotherhood of Maintenance of Way Employes
PARTIES TO DISPUTE:
(The Denver and Rio Grande Western Railroad Company
STATEMENT OF CLAIM: Claim of the System Committee of the Brotherhood that:
(1) The Carrier violated the Agreement when it assigned excavation
work in connection with a grade widening project at Glenwood Canyon beginning
July 6, 1982 to outside forces (System File D-33-82/MW-1-83).
(2) Because of the aforesaid violation, Work Equipment Operators
D. Drake, L. Moore, L. Bartlett, J. Matlock and L. Ebaugh shall each be
allowed pay at their respective rates for an equal proportionate share of the
total number of man-hours expended by outside forces beginning July 6, 1982.
OPINION OF BOARD: The essential facts in this dispute are set forth as
follows:
Beginning on July 6, 1982, Carrier assigned outside forces to perform
excavation work in connection with a grade widening project at Glenwood Canyon
between Allen and Shoshone sidings. It is the Organizations position that
work of this character has been traditionally performed by Maintenance of Way
and Structures Department employes using Carrier owned equipment and said
work is reserved to these forces. Specifically, it asserts that Carrier
violated Rules 1, 2, 3 and 4 of the Controlling Agreement, and particularly,
Article IV of the May 17, 1968 National Agreement, and the Letter of Agreement,
dated December 11, 1981. Article IV - Contracting Out, which is pertinent
herein, reads:
"Article IV - Contracting Out
"In the event a carrier plans to contract out work
within the scope of the applicable schedule agreement,
the carrier shall notify the General Chairman of the
organization involved in writing as far in advance of
the date of the contracting transaction as is practicable and in any event not less th
"If the General Chairman, or his representative, requests
a meeting to discuss matters relating to the said contracting
transaction, the designated representative of the carrier shall
promptly meet with him for that purpose. Said carrier and
organization representative shall make a good faith attempt
to reach an understanding concerning said contracting, but if
no understanding is reached the carrier may nevertheless
proceed with said contracting, and the organization may file
and progress claims in connection therewith.
Award Number 25677 Page 2
Locket Number MW-25679
"Nothing in this Article IV shall affect the existing
rights of either party in connection with contracting out.
Its purpose is to require the carrier to give advance
notice and, if requested, to meet with the General Chairman or his representative to discuss and if
reach an understanding in connection therewith.
"Existing rules with respect to contracting out on
individual properties may be retained in their entirety
in lieu of this rule by an organization giving written
notice to the carrier involved at any time within 90
days after the date of this agreement."
A pertinent portion of the December 11, 1981 Letter of Agreement
states:
"The parties jointly reaffirm the intent of Article IV
of the May 17, 1968 Agreement that advance notice requirements be strictly adhered to and encourage
locally to take advantage of the good faith discussions
provided for to reconcile any differences. In the interest
of improving communications between the parties on subcontracting, the advance notices shall identif
to be contracted and the reasons therefor."
The Organization avers that while Carrier notified the General Chairman of
its (Carrier's) intent to contract out work by letter, dated April 27, 1982,
the written notice did not comply with either the letter or spirit of Article
IV. In effect, it contends the notice did not identify the specific location
of the work, the type of equipment needed, the work's commencement date or
the reasons for contracting out the work.
Carrier argues that it complied with Article IV since it notified
the General Chairman of its
intention to
contract out the disputed work by
letter, dated April 27, 1982, and moreover, it supplied the General chairman
at a mutually scheduled conference with the particulars on each of the ten
(10) locations mentioned in the April 27, 1982 notice. It maintains that the
General Chairman was fully apprised of the prospective work details and the
operational reasons for contracting out the work. It further contends that
the claim appealed to the Division was procedurally defective since the
wording differed from the claim initially presented on the property, and
requests that it be peremptorily dismissed.
On substantive grounds, it asserts that the Organization has never
proven that the work of constructing and preparing grades is exclusively
reserved to the Maintenance of Way Department and observes that it does not
have the necessary equipment to construct new grades of major magnitude. It
avers that time is of the essence on these types of projects and it needed
its own forces to perform regular maintenance duties.
Award Number 25677 Page 3
Locket Number MW-25679
In our review of this case, we concur with the Organization's
position. Firstly, as to the procedural questions raised by the Carrier, we
find nothing in the record of the claim handling that would indicate a
violation of the timeliness requirements, nor a correlative finding that the
claim was materially changed so as to constitute a new substantive grievance.
Its wording did not prejudice Carrier's ability to respond to the asserted
violation nor effectively present it with a new dispute.
Secondly, we agree with the Organization that Carrier failed to
comply with the explicit requirements of Article IV since the notice of April
27, 1982 was vague and
inconsistent with
the specific requirements of the
December 11, 1981 Letter of Agreement. In effect, the advance notice was
tantamount to a general blanket notice and not the type of notice contemplated by the Agreement.
In Third Division Award Nos. 25141 and 25103 involving the same
basic issue, we upheld the Organization's position on the rationale that a
blanket notice fell short of meeting the relevant notice requirements. In
the case herein, the April 27, 1982 advanced notice was not fully developed,
and as such, was not consistent with the manifest intent and requirements of
Article IV of the May 17, 1968 National Agreement and the December 11, 1981
Letter of Agreement. In view of this violation and in accordance with our
prior rulings we will sustain the claim as follows:
"Claim for each named claimant is sustained for wage loss suffered,
i.e., the named claimant's proportionate share of time when added to his
straight-time compensable time for period involved shall be limited so as not
to exceed the total of his normal compensable time."
FINDINGS: The Third Division of the Adjustment Board, upon the whole record
and all the evidence, finds and holds:
That the parties waived oral hearing;
That the Carrier and the Employes involved in this dispute are
respectively Carrier and Employes within the meaning of the Railway Labor
Act, as approved June 21, 1934;
That this Division of the Adjustment Board has jurisdiction over
the dispute involved herein; and
That the Agreement was violated.
Award Number 25677 Page 4
Locket Number MW-25679
A W A R D
Claim sustained in accordance with the Opinion.
NATIONAL RAILROAD ADJUSTMENT BOARD
By Order of Third Division
Attes4~Zo~- 0000'
t:
Nancy J r - Executive Secretary
Dated at Chicago, Illinois, this 28th day of October 1985.